Powers v. City of Yonkers
Opinion of the Court
The agreement upon th'e part of the contractor to complete the work within the fixed time is fully explained. There were difficulties in the way of a speedy execution of the agreement in consequence of claims made that the proposed work interfered with private rights, and the time was extended not only by actual permission but by the giving of certificates for' work long after the time to complete had passed.
The answer set up no improper execution beyond the fact that the work was not actively continued. The city rescinded the contract only upon the ground
The evidence tending to show defects was properly stricken out, as not within the issue made.
The judgment should therefore be affirmed with costs.
Pratt, J., concurs; Dykman, J., not sitting.