Sullivan v. New York & Rosendale Cement Co.
Opinion of the Court
If it were a new question, I should think that a defect of parties plaintiff might in all cases be set up by demurrer or answer. Either form of pleading sufficiently apprises the plaintiff of the defect; and an answer is less dilatory. But it seems to be settled that, if such defect appear in the complaint, the objection must be taken by demurrer. Zabriskie v. Smith, 13 N. Y. 322, and other cases. The question, then, comes up, does the defect appear in the complaint where there is not a distinct averment that the omitted party is living at the commencement of the action? On the whole, considering the case above cited, and Eaton v. Balcom, 33 How. Pr. 80, and Sanders v. Yonkers, 63 N. Y. 489, we conclude that an allegation in the complaint that the omitted plaintiff was living at the time of the action is not needed to make the complaint demurrable. Therefore this defendant could have demurred, and cannot set up the defect by answer. We come to this result reluctantly, and follow authorities.
The action is for damages on the ground that defendant prevented plaintiffs from fully performing a written contract between the parties for excavating a tunnel for defendant. Sullivan, Foley, Enright, and Bradley were the original parties. Buchley signed subsequently. Bradley quit working October 1st; Enright, November 25th. About December 17th work was suspended. The plaintiffs claim that by their consent the work was suspended two weeks; that after that time they were ready and offered to go on, but were prevented by defendant. On the 11th of February, a formal notice was sent by plaintiffs, Sullivan, Foley, and Buckley, to defendant that they were ready, and desired to know whether they were to run the tunnel further. On the 27th of February, defendant demanded by a letter that they should go to work. To this they replied March 2d that they would go to work if they were paid damages for the stoppage of the work. Foley had obtained employment with another company, February 15th; Buckley, the 8th. Sullivan went to work by the day for defendant, the 15th. The court submitted to the jury the
The defendant asked the court to charge that the plaintiffs would have had a right to go to work upon the tunnel when notified to do so, and hold defendant for damages caused by delay. The court refused. Perhaps, the request meant that the plaintiffs were bound to go to work when thus notified for whether they had a right to do so or not was not in question. But we must take this refusal in connection with the previous charge, since it is well settled that, when a judge has properly charged the law, he is not required to repeat the same thing, in substance, in order to comply with a request which may contain different language. The judge has previously charged that if the defendant’s version was right, and they gave the plaintiffs the opportunity of resuming when general work was resumed, and the plaintiffs refused, then plaintiffs could not recover. If the suspension was only for two weeks, then it could not be claimed that, at the end of that time, the defendant permitted plaintiffs to go to work. That it was the duty of plaintiffs not to be idle, but to engage in other work, when prevented from performing this contract is. quite true. When they had engaged in other work, then we cannot say that they were bound to go back to this contract, though requested, if they had waited a reasonable time. There seems to have been no claim by defendant that the damage was mitigated by any amount earned by plaintiffs in other work; so that the question whether that rule of mitigation would apply here does not arise. The plaintiffs could not go on with the work against defendant’s wishes, as sufficiently appears by the contract and the proof. We discover no error in the trial. Judgment affirmed, with costs.
Ingalls and Landon, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.