Empress Apartments, Inc. v. La Gee Contracting Corp.
Opinion of the Court
This is a motion pursuant to section 59 of the Lien Law to cancel a mechanic’s lien upon the ground that no action to enforce the same had been commenced within 30 days from the date of service of a notice to commence an action, namely, July 1, 1960. The attorney for the lienor has sworn that he mailed a copy of the complaint to the attorneys
The court feels that the indignation shown by the attorney for the lienor is entirely unjustified unless there are special circumstances which certainly did not exist in this instance, where the attorneys are “fighting nail and tooth ”, to expect an opposing attorney to accept service of a summons without as much as requesting him in advance to do so. “ In Matter of Poole ([38 N. Y. St. Rep. 806], supra) the court remarks that ‘ the statute, pursuant to which the notice was served, provides that the owner may give notice to the lienor to bring an action of foreclosure by a day named, or show cause why the lien should not be vacated; and further provides that the court may make an order vacating the lien. The language of the statute is plain and intelligible. The intention of it was clearly to enable the owner to require the lienor to test the validity of his lien speedily and to give to the court the power to vacate or discharge the lien in case the action was not commenced, or sufficient reason presented to the court excusing the lienor for not commencing the action in the time named in the notice. ’ ” (Jackson Co. v. Haven, 87 App. Div. 236, 238.)
Section 59 of the Lien Law is not a Statute of Limitations. The lien does not fall by noncompliance with the notice. It is the duty of the court to consider the equities of the ease and it
The owner is not in any way prejudiced by the denial of this application. The owner’s position has not changed because it knew at all times that the lienor intended to pursue its remedy. The owner is a corporation. Should the owner sell, it might be difficult to locate assets. It is possible that the attorney for the lienor might be subject to a malpractice action if this application were granted.
The lienor at the most was 9 days late in commencing its action. A delay of as long as a period as 29 days has been excused. (See Matter of Rosen, 13 N. Y. S. 2d 1019.)
The motion to vacate mechanic’s lien pursuant to section 59 of the Lien Law is denied.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.