Whitmore v. Village of Charlotte
Opinion of the Court
Plaintiff entered into a contract to do certain paving for defendant. The work has been completed to the satisfaction of defendant, whose engineer has certified the amount due the plaintiff for this work. The only controversy between the parties is on the question of interest, whether or not the plaintiff is entitled to interest on the amount conceded to be owing it for the work and materials furnished under the contract. The amount, due plaintiff was easily computed by the engineer, and I see no reason why the claim should not bear interest. 22 Cyc. 1513; Sweeny v. City of New York, 173 N. Y. 414; Braas v. Village of Springville, 100 App. Div. 197; Roebling’s Sons Co. v. City of New York, 110 id. 366.
According to the complaint the work was not com
It appears, therefore, that the demand for payment was made before the work was fully completed, and I do not think plaintiff would be entitled to interest from the time of that demand, March 19, 1915, but should be entitled to interest from the date of the commencement of this action, which was subsequent to the completion of the work, and the making of the final estimates of amount due plaintiff by the defendant’s engineer.
The demurrer is therefore overruled, without costs, and it is held that plaintiff is entitled to interest on the claim in question from the date of the commencement of this action.
Ordered accordingly.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.