George A. Fuller Co. v. Cedar-William Street Corp.
Opinion of the Court
The plaintiff (the contractor) erected an office building for the defendant (the owner). The plaintiff claims a balance due of $45,007.43, with interest, for which it asserts a lien. The owner denies that it owes anything, contending that it has overpaid the contractor. It, in turn, asserts counterclaims on the basis that the contractor defrauded the owner of large sums by means of a scheme of increasing estimates of costs and by erroneously duplicating charges by inserting said items both as costs and in a certain ten per cent allowance, which will be later referred to. It asks for an accounting between the parties. The contract was in writing, carefully drawn by the parties after numerous conferences, at some of which lawyers represented them, and detailed and voluminous plans and specifications were prepared. The contract named as architects men of apparently wide experience, who were designated as the owner’s agents. The contractor was a large construction firm, and the owner’s president a builder of some experience. The provisions of the contract applicable to the disputed points were that the contractor was to furnish the labor and materials in the erection of the building in accordance with the plans and specifications. The owner agreed to pay the cost incurred by the contractor and a fixed fee of $43,000. The contractor agreed that the main work specified would not cost in excess of $836,053, including the fee of $43,000, and, if it exceeded said sum, the contractor was to pay the excess. The parties knew the contract covered only part of the work. In order to obtain a finished building, a great deal of construction not included in the main contract was required. The original plans specified some of this additional work, but it was later omitted, with the understanding it would be ordered as alterations or extras.
The three main points in dispute between the parties are: (1) Was the contractor required to segregate the cost of extras from the cost of the main work under the contract? (2) Have the defendants established that the contractor committed fraud in intentionally overestimating the cost of the extras so that they might receive the benefit of an enlarged guaranteed limit price? (3) What is the meaning of the provision in the contract that “ the contractor shall receive the cost to it plus 10 per cent, for general conditions and a commission of 6| per cent, thereon in addition for all work in excess of $960,682? ” (Italics mine.) The first question requires a consideration of the contract provisions relating to (a) costs, (b) the guaranteed limit price, (c) the contractors’ allowances, and (d) extras; also a consideration of the practical construction given the contract provisions by the parties. It has been seen that the contractor was to get actual cost plus certain fees in certain contingencies; that for the main work he fixed a limit, price; that the parties contemplated extras; that, when extras were ordered, the limit price was to be increased by the amount thereof; that a certain form of monthly accounting was required. The alterations and extras did not, nor were they intended to, await the finishing of the main work. They consisted in many instances of preparations for contemplated tenants of partitions, plumbing, wiring, etc. This work was ordered as the
The owner now complains that, by submitting grossly exaggerated estimates of the cost of extras, the contractor was enabled to avoid paying the excess of the cost of the main work over $830,053. Assuming that that happened, it was caused by two things: First, the contract provision that the limit price' was to change each time an extra was ordered; and, second, that the owner ordered the extras done without requiring a more conservative estimating of the cost of the extras. The proof as to the fairness of these estimated costs will be discussed later. The contention of the owner that the contractor was to segregate the cost of the two branches of the work is, in my opinion, neither warranted by the contract nor supported by a consideration of the practical side of the job involved. In . fact, it appears clearly as an afterthought. Neither the owner nor his architect ever requested it or objected to the contrary method which was consistently pursued. The testimony on the second claim of the owner, that the contractor was guilty of a fraud in that it willfully and intentionally submitted grossly excessive estimates of the cost of extras ordered, was voluminous.
The owner’s counsel have carefully and painstakingly reviewed this testimony. They have prepared elaborate and imposing tabulations and comparisons of the estimates involved with the subcontractors’ prices. By comparative analysis of the testimony, the owner’s expert witnesses, and the “ break-down sheets,” or detailed estimates, which the contractor used in arriving at the lump sum estimates, it attacks the fairness of the estimated prices for extras. A careful scrutiny of this proof convinces me that the elements of fraud not only have not been established, but that there is no basis for the claim. It is true that in. many instances the unit prices used in estimating the costs of extras were larger than those contained in the subcontracts. This appears to me readily understandable and to be expected. That the cost of performing a given quantity of extra work ordinarily exceeds that of a similar quantity of the main work was established. The contractor, when called on to do a particular item of extra work (and
The remaining question is the construction of the contract provision with relation to the allowance of ten per cent for “ general conditions.” Defendant owner contends that this provision means that as to extras the items of general expense, or “ job costs,” such as permits, water, insurance, etc., as distinguished from those costs which would be allocated to some particular “ trade,” were not to be paid by the owner as items of cost (though they were properly so charged as to the main work), but were to be covered by the allowance of ten per cent. The contractor contends that it was entitled to charge all “job costs ” in connection with extras as “ cost,” and that the ten per cent for “ general conditions ” was a sum in addition thereto for the increased general office overhead that the doing of extras entailed.
The meaning of the phrase “ general conditions ” as used in the contract is uncertain. The specifications contained a title heading “ The general conditions of the contract.” There follows a long series of articles or contract provisions applicable to the work as a whole. Following this series of articles are the specifications proper.
The word “ cost ” as used in the contract is also specifically defined to include many of the items of so-called “ job costs.” In order then to have the term “ 10% for general conditions ” interpreted to exclude the right of the contractor to charge actual " job costs ” on the extras, the word “ cost ” as to extras must be given an entirely different meaning from that specified in the contract as the meaning to be assigned to it. Plaintiff’s contention that the “ ten per cent, for general conditions ” meant a charge to cover the heavy general administrative overhead incurred in connection with the doing of extra wol'k seems more logical. I am not unmindful of the fact that the plaintiff’s summary showing how the figure $838,053 was arrived at classified what would ordinarily be the job costs uses the heading “ general conditions.” Some witnesses testified that this phrase is used in more than one sense in the building trade. This is apparent from what occurs in this very contract. Many absurd situations would occur if the construction contended for by defendant were followed. On the other hand, the allowance of ten per cent as a charge for overhead plus the six and one-half per cent for commissions would not, as defendant
Judgment is awarded the plaintiff adjudicating the existence of a lien in its favor for the sum demanded in the complaint, with interest. Submit appropriate decision and findings.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.