Bridgeport Construction Co. v. Duffey
Opinion of the Court
The plaintiff, a domestic corporation, entered into a contract on the 11th day of March, 1914, with the state of New York for the improvement of the Coxsackie village highway No. 5369 located in the county of Greene, state of New York.
By the terms of the contract the plaintiff agreed to construct the said highway in accordance with the plans and specifications which were made a part thereof.
Upon the completion of said highway the state of New York agreed to pay the sum of $25,161.54. •
“ The contractor in consideration of the moneys to be paid and received for the construction of such work hereby expressly covenants and agrees for a period of three years to guarantee and maintain the parts of the road hereinafter mentioned and under the following conditions:
“ The base of the road when laid shall be accepted in writing by the State Commissioner of Highways, and after such acceptance in writing is given by the State Commissioner of Highways the Contractor then covenants and agrees to guarantee and maintain all that part of said road over, the accepted base for a period of three years from the final acceptance thereof by the ¡State.
“ The Contractor further agrees to promptly make and execute free of charge any and all repairs to said part of said road and renew all such materials as aforesaid as may become necessary from ordinary and legitimate wear and tear, from natural causes, or from defective materials, and to restore said portion of said work to the proper grade if it falls below it any place, and remedy all such defects as may disclose themselves during said period of three years, even if the repairs are not or cannot be made during the said term. In case of the failure of the Contractor
“A sum equal to five per centum of the contract price for that part of the work for which guaranty is required will be retained out of the moneys accruing to the Contractor for a period of one year after the completion and acceptance of the work.”
On the 20th day of November, 1914, the plaintiff was duly adjudicated a bankrupt by the United States District Court of the Southern District of New York and thereafter Charles W. H. Arnold was appointed the receiver of said bankrupt and upon qualifying as such receiver entered upon the duties of such office. Thereafter the said receiver was duly appointed and qualified as the trustee in bankruptcy of the plaintiff and by an order of the United States District Court of the Southern District of New York is authorized to commence this action.
On the 22d day of April, 1915, the commissioner of highways notified the plaintiff that certain repairs had become necessary upon state highway No. 5369 and thereby directed said plaintiff to proceed within twenty days from the date thereof to make the repairs therein designated. Upon the 18th day of May, 1915, the commissioner of highways notified the plaintiff
On or about the 7th day of July, 1915, the state commissioner of highways notified the plaintiff that whereas ten days had expired and neither the contractor nor the receiver nor the surety company upon the bond of the contractor had complied with the notice hereinabove mentioned, it was ordered that, pursuant to the terms of said contract for the improvement of Coxsaclde village state highway No. 5369, said contract was thereby canceled and annulled; and it was further ordered that all or so much thereof as might be necessary of the sum of $608.89 retained for the guaranty of the first year’s maintenance work on said highway should be and the same was thereby made applicable to any expense which might be incurred by the state in such' maintenance owing to the neglect or refusal of the contractor or the surety company to perform the same.
On the 8th day" of October, 1915, summons and complaint in the above entitled action were served upon the defendants herein, in and by which the plaintiff seeks to restrain the defendants from using the said sum of $608.89 for the purpose of maintaining or repairing said state highway No. 5369.
Upon the trial of the issues joined herein the following facts other than those already stated were stipulated:
“ Third. That certain repairs became necessary upon said State highway 5369 during the period of one year after the completion thereof; that the Com-
“ Fourth. That pursuant to § 20 of the contract for the construction of said highway (a part of Exhibit 1) the base of the road when laid was duly accepted in writing by the State Commissioner of Highways.
“ Fifth. That there was no amount added to or included in the contractor’s total bid price for the construction of said highway No. 5369, pursuant to the contract and specifications therefor (Exhibit 1 herein) by reason of the guaranty clause (§20) contained in said contract, and that there was no amount added nor included in the engineer’s estimate made upon the construction of said highway prior to the letting of the contract therefor.”
Upon these facts the defendant moved to dismiss the complaint of the plaintiff herein upon the grounds, first, that the complaint fails to state facts sufficient to constitute a cause of action, and second, that the proof submitted by the plaintiff is insufficient upon the merits to constitute a cause of action against the defendant.
Section 20 of the specifications is the only portion of. the contract which needs judicial interpretation.
It seems clear to me that the repairs required by specification No. 20 have reference to “ any and all repairs ” of whatever name or nature whatsoever and
There is a clear line of distinction in the Highway Law between “ construction and improvement ” of a highway on the one hand and “ maintenance and repair ” on the other. See Highway Law, arts, vi, vii. This distinction existed at the time of the passage of the Referendum Act of 1912 (Laws of 1912, chap. 298), and had existed in the Highway Law from the inception of the policy of improved state and county highways. Express provision is made for the appropriation of funds from the state treasury to maintain and repair the state and county highways of the state. Highway Law, § 171. An examination of the Highway Referendum Act (Laws of 1912, chap. 298), which made available the moneys used in connection with this highway contract, discloses that the moneys thereby made available could be appropriated solely for the purpose of “ constructing and improving ” highways. No mention is made of “ maintenance and repairs. ’ ’
The theory of the plaintiff is that the repairs in question are not part of the new work contemplated by the statute when it made moneys available by bond issue for the “ construction ” of highways, but it is the “ repair ” of old work, which is clearly distinguished from the former in the Highway Law and which is separately provided for in that law and in the making of appropriations by the legislature.
It is contended that the requirements of specification 20, that the contractor guarantee and maintain the road for three years, necessarily tended to impose upon the bond moneys a burden which was illegal, in
It seems clear to me that the natural result of this guaranty clause is to increase the amount which contractors will bid for the construction of highways where the contract for the same contains this guaranty clause and that by the terms of section 20 of the specifications an attempt was made through this guaranty clause to provide, for a period of three years, for the maintenance and repair of such highways out of the funds appropriated for construction and improvement.
It is stipulated as one of the facts in this case that there was no amount added or included in the contractor’s total bid price for the construction of the highway in question by reason of this guaranty clause, but it seems to me that the validity of the clause itself must be determined not by the facts of this particular case but by what is possible under it, as was said by Judge Hiscock in People v. Klinck Packing Co., 214 N. Y. 121,138.
I cannot agrée with the counsel for the defendant that the guaranty included under section 20 of the specifications is “ a guarantee of the quality and character of the work,” such as was indicated by Judge Haight in People ex rel. North v. Featherstonhaugh, 172 N. Y. 112. In that case Judge Haight said: “ We think the repairs required by the contract have reference to making good the imperfect work done, or the defective material used therein.” But here by the-stipulated facts we have an admission that it is not making good the imperfect work or materials but is a guaranty to make repairs which “ have become neces
But whether the specification in question involved an expenditure of moneys for a purpose not authorized by the Appropriation Act or not, there are two sufficient answers to the plaintiff’s complaint. An action to restrain the expenditure of such state moneys, if such expenditure is illegal, it seems, could be brought by the people of the state alone. County of Albany v. Hooker, 204 N. Y. 1, 19.
Moreover a party may waive the benefit of a constitutional provision. Vose v. Cockcroft, 44 N. Y. 415; Conde v. City of Schenectady, 164 id. 258, 263. Certainly the plaintiff, the contractor, who has done the work and has been paid everything due him under the contract, except the small percentage here involved, could not lie by and obtain the benefit' of the contract and then ask that the retained moneys be paid to him and that he be permitted to escape the terms of the agreement as to these repairs because of want of power in the highway commissioner to contract to pay for such repairs out of such moneys.
The plaintiff claims the moneys reserved to guarantee the performance of the work to be the moneys of the contractor, on the ground that the contractor did not estimate any additional cost for these repairs when submitting its bid and yet the contractor seeks to avoid the work of repairs on the theory that the contract contemplated the expenditure of public moneys for a purpose not covered by the Appropriation Act. The effect of granting him the relief sought would not be to prevent improper expenditure but to permit him to escape his just obligations voluntarily assumed. Thus, it is not a taxpayer or the state which is seeking to impeach the transaction but it is the contractor who has acquiesced in the unauthorized act and benefited
It could not be contended that the act of the highway commissioner was per se illegal or malum, prohibitum, but simply ultra vires. It was simply one of capacity or power of the highway commissioner to agree directly or indirectly to pay for repairs out of the referendum moneys. The plaintiff having had the full benefit of the contract is estopped from questioning its validity. City of New York v. Sonneborn, 113 N. Y. 423; Sheldon H. B. Co. v. Eickemeyer H. B. M. Co., 90 id. 607; Rothschild v. Title Guarantee & Trust Co., 204 id. 458, 461; Pollitz v. Wabash R. R. Co., 207 id. 113, 129; City of New York v. Delli Paoli, 202 id. 18.
Since a court of equity cannot grant the relief sought herein, the motion of the defendant to dismiss the complaint of the plaintiff is granted.
Motion granted.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.