Building Chemicals Corp. v. Tiffany
Opinion of the Court
This is an application by the petitioner for a peremptory order requiring the respondents to award to the petitioner the contract under what is known as “ Specification No. 9669 ” for the waterproofing of buildings at the Pilgrim State Hospital in Brentwood. The lowest bid was made by G. R. McNulty Co., Inc. One of the requirements, however, of the bidding was that each bid- be accompanied by a deposit of “at least five per centum of the amount of the bid.”' The McNulty Company bid was accompanied by a check for $1,671.72, which was five and one-fourth cents less than five per centum of its bid of $33,435.45. The certified check was in the sum of $1,671.72, whereas it should have been in the sum of $1,671.77. This petitioner was the second lowest bidder and now claims that it should be awarded the contract on the theory that the McNulty Company’s allegedly improper bid should be thrown out.
The petitioner’s contention is without merit. The sum of five cents is so insignificant, in view of the inequitable result that would arise from a strictly technical application of the requirement herein,
The petitioner has set forth an able argument relative to the advisability of demanding a strict adherence to technical requirements. In this case, however, such manifest inequity would result that a more liberal rule must be followed. The ruling, however, should be limited to the facts of this case.
Motion denied. Enter order accordingly. No costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.