C. T. Willard Co. v. City of New York
Opinion of the Court
The action is to foreclose a lien claimed to have been acquired under a contract in writing dated on or about August 27, 1909, for a public improvement, entered into by the Robertson & Gerehart Contracting Company with the city of New York for the regulating, grading, and paving with macadam pavement Bay Ridge Parkway (extension of Shore Road), between Fourth avenue and Ft. Hamilton avenue, in the borough of Brooklyn, city and state of New York. The said Robertson & Gerehart Contracting Company also entered into other contracts with the city which are designated in the evidence and briefs as “Purification Plant” and “Sixty-Seventh Street” contracts. Another contract was entered into relative to work on Bay Ridge avenue, which was considered as part of the contract which is the subject of this action. The evidence shows that the Ridgewood National Bank agreed to finance the contractor in its said contracts, and that the latter, on or about September 23, 1909, by an instrument in writing, assigned to the said bank all moneys due or to grow due under the contract in suit, and assignments were also made by the
The bank claims that it loaned and advanced to the contractor various sums of money, amounting in the aggregate to $108,754.06, and that there should be added to the amount due to the bank the following items, viz.: Interest, $1,499.68; premiums paid on bonds to discharge liens, $388.49; additional premiums paid on indemnity bonds, $128; attorney’s fees for services rendered in connection with the giving of bonds, $200; total, $2,216.17. This last-mentioned sum, added to the sum of $108,754.06, brings the total of the bank’s claim up to the sum of $110,970.23. The bank received the following sums from the following sources, namely: Bay Ridge (A) $68,067.59; Bay Ridge (B), $1,452.29 ($69,519.88); purification plant, $11,687.26; Sixty-Seventh Street, $11,143.45; other work, $24,903.74; total, $117,-254.23. Subtracting the total of the bank’s alleged offsets, $110,970.-23, leaves a net balance of $6,284 over and above all loans and advances made by the bank to the contractor, exclusive of charges for interest, premiums on bonds, and attorney’s fees.
It is claimed on behalf of some of the lienors that the bank is not entitled to reimbursement for premiums paid on bonds, nor should they be allowed anything for attorney’s fees claimed to have been incurred. It is further claimed in their behalf that the bank should be charged with the ihterest on the balance in its hands, which claim is disputed by the bank. It is claimed on behalf of the lienors that the balance in the hands of the bank is applicable to the payment of their liens which are embraced in this action, because the last two payments came out of the.contract in suit, as follows: March 8, 1911, $11,430.-22; April 25, 1911, $11,591.77; total, $23,021.99. The learned counsel for the bank and surety company, adverting to such final payments on the Bay Ridge contracts, urges that it does not follow from the “mere sequence of contributions to the pot that the dregs of the entire mixture are attributable to one ingredient rather than to another.”
The previous payments were $11,687.50 on the purification plant contract and $11,143.35 on the Sixty-Seventh Street contract, making a total of $22,830.61, which the bank claims was received for the purpose of finishing.the contract which is the subject of this action and to earn the said final payments on it, which overcamé the deficit that
Before making a definite disposition of the matter I wish to see counsel, and will appoint the 29th day of March, 1912, at the opening of the court at Trial Term, Part IV, as the time and place of such further hearing.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.