Mansfield v. New York Central & Hudson R. R. R. Co.
Opinion of the Court
contractors were entitled to have the foundation ready ■at least so far as to enable the contractor to prosecute the work to the utmost advantage and economy. It was not a waiver of their rights in respect to commencing the work under a protest that the contractors would waive no rights secured to them under the contract. Mansfield v. New York Central, etc., 102 N. Y., 205; 1 N. Y. State Rep., 390.
The law of the case being thus settled, the question was left to the jury to determine whether or not the defendant’s engineer gave the notice called for by the contract. When the foundation was ready to begin the superstructure, the foundations were actually then in such a condition as to enable the contractors to go on with the work with the utmost advantage and economy. The jury found they were not. By the contract $500 per day in addition to the ■contract price was to be allowed the contractors for every day less than five months it took them to complete the elevator. The jury have found that the ■contractors could have done the work in thirty days less than five months, and for this they allowed $15,000. If this sum had been in fact earned by a conpletion of the same in a term less by the thirty days the money would have been payable immediately.
With the finding of the jury it was legally so payable at the end of five months from the commencement of the contract. Compensation for the
Dykman and Pratt, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.