Seaboard Pools, Inc. v. Freeman
Opinion of the Court
In this Special Term action the plaintiff seeks to foreclose a mechanic’s lien which it filed for the work, labor, and services performed and materials furnished. The complaint alleges that the parties entered into a contract and that the defendants agreed to obtain the financing. The plaintiff alleges that it duly performed the conditions of the contract; that it did its work between June 7 and June 10. In a second cause of action, the plaintiff seeks to recover the loss of profits. The defendants’ answer contains a counterclaim in addition to denials.
The plaintiff, a corporation engaged in the construction of swimming pools, and the defendant Donald Freeman, a homeowner on the North Shore of Long Island, on May 15, 1961 executed a paper writing providing for the construction of a pool on the latter’s property. Indorsed on the printed form used by the plaintiff was the note: “Final Financing to be determined”, followed by the initials of the signatories to the document. This paper also provided ‘ ‘ approximate date of construction June 1st, 1961”. Discussions as to terms of financing preceded and followed the execution of the instrument. At plaintiff’s request the defendant Donald Freeman signed a
On June 1, 1961, on plaintiff’s application, a permit for the construction of the pool was issued. On June 7 the excavation was begun, materials were delivered to the site, and a substantial part of the work was completed on June 10 when plaintiff stopped work. There is no doubt that prior to June 1, on the date when the application for the permit was made and before plaintiff began its work, it knew that its application for credit had been rejected and that the defendants had refused to comply with the conditions imposed by the finance company. It must be assumed that since the work was proceeding on the property owned by the defendants and in which they lived at the time, they knew that the work was being done. Had the plaintiff proceeded to completion of the work, the court might have come to a conclusion different from that reached here.
The plaintiff then made various proposals to the defendant Donald Freeman for terms of financing which varied from those to which the said defendant had agreed after signing the “contract”, all of which the defendant rejected. Thus the situation remained throughout the Summer. In a letter dated September 8, 1961, the plaintiff, among other things, advised the defendant that it had obtained an approval by a bank. The plaintiff did not attempt nor offer to complete the pool. The defendant, in an answering letter, indicated that he would execute the notes if payment were postponed until May of 1962, in view of the fact that he would not have the use of the pool until the Summer of that year, and informed plaintiff that its failure to arrive at an agreement would be treated as an abandonment of the contract and that the defendant would seek to recover the expense incurred for restoration of the premises.
On June 1, 1962 the defendant again wrote to the plaintiff advising it that the Building Inspector for the village had noti
It is obvious from the phrasing used by the parties, “ Final Financing to be determined ’ ’, that it was an agreement to make an agreement in the future. The terms of payment were an important consideration to the parties and the instrument executed by the parties which lacked a material element was not a contract. (Ansorge v. Kane, 244 N. Y. 395.)
We agree with the plaintiff’s contention that a valid contract is not a prerequisite to the contractor’s having a lien under the Lien Law and with its further contention that -the proper consent of the owner eliminates the need for a formal contract. However, as held by the court in Jenkin Contr. Co. v. Sixth Ave. & 57th St. Corp. (282 App. Div. 662) it is the opinion of this court that the defendant here had not given his “ consent ” to the work which plaintiff started and halted without the interference of the defendant. Section 3 of the Lien Law gives a contractor a lien for work done or materials furnished for the improvement of real property when it is done with the consent of the owner and section 2 of that law defines the term “ improvement ” as used in the statute. Here the contractor began work toward making an improvement and then stopped the work and it has failed to show that it performed its agreement or that performance was excused. (Rising v. Kendzie, 12 A D 2d 988.) Even if the consent of the defendant might be shown, it would have had to have been a consent to the construction of a pool, not a portion thereof and since the owner “ did not cause the failure substantially to complete the contract he may not be held ”. (William Saloy, Inc. v. Luhrs, 284 App. Div. 908.) Defendants cannot be held liable for the work done for as it stood incomplete it was not an “ improvement ”. The language used by the court in New York Elevator Supply & Repair Co. v. Bremer (74 App. Div. 400, 402-403, affd. 175 N. Y. 520) is particularly applicable to the facts in this action: “ an owner cannot be charged for improvements which are incomplete and which fail to comply with the terms and specifications under which they were to be done and upon the performance of which the consent is based. * * * If the contractor desires to hold the owner of the building responsible for the work and materials furnished, it is
Defendants’ motions to dismiss the complaint made at the close of the plaintiff’s case and at the close of the entire case is granted. Defendants having failed to offer any proof on their counterclaim, it is likewise dismissed. No one of the parties shall have costs against any of the others.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.