Roe v. Redner
Opinion of the Court
As constructed in 1880, the dam at the outlet of Popolopen pond is upon the site of the previous one,
The deeds from Wyckoff’s descendants, Sergeant, Bright, and others, to Redner, convey no title to the premises in question here and are void. From the proofs and from the lapse of time the presumption that the whole title was vested in Suydam, prior to his death, must be indulged in, and that must obtain in support of the ore company’s title.
The dam is the property of the ore company, is upon its lands, and even if there were any serious question as to its precise location that would not avail the defendant Redner, for these reasons: There was the right to alter and to rebuild the former dam; then we have the lapse of time and the possession of and the control by the ore company for more than twenty years, adversely to any right of Redner, and the doctrine of an estoppel in pais would operate against him, he having stood by during such construction and acquiesced therein.
As between Redner and the electric company a different holding, upon the question of title to the lands upon which the dam stands, would be called for; as between them the principle of' res judicata would obtain, since that question was necessarily involved in the previous litigation in which they were parties, but that does not apply to the plaintiff Roe, whose title comes through the same chain as that of the ore company’s. The determination of that question is not, however, necessary here, and would not be decisive upon the rights claimed by the plaintiffs as against the ore company.
The ore company concedes that “ plaintiffs are entitled to the natural flow of the water without any material diminution or waste,” but claims that “ they are not entitled to have the flow increased by the stored water,” and that plaintiffs are now getting the natural flow of the stream over the spillway of the dam.
There had been no dam at the outlet of Popolopen pond for about twenty years prior to the construction of that now standing; in dry seasons there was not a sufficient natural flow of water to operate the machinery in the mill formerly owned and operated by plaintiff Roe’s predecessors in title; there is not now, and since 1880 there has not been, a sufficient flow of water for that purpose in dry seasons, unless the stored and impounded waters in the pond are released, and there is no proof of any interference with the natural flow of the stream since the plaintiff Rue acquired title to the premises formerly known as the Miller mill, conveyed to him by the grantee of Annie B. Phelps, who had, prior to the conveyance to Roe’s grantor, convened to the defendant ore company the lands and rights hereinbefore referred to, together with other lands.
Roe took his title subject to the grant of lands and rights to the ore company in relation to said dam and the storing up of water thereby; he has succeeded to all of the rights which said Annie B. Phelps had after the aforesaid conveyance to the ore company and to such rights as have accrued to her or himself by reason of the covenant in said deed contained, as to the maintenance and control of said dam and of the waters stored up because thereof. There is no ambiguity in said covenant and its language is to be interpreted according to the ordinary and popular meaning and significance thereof, so as to effectuate the intention of the parties.
The mill privilege which the grantor Phelps then had was down stream from the pond about six miles, and a very necessary essential to'the enjoyment of said privilege was a sufficient flow of water to propel the water-wheel and machinery, since it was a mill operated by water power. The defendant covenanted not to “ use the * * * rights so granted,’ which included the right to store up the water which would naturally flow through the stream and past the grantor’s mill, “ so as to injure or impair the mill privilege ” which she then had or which she “ or her * * * assigns ” thereafter might have, and by the same instrument Mrs. Phelps granted all her “ right * * * to draw water from said Popolopen pond for propelling machinery or otherwise so far as heretofore granted to her in any way or by any person.” Clearly it was not contemplated that the natural flow of the stream was to be increased for her benefit by. the storage of water, for she
Whatever right or privilege remained to her has come, by mesne conveyances, to the plaintiff Roe, and it is not shown that he has since acquired any other or greater right or privilege.
Plaintiffs have not shown any “ use ” by the ore company of “the premises or rights so granted * * * so as to injure or impair the mill privilege which the ” grantor then had, and, as said before, it does not appear that any other right of privilege has since then accrued to Roe. There were then the ruins of the old dam and she had only the natural flow of water, which, as we have seen, was insufficient for the operation of her mill in all seasons, and
The ore company has fully kept and performed the covenant on its part as to the construction of the dam and has not been shown to be guilty of any breach or disregard of any right which the plaintiffs or either of them have.
Judgment for defendants against the plaintiffs and in favor of the defendant ore company as against the defendant Redner in accordance herewith. Let decision be settled on notice, at which time the question of costs will be passed upon.
Judgment accordingly.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.