Whale Creek Iron Works v. New York & Queens Electric Light & Power Co.
Opinion of the Court
This is a motion to discharge a mechanic’s lien on failure to begin action to enforce the same within thirty days after notice given pursuant to section 59 of the Lien Law. The motion is made by the contractor and not the owner.
The law authorizing this practice was originally contained in chapter 342 of the Laws of 1885. By the terms of that act, the right to serve the notice and move to discharge was o conferred on the owner or the person against whom the lien was filed. Whether by the terms of that act the notice could be served by the contractor who employed the lienor, or whether the right was limited to the owner, is, in view of the change in the law, immaterial. This provision of law was carried into the Code in 1897 and became section 3417, and from there it was transferred to and has become section 59 of the Lien Law.
By the terms of the law, as it now reads, the right to serve the notice is not expressly limited to the owner. I believe that the notice may now be served by any person whose interests are affected by the lien. The lien practically garnishees the amount due the contractor. Frequently, the lien is more burdensome on the contractor than on the owner. It does not trouble the owner unless he wants to sell the property, whereas it may seriously embarrass the contractor not to be able to collect the amount due him'until the lien is discharged. I think, therefore, that the contractor may make the notice.
Section 59 of the Lien Law empowers the court in its discretion to discharge the lien for failure to prosecute. Whether it should do so or not depends upon the circumstances of each case. Ordinarily, the lien should be discharged unless some cause be shown to the contrary. The cause shown in this case is that the- lienor has brought an action at law in the City Court of the city of Hew York against the contractor upon the claim- for which the lien is filed and that the contractor opposed advancing that case on ‘the calendar for trial. As the City Court decided that the ease should not be advanced, the opposition of the contractor to that motion was justified.
I shall grant the motion and thus prevent unnecessary litigation.
Motion granted.