Smith v. Mayor of City of New York
Opinion of the Court
The action was brought to recover sums paid by plaintiffs for two assessments for sewers in the Boulevard. The first was an assesment for sewers between 92d and 106th streets, and the second an assessment for sewers between 61st and 77th streets. By the judgment the plaintiffs recovered the first, but were nonsuited as to the second; and it is from the refusal to allow a recovery for the second assessment paid that the plaintiffs appeal, while the defendant appeals from so much of the judgment as allows any recovery.
Questions involving assessments for the improvement of the Boulevard have been before this court and the court of appeals so many times that it is unnecessary to recite the facts at length, it being sufficient to state only those that present the questions raised upon this appeal. Between the years 1872 and 1876 the construction of the Boulevard between 59th and 154th streets was in progress by men employed by day’s work, and not by contract. This construction included, not only the regulating and grading of the
In Be Blodgett, supra, it is said:
“We have recently considered the meaning of the phrase ‘work in progress,’ as used in the charter, and the scope and purpose of the exception thereby declared. In re Weil, 83 N. Y. 543. In that case we expressed the opinion that the purpose of the exception was to avoid the evil and complication arising from an application of the contract system to work already commenced and moving towards completion in a different manner, and was descriptive of cases where the city was already committed to a specific mode of doing the work, and could not change the system without complication or confusion. * * * The exception of the charter had an evident purpose and aim. The general and dominant idea was to do all of the city work by the contract system, and that, only, was intended to be exempted which was already begun, which was ‘in progress’ on a system and in a mode of its own, and which could not be interfered with unless at the peril of evil consequences.”
VAN BRUNT, P. J., concurs.
Dissenting Opinion
I concur in that part of the prevailing opinion which sustains the recovery for $2,844.85, but dissent from that portion which denies the plaintiffs’ right to recover $7,371.83, the amount of the taxes collected, with interest, on account of the work done on the second section between 61st and 72d streets.
Section 91, c. 335, Laws 1873, provides:
“Whenever any work is necessary to be done to complete or perfect a particular job, or any supply is needful for any particular purpose, which work and job is to be undertaken or supply furnished for the corporation, and the several parts of the said work or supply shall together involve the expenditure of more than one thousand dollars, the same shall be by contract, under such regulations concerning it as shall be established by ordinance of the common council, excepting such works now in progress as are authorized by law or ordinance to be done otherwise than by contract. ”
The exception in italics relates to particular works in progress April 30,1873, when the statute took effect, which had then been authorized by law or ordinance to be done otherwise than by contract. Two conditions must have existed April 30, 1873, to bring the Boulevard sewer within the exception: (1) The work must have been in progress; and (2) it must have been “authorized by law or ordinance to be done otherwise than by contract.” Our attention has not been called to any law or ordinance authorizing this particular work to be done otherwise than by contract. On the contrary, the undisputed evidence is that there was no such ordinance, and so the work on this sewer is not within the exception. Laws 1870, c. 137, § 104; In re Robbins, 82 N. Y. 131. Notwithstanding the statute, and the fact that there was no law or ordinance authorizing the construction of this sewer otherwise than by contract, the commissioner of public works constructed the whole of it by day’s work. This sewer is about five miles long, divided into five sections, numbered from 1 to 5, every
Case-law data current through December 31, 2025. Source: CourtListener bulk data.