Lewis v. Yagel
Opinion of the Court
In tbe complaint as a first cause of action it was alleged that tbe plaintiffs were co-partners; that on tbe 2d day of June, 1886, they entered into a written agreement with tbe defendant to construct two three-story stores, except party wails, plumbing and painting, and to furnish tbe materials therefor for the sum of $1,100, part of which was to be paid in installments as tbe work progressed, and at completion, upon tbe production of tbe architect’s certificate that tbe work was completed in accordance with tbe contract, tbe remainder was to be paid; that they performed such work on tlieir part, and tbe stores were completed and accepted by tbe defendant; that she paid them tbe sum of $1,368.85, leaving unpaid $311.35.
Eor a second cause of action it was alleged that on tbe 5th day of
For a third cause of action the plaintiffs allege that between the 2d day of June, 1886, and the 10th day of December of the same, year, the defendant became indebted to them in the sum of $9',494.26-for work, labor and services rendered and performed and for materials furnished at her request, and for which she agreed to pay that sum; that she has paid thereon the sum of $8,595.91, leaving a. balance unpaid of $898.35, with interest from December 11, 1886, for which sum judgment was demanded.
The defendant set up in her answer that all the work performed, and materials furnished by the plaintiffs, were perfoi-med and furnished under written contracts which were entered into by and between the parties, and copies of which were made a part of the answer; that the contracts were not fulfilled by the plaintiffs, and by reason thereof she suffered damage to an amount greatly in excess of the amount claimed by them, which was set up as an offset or counterclaim. It was also alleged that she had paid the plaintiffs; more than was due upon the contracts between them; that she was-not indebted to them in any sum whatever; that certain conditions, precedent to the plaintiffs’ right of recovery were not performed by them; that the second contract, so far as it related to the area wall,, was obtained from her by the fraud and misrepresentations of the plaintiffs, and that it was not performed by them. The answer likewise contained a denial of all the allegations of the complaint not admitted by the answer, and contained allegations that the plaintiffs had been fully paid; that the contracts between the parties had not been either actually or substantially performed by the plaintiffs, and that the defendant had sustained material damage by reason thereof, and demanded judgment for the amount of such damage.
The plaintiffs replied to the defendant’s answer, denying each and every allegation thereof, and alleging that each and all of the changes which were made in the construction of the buildings mentioned in the complaint and answer herein, so far as the same differed from the plans and specifications thereof, were made at the request of the
The defendant served an amended answer wherein it was averred that the plaintiffs did not perform the work under the second contract between the parties according to the contract, plans and specifications, and omitted to do the same in a good, proper and workmanlike manner; that they omitted to put in ventilating pipes, and to vent the traps to the water closets and sinks according to the plans and specifications, and as required by the contract for such plumbing ; that they omitted to construct the area wall in the same manner as the area wall of tlie First National Bank building mentioned in the contract; that the same was constructed in an improper, imperfect and unsubstantial manner, and that she sustained damage thereby to the amount of §500, which was set up as an offset or counterclaim in the action.
The plaintiffs’ reply to'such amended answer denied each and every allegation contained therein respecting the alleged counterclaims, and also alleged that each and all of the alterations and changes or omissions which were made in the work and materials mentioned in the amended answer, so far as the same differed from the plans and specifications, were made at the request of the defendant, with her knowledge or consent, and under the supervision and direction of her architect.
That the work performed and materials furnished, for which this action was brought, were performed and furnished under the two written contracts between the parties, and in pursuance of their provisions, there can be no manner of doubt. Therefore, to a proper understanding of the questions involved on this appeal, it becomes necessary to examine some of the provisions contained in the contracts between the parties.
The first contract between them, which was made June 2, 1886, provided that the plaintiffs should erect, finish and deliver in .a true, perfect and thoroughly workmanlike manner, the building mentioned, except plumbing and painting, agreeably to the plans, drawings and specifications referred to, under the direction of Blend, who was an architect, the plaintiffs to furnish all the labor and materials, and to be paid'therefor the sum of $7,700, which the defendant agreed to pay in the manner stated in the contract.
It contained the further provision that in case of dispute as to the value of extra work or work omitted, the same should be “ valued ” by two competent persons, one employed by the owner, or her agent, and the other by' the contractor, and they should have the power to name an umpire whose decision should be binding on all the parties. By the contract the last payment was to be made when the building was “ all ” completed, and the drawings and specifications returned to the architect, provided that in each case of payment a certificate should be obtained- from, and signed by, the architect to the effect that the work was done in strict accordance with the drawings and specifications, and that he considered the payment properly due, the certificate, however, in no way lessening the total and final responsibility of the plaintiffs, and the contract provided further that when the work was “ all ” completed, a certificate should be obtained by the plaintiffs from the clerk of the office where liens are recorded, and signed and sealed by said clerk, that he had fully examined the records, and found no liens or claims recorded against said work, or on account of the plaintiffs. All ceilings were to be seven-eighths of an inch thick instead of one-lialf of an inch, as mentioned in the specifications, and the floors in the third story were to be one and one-eighth inches in thickness instead of the thickness mentioned therein. The plaintiffs were to take out the sub-cellar windows and doors, and put in stone work in their place, and two small windows, as the owner should direct.
The drawings and specifications were made a part of the contract. In the sjDecifications it was provided that the work was to be executed in the best and most substantial and thoroughly workmanlike man
The foregoing is the substance of some of the provisions of the contract between the parties, and perhaps all to which we need refer to a proper understanding of the questions involved on this appeal.
The evidence of the defendant was to the effect that a portion of the work on this building was sub-let without the written consent of the owner ; that there was no hand rail along the stairway; that there was not a ventilating pipe in the building; that the two wells mentioned in the contract were not driven; that there were no arches over the doors in the basement; that the plastering did not extend down to the floor as required by the contract; that there was but one course of bridging of the joists where the contract required two; that the area wall was not built in accordance with the contract ; that no curb was put down as required; that the plastering was improperly done and not according to the provisions of the contract ; that the building was not of the height called for by the plan; that the wall was not laid level, but the joists were blocked up with chips and pieces of wood; that a portion of the ornamental brick on the arches in front of the building was left out and plain brick substituted; that the brick work did not fit closely to the window frames; that none of the walls were plastered where the wainscoting was put on; that the mortar which was used for the walls was poor and improperly made, and that the walls were in no respect in accordance with the contract; that there were no clean-outs in .the drain as required; that the joists were not placed sixteen inches from center to center as required, but that they were in many instances from eighteen to nineteen inches from center to center; that one door was omitted in the division wall in the basement; that the lumber used in the ceilings, wainscotings and for finishing the building was Norway pine instead of clear white pine; that there were fifty feet of partition omitted in the basement; that the wall plates were hemlock instead of oak; that some of the trussing over
"While there is a conflict in the evidence as to many of the omissions and changes claimed by the defendant, yet there are numerous instances where the undisputed evidence shows that the plaintiffs have not performed the contract according to its terms and specifications. A careful study of the evidence renders it extremely difficult to discover how it could properly be found that there was a substantial performance of their contract by the plaintiffs.
While the rule relating to substantial compliance with the terms of a building contract may have been by the later decisions some
As bearing upon the question as to whether the omissions of the the plaintiffs in this case were substantial, or merely technical and unimportant, it may be proper to consider the evidence as to the value of some of the work and materials omitted, and the amount it would cost to make the building conform to the provisions of the contract. The extra work for which the plaintiffs were allowed, and for which no estimate in writing was made or submitted by the contractor to the architect and owner and their signatures obtained thereto, amounted to the sum of $253.14. The hand rail and brackets omitted would have cost $16.20. The ventilating flues omitted would have cost $112.72 if put in during the erection of the building ; after its completion, $255.75. The wells omitted would have cost $85 at the time, and now $100. The arches over the doors
The foregoing statement is based upon the evidence of the defendant as to the work omitted, its cost and the difference in the value between the materials and work as furnished, and that called for by the contract. It should, however, be stated that while many of the omissions referred to are conceded by the plaintiffs, their evidence as to the value of the work and materials omitted, and the difference between that furnished and agreed to be furnished varies very essentially from that of the defendant. As to many of the particulars mentioned, it may, I think, be safely said that the question whether the changes and omissions occurred, or were, of the character and extent claimed by the defendant, was a question of fact to be determined by the referee. There are, however, numerous instances in which there is no dispute as to the fact that the building was not. constructed in compliance with the contract between the parties, and that, by reason of the omissions or changes made in the materials and manner of construction, the contractors were required to expend a much less sum than it would have cost them to build according to the provisions of the contract. As has already been intimated, it is. extremely difficult to see how, under the circumstances of this case,, and in view of the character and extent of the omissions and failures-to perform the contract as shown by the evidence, it can fairly be said that there was a substantial performance of the contract by the plaintiffs. It may be, however, that the question was one of fact, and that the finding of the referee is sufficiently sustained by the evidence to be upheld.
If, however, it were to be held that there was a substantial performance of the contract, the questions as to whether the plaintiffs were properly allowed for the extra work which they performed for the defendant, and whether the defendant was allowed a fair and reasonable valuation for the differences which should have been deducted from the amount of the contract price by reason of the changes and omissions referred to, must still be determined. As we have seen, the contract provided that no work should be considered as
This brings us to the question Avhether the defendant was allowed ■a fair and reasonable valuation for the differences which should have been deducted under that part of the contract which provides that where changes were made, the difference should be added to or deducted from the amount of the contract, as the ease might be, by a reasonable and fair valuation. It seems impossible to read the evidence in this case without concluding that the defendant has not been allowed the deductions to which she was fairly entitled under this provision. As already pointed out, the omissions to perform the labor and furnish the materials in accordance with the contract
It may be said that these changes were made with the consent of the architect or the defendant, and, hence, that no such allowances should be made. We doubt if the architect had the right to permit such changes without the consent of the defendant, and feel confident that he did not and could not so change the contract as to deprive the defendant of the benefit of the provision which entitled her to such deductions. (Fitzgerald v. Moran, 141 N. Y. 419.) An examination of the proof bearing upon this question renders it quite manifest that the defendant did not consent to the changes and omissions, upon any agreement, or with the understanding, that she should not have the benefit of the provision in the contract which allowed deductions therefor. We find the evidence insufficient to show any such consent or any waiver of her rights under this provision. The evidence shows that the architect was a subcontractor under the plaintiffs, and also tends to show quite plainly that he did not attend to or guard the interests of the defendant
The learned referee has found that the value of the building as completed was equal to the value it would have had if constructed precisely as called for by the contract and specifications. This finding, as well as the rulings upon the trial, seem to indicate that the referee was of the opinion that if the plaintiffs furnished a building as useful or of equal money value witli the one called for by the contract, they were entitled to recover their full compensation therefor without regard to the provisions of the contract • under which it was to be constructed. In this we think he erred. The defendant was entitled to have her contract at least fairly if not strictly performed.
The referee also found that the defendant, about the first of December, duly accepted the building, having before that time taken possession of a portion of it. We think this finding cannot be sustained. The evidence renders it quite clear that there was never any acceptance of the building by the defendant as in full performance of the contract between her and the plaintiffs.
There was an issue between the parties as to one payment of $500. The defendant claimed that she paid the plaintiffs or the architect, who was their agent, $500 in cash November twenty-seventh, and paid an equal amount on November twenty-ninth by the check of her husband. That _ the plaintiffs received the check is admitted. On the trial the defendant produced a receipt, dated November twenty-seventh, for $500, signed by Blend for the plaintiffs. They contended that the receipt was given for the payment made by the check dated November twenty-ninth, and that no payment in cash was made on the twenty-seventh as was claimed by the defendant, but that the check was in fact given November twenty-seventh, and that the receipt was dated on the day the check was received. The defendant’s witnesses testified that the check was given on the day of its date, and not on the twenty-seventh, as claimed by the plaintiffs. The weight of the evidence upon this
On the trial the following stipulation was made and entered in the minutes of the referee: “ It is stipulated that the referee may, at his convenience, at any time before the close of the testimony in this case, or before the case is finally submitted, take with him a person of his own selection, and make an examination of the building in question; and that for the purposes of his decision in this case, he may take into consideration what he discovers in making the said inspection; but this arrangement is not to be deemed as limiting either party in the further testimony which they shall give upon the trial of this action ; also, that the referee shall make the inspection in such manner, and using such papers in connection therewith, as he shall deem necessary and proper, each party to pay one-half of the expense of the person whom the referee may select, and the expense of such person accompanying the referee shall be paid one-half by each party, to be taxed in with the referee’s fees.”
The referee, when he made his report, referred to such stipulation and his proceedings under it, as follows : “ This action having been referred to me to hear and determine, and having heard the proofs and allegations of the respective parties, and stipulation having been made in open court before the close of the testimony, as
The inquiries referred to by the referee in his report, were as follows:
"Mr. Murphy, builder, etc.:
“ In pursuance of stipulation, made by the above parties in the above cause, I desire you to examine the Yagel building in Oneonta, N. Y., with reference to the following points:
“ 1. The walls: rear wall, central wall and the area wall, this last being wall under flagging in front of^ building, and between building and curb. In this, I want your examination to be, reference to quality of stone and brick used, as to construction, and as to whether the rear or middle wall has settled, and if they have, state .the cause.
“ 2. As to blocks or blocking under floor joists, if found, state extent, and what is used, why used, and effect.
“ 3. Plastering: how many coats, whether properly put on and material making plaster.
“4. What is the difference in value, if any, in the Norway pine used, between that and pine called for by building contract ? What is the effect of its use in the vame of the building as completed I Examine contract and specifications, and then, from your examination of building, state whether in the construction of the building ■and the materials, has there been a substantial compliance with the contract. If there has been a material variation in the construction*355 of tlie building from that provided in tbe contract, is tbe bunding, as it stands, better or worse by reason of it % What would this building have been worth December 11th, 1886, if built as provided for in the contract and specifications ? What was it worth on that day, built as it was ? Please answer the foregoing in writing.
“ February 25, 1892. . W. 0. LAMONT.”
In compliance with this request, Murphy made, signed and sent to the referee the following paper :
“To Win. 0. LaMont, March 24th, 1892. Prom W. H. Murphy, as inspector on the Yagel block in Oneonta, N. Y. I have examined the same and find it: 1. I find that the foundation in under basement as a partition wall has cracked, and my best judgment is that the same has been undermined by excavation since the erection of the building, and allows the water to flow to and under the said wall, and comes from the embankment under basement floor causing the same;
“ 2. The rear wall shows a crack to the end of iron girder; is •caused by the weather, expansion and contraction by heat and cold; but there is no settling whatever;
“ 3. The area wall is perpendicular and put up in a good workmanlike manner as such wall should be;
“ 4. Stone and brick: stone are limestone, as I call good and sound material; brick are good hard brick, and front is hard pressed and ornamented for front;
“5. As regard to the blocking under joist, I find blocks and furring under the same, both under party and partition walls. I do not believe that the same does any damage, as to the settling, or any damage to the building, as it is customary to level up the timber in this way;
“ 6. The plastering I find to be two coats; wall a greén finish and second coat skim finish; a good hard wail;
“ 7. Interior finish between Norway and white pine. The difference is of no account, except the Norway can be kept better and cheaper; and as to quality, the Norway is No. 1, and is better than white pine in my mind;
“ 8. In my examination of the building I find that there has been ■changes from the contract in many details, viz., stairs, closet and*356 also material and other changes. But as a whole the general erection of the building as to plans and specifications has been in good, workmanlike manner, and as to the value of the building in December, 1886, that the changes do not, in my judgment, materially change it. Yalue: in other words, the change in "material and workmanship have not lessened the value of the building in December-, 1886. From my examination I am led to believe the buúding has been most shamefully abused and torn, and has .not been properly cared for. It seems to have been the desire of some persons to make it appear as bad as possible in some respects, and this is especially so as to digging around and along the center wall.
“All respectfully submitted,
« W. H. MURPHY.
“ Cobleskill, N. Y., Mcvrch 25, 1892.
“ To expenses.................................... $6 5Ú
“ Two days examining building....................; 20 00"
“ One day making out report....................... 10 00
$36 50 ”
Whether the referee, in determining this case, has relied entirely upon the report or opinion of Mr. Murphy, or somewhat upon the-evidence taken before him, is not disclosed. That the unverified statement made by Murphy was considered by him, and to some extent made the basis of his decision, is to be inferred from his report. The defendant insists that the course pursued by the referee was illegal and entirely unwarranted by the stipulation of' the parties. That it was illegal unless justified by such stipulation there can be no doubt. So that, in deciding this question, it becomes, necessary to determine whether the referee was authorized by the stipulation not only to make an examination of the premises in the-presence of a person he might select, but also to delegate the power to make such an examination to a third person, to be made in the-absence of the referee, and to call upon such third person to make an unverified report, which, if relied upon, substantially determined the questions involved in the case." We think the only right conferred upon the referee by the stipulation was to examine the building in the presence of a person to be selected by him, to the end that he might better understand the evidence which had been given.
On the trial, during the examination of the plaintiff Lewis, the plaintiffs’ counsel asked the following question: “ In reference to the portion of the work which was designated by the counsel as subletting, you may state if in your conversation with the defendant it was talked that other persons than yourself would do the wood work, when you were conversing about taking the contract. [Objected to on the ground that the witness should state the conversation, and any conversation prior to or at the time of entering into the contract merges in the writing itself, and is the best evidence. The terms of the contract cannot be impeached by parol. Objection overruled. Exception by defendant.] A. I did. There was competition in the letting of this contract. There were various other persons besides the plaintiffs that put in bids for the work. Q. In conversing with this defendant in reference to the manner in which
Henry W. Brown was called and sworn as a witness for the defendant and testified to a thorough inspection and examination of the building, and detailed such defects in the construction and materials as he discovered. Among other things, he found that the belt course of stone was discontinued at the balcony. He was then asked: “ And what put in their ¡olace ? ” This was objected to by the plaintiffs as incompetent, and the objection was sustained. We think this was error. The defendant clearly had the right to show any defects that existed in the building, and, where there had been an omission of the materials provided for by the contract, to show what had been substituted in their place.
On the cross-examination of Edward A. Walsh, who was called as a witness for the defendant, after giving the price of pine lumber and stating that only perfectly clear pine was what was called “ uppers,” he was asked the following question: “You use very little of that compared with the other qualities ? [Objected to as immaterial. Objection overruled and exception by the defendant.] A. I don’t know how to answer that question. We use cheap lumber; a good deal more of (selects ’ than of ‘ uppers.’ Ho not use most all 1 selects.’ ” We dp not think this evidence was admissible. The question at issue was not as to what was used by others, nor what was in general use,' and, hence, what the witness, who was an experienced builder, might or might not have used, was wholly immaterial.
Peter Bogart, who waé called as a -witness by the plaintiffs, and who testified that he was employed by them to work on the defendant’s building, was asked this question : “ Hid Mr. Lewis frequently tell
Our attention lias been called to many other rulings of the referee which present grave questions as to their propriety, but as we think the judgment should be reversed for the reasons already given, and as these rulings are not liable to occur upon another trial, we deem it unnecessary to specially discuss them at this time.
Judgment reversed on the law and facts and a new trial ordered, with costs to abide the event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.