Kenny v. Monahan
Opinion of the Court
The plaintiffs have sustained, by a preponderance of evidence, their claim that they completed their work in accordance with the contract, and in a substantial and workmanlike manner, and that their claim for extra work should be allowed. The contract provided that the work should be done in a good, workmanlike, and substantial manner, to the satisfaction and under the direction of the architect, to be testified by a certificate under his hand. The architect furnished the required certificate, and testified himself upon the trial that the performance of the contract was in accordance with the plans and specifications thereof, and in a substantial and workmanlike manner. The variation in these specifications of which the defendant most seriously complains is the substitution of angle irons for bridle irons. I find that such substitution was done under the direction of the architect, and he testified that the defendant agreed to the change. Whether he did or not, I do not consider that material, because upon the evidence I find that the defendant was not damaged by the substitution; for, all things considered, angle irons make just as good a job as bridle irons.
The defendant interposes two substantial counterclaims—First, for damages for delay in the completion of the building beyond the time specified in the contract. The contract provided that the work should be completed by September 25th. The work was not actually com
The second substantial counterclaim argued by the defendant is for damages occasioned by the water coming in through the roof, and particularly on the night of October 12, 1898, to the injury of the stock of goods upon the floors below. The contract provided that “the contractor must at all times protect his works, and will be held responsible for any damages thereto until the completion and acceptance of the work.” It was contemplated by both parties that the defendant should actually conduct his business upon the lower floors during the progress of the work. The safety of the stock was in the hands of the plaintiffs, and, in my judgment, a very high degree of care should have been exercised by the plaintiffs to insure the safety of the defendant’s property. I do not think that the care exercised by the plaintiffs was quite up to the standard, and that whatever damage was sustained by the defendant by reason of water coming in through the roof on October 12th should be charged against the plaintiffs. The amount of this damage was the subject of considerable litigation upon the trial of this action. A short time after the damage was done the parties agreed to submit to three arbitrators the question of the amount of damages. The plaintiffs selected one arbitrator, the defendant another, and the two thus chosen selected a third. They met and examined the goods claimed to be damaged by the defendant, made an appraisal, and agreed that the amount of damage sustained by the defendant was $278.65. The defendant repudiated .the award of the arbitrators. The plaintiffs now claim that the award of the arbitrators is binding upon the defendant. The defendant claims that the arbitration is void. From my view of the case, it is
My conclusion is that the plaintiffs are entitled to judgment against the defendant for the amount claimed by them as the balance due on the contract and for extra work claimed, less the amount of the counterclaims of the defendant, which I find have been established at the sum of $411.15'. The plaintiffs are also entitled to the costs of the action, but I award no extra allowance.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.