In re King-Varick Corp.
Opinion of the Court
The controversy arises out of a certain contract by which the respondent undertook, in consideration of the sum of $50,000, subject to certain additions and deductions, to furnish material and labor in connection with excavation, underpinning, etc. After the performance by the contractor of perhaps the major part of its work, the owner, who is the petitioner herein, terminated its employment for cause which it deemed sufficient, and completed the work at its own expense, and is now seeking to charge the contractor with the cost. The latter has brought an action to foreclose a mechanic’s lien and the petitioner seeks to have its damage established by arbitration as an offset to the respondent’s claim. The amount of this alleged damage exceeds the sum demanded under the mechanic’s lien.
The arbitration clause upon which petitioner relies reads in part as follows: “ In case the owner and the contractor fail to agree in relation to the allowances mentioned in paragraph ‘ 23 ’ of these ' General Conditions ’ or losses specifically referred to as such in these general conditions, or the expense of completion mentioned in paragraph 1 33 ’ of these ' General Conditions,’ or should either of them dissent from the decision of the architect' relating to any of these matters, * * * then the matter shall be referred to a board of arbitration * * *. No matters other than those mentioned in this paragraph shall be the subject of arbitration. The contractor shall diligently prosecute his work pending the arbitration of any dispute under this paragraph.”
Arbitration is, therefore, limited to the assessment of damages arising by reason of the default of the contractor in abandoning the work or refusing or neglecting to proceed therewith or to certain other contingencies. But the respondent specifically denies any default and alleges that the termination of employment was entirely wrongful. The propriety of the contractor’s discharge is not the subject of arbitration, and can only be determined by the court. But in advance of such decision it is difficult to perceive how damages can be assessed by arbitration upon a hypothetical default of the contractor. True it is that section 3 of the Arbitration Law provides: “ If the making of the contract or submission or the default be in issue, the court, or the judge thereof, shall proceed
Case-law data current through December 31, 2025. Source: CourtListener bulk data.