Neptune Estates, LLC v. Big Poll & Son Construction, LLC
Opinion of the Court
OPINION OF THE COURT
A bench trial in this action seeking damages under alternative theories of breach of contract, negligence, indemnification, restitution, a “wrongfully filed mechanic’s lien” and counterclaims of breach of contract, conversion, and unjust enrichment was commenced on July 30, 2012 and concluded on September 20, 2012. This action was joined for trial with the related action, IVM Gen. Constr. v Neptune Estates, LLC (Sup Ct, Kings County, index No. 19311/10), in which IVM sought to foreclose a mechanic’s lien at issue in both matters.
At the conclusion of the joint trial, this court ruled from the bench that the mechanic’s lien was void as it was filed untimely pursuant to the New York Lien Law. As a result, Neptune’s counterclaim for wilful exaggeration in that action could not be adjudicated and the IVM action was dismissed.
In the present action, the first and second causes of action for breach of contract and negligence, respectively, were withdrawn. At the conclusion of the bench trial, the third, fourth, and fifth causes of action for indemnification and restitution were dismissed as was the seventh cause of action for a “wrongfully filed mechanic’s lien” as to defendant Pavel Lutso (Lutso) only. Defendants Big Poll & Son Construction, LLC (Big Poll) and Lutso’s second counterclaim for conversion was similarly dismissed.
The court reserved decision on the sixth and seventh causes of action for a “wrongfully filed mechanic’s lien” as well as Big Poll’s first and third counterclaims for breach of contract and unjust enrichment, respectively.
Background
This action involves a dispute between plaintiff Neptune Estates, LLC (Neptune), owner of 380 Neptune Avenue,
On August 21, 2008, Neptune entered an agreement with defendant Big Poll whereby Big Poll would act as the general contractor on a construction project on the property. By contracts dated February 2009, IVM entered two subcontractor agreements with Big Poll whereby IVM agreed to perform the structural steel work, masonry, and concrete slabs on the project.
On January 5, 2010, IVM filed a mechanic’s lien (January Lien) against the property and, pursuant to Lien Law § 9 (3), IVM improperly identified the person with whom the contract was made as both “Big Poll & Son Construction, LLC and Future City Plus, Inc.” On March 10, 2010, after Neptune moved to discharge the January Lien, Justice Bunyan vacated the January Lien without prejudice in a short form order with the consent of the parties. The order indicated that “a new
At the conclusion of the joint trial, Neptune moved to vacate the Lien and dismiss the lien foreclosure action based upon IVM’s failure to establish substantial performance of the steel or concrete masonry contracts and upon Lien Law § 10 (1) for failure to file the Lien within eight months after the final performance of work. The court held that, based on the testimony and evidence introduced at trial, Big Poll was off the construction site no later than April 21, 2009. Accordingly, the filing of the Lien in January of 2010
With respect to the Neptune action, this court dismissed Neptune’s fourth and fifth causes of action for restitution of allegedly diverted trust assets holding that Neptune was not a beneficiary pursuant to Lien Law article 3-A and no proof of any actual diversion of assets by Big Poll, Gorshkov, or IVM was presented at trial. The court dismissed Neptune’s seventh cause of action for wrongful filing of a mechanic’s lien as to Lutso as it was established that Gorshkov, on behalf of IVM, had filed the Lien, not Lutso. The court also dismissed Big Poll’s second counterclaim for conversion holding that if Big Poll were entitled to recover against Neptune at all, as a matter of law,
At the conclusion of the trial, counsel were given the opportunity to submit posttrial briefs. The court specifically noted that the briefs should include a dollar amount with respect to each of the parties’ respective claims. During oral arguments, the court noted that the signed release by Lutso on behalf of Big Poll (exhibit 12), acknowledging payment in full by Neptune, appeared to preclude recovery by Big Poll upon its breach of contract counterclaim and the existence of the contract would preclude recovery upon the equitable unjust enrichment claim. However, the court permitted Big Poll the opportunity to brief these issues. Plaintiff submitted a posttrial memorandum seeking $328,278 in damages. IVM submitted a posttrial reply letter arguing that the “counterclaims must fail.”
Discussion
Big Poll’s Claims
Plaintiff argues that Big Poll’s counterclaims for breach of contract and unjust enrichment must be dismissed as Big Poll was paid for its work through its last payment application, number four, which was signed by Lutso on March 28, 2009 (exhibit 8).
At the conclusion of the trial, Big Poll claimed that the evidence at trial established that Big Poll was only paid approximately $1,500,000
Big Poll’s first and third counterclaims are dismissed as Big Poll failed to meet its burden to prove its damages for breach of contract and unjust enrichment. The Final Release, signed by Big Poll’s principal, clearly states a balance due of $0 and Big Poll has not demonstrated that it was owed the claimed approximately $700,000 (exhibit 12). Big Poll did not contest Neptune’s calculations in a posttrial brief as directed by the court. At the conclusion of the trial, Big Poll argued that it anticipated receiving the proceeds from payment application number five, signed and submitted by its successor, Future City, months after Big Poll signed the Final Release and months af
Neptune’s Claims
Plaintiff contends that its sixth and seventh causes of action seeking damages for “wrongfully filed mechanic’s liens” are based upon the common-law tort cause of action for “injury to property.” Neptune alleged that IVM and Gorshkov filed the Lien with “a material misstatement or false claim,” with the intent “to cloud title in order to exact from Neptune money that IVM was not entitled to,” and the “wrongfully filed mechanic’s liens caused Neptune to lose the use of the Neptune property with resulting delay to the completion of the Project thereby lessening the value of the Neptune Property.” The alleged tortious conduct allegedly resulted in “damages including increased interest payments in an amount to be determined at trial but presently estimated to be not less than $250,000.” At trial Neptune established that the filing of the Lien resulted in a work stoppage from January 5, 2010, when the lender, Brooklyn Federal Savings Bank, ceased releasing funds as a result of IVM filing the Lien, and continued until June 7, 2010, when the Lien was bonded and Brooklyn Federal Savings Bank resumed releasing funds to Neptune. Neptune calculates damages of $125,010 in interest it paid on a $500,000 loan necessary to secure the Lien, $199,633 for the interest on the mortgage between January 5, 2010 and June 7, 2010, and $3,635.40 for flood insurance on the property between January 5, 2010 and June 7, 2010. Accordingly, plaintiff seeks $328,278 in damages as calculated through December 7, 2012.
In support of its legal theory, Neptune cites the definition of “injury to property” in General Construction Law § 25-b as “an actionable act, whereby the estate of another is lessened, other than a personal injury, or the breach of a contract.” Neptune also cites to Ghiglione v Friedman (115 App Div 606 [2d Dept 1906]) and Buckley v Mayor (30 App Div 463 [1st Dept 1898]) in support of its common-law claim for injury to property. In Ghiglione, plaintiff
“alleg[ed] in effect that the defendant wrongfully, unlawfully and knowingly caused a notice of mechanic’s lien against plaintiffs property to be filed in the clerk’s office of New York county upon a fictitious claim, thereby delaying the work on a building in process of construction, resulting in the loss of a*657 month’s rental of the property” (Ghiglione, 115 App Div at 607).
In citing the definition of “injury to property” then found in section 3343 (10) of the Code of Civil Procedure,
IVM argues that Neptune’s sixth and seventh causes of action are actually for “slander of title” and that Neptune failed to allege the requisite malice and special damages in its pleadings. Further, IVM claims that Big Poll acknowledged that it owes IVM the full amount of the Lien
FVM’s argument that the sixth and seventh causes of action are actually claims for slander of title is unavailing as plaintiff has never asserted that it seeks to recover based upon slander of title and a mechanic’s lien does not cast doubt on the validity
IVM argues that the common-law cause of action for injury to property is no longer viable, claiming, erroneously that there does not appear to be a single case published in the past 100 years holding that the filing of a false mechanic’s lien constitutes injury to property (see Lippes v Atlantic Bank of N.Y., 69 AD2d 127, 140-141 [1979]). As discussed herein, there is no merit, or authority to support, IVM’s contention that this ancient common-law cause of action is extinct. Further, IVM’s suggestion that slander of title is the only “applicable doctrine”
“An action based upon an alleged injury to property is one sounding in tort. Accordingly, any manner of commercial torts have been found to be within the purview of ‘injury to property’ ” (Lippes, 69 AD2d at 140 [citations omitted]). In its discussion of injury to property in Lippes, the First Department appellate court specifically cited Ghiglione in explaining that “improperly filing a mechanic’s lien upon a fictitious claim resulting in delaying building work” was an “injury to property” (Lippes, 69 AD2d at 140-141). Upon a finding that Neptune incurred losses as a result of FVM’s wrongfully, unlawfully and knowingly filing a mechanic’s lien against the property, based upon a fictitious claim, Neptune is entitled to recover damages
Upon the evidence adduced at trial, this court found that Big Poll was not running the project as general contractor, but that Gorshkov and IVM, who had brought Big Poll into the job, were actually managing it and acting as the general contractor. There was significant evidence that IVM and Gorshkov controlled Big Poll’s bank account, disbursed funds to itself as well as other subcontractors, and Big Poll was rarely on the site. Big Poll was brought into the project because, unlike IVM and Gorshkov, who had initially been approached by plaintiff, it was licensed to act as general contractor. In dismissing Big Poll’s claims, the court gave full credit to the waivers signed by Big Poll, including the Final Release in which Lutso, on behalf of Big Poll, signed a document clearly labeled, “FINAL RELEASE: FINAL WAIVER OF CLAIMS AND LIENS AND RELEASE OF RIGHTS” which expressly stated that Big Poll “waive[d] and release [d] [Neptune] from any and all claims and liens and rights of liens upon the [property]” (exhibit 12). Since it was Gorshkov who was controlling all aspects of the construction and was managing Big Poll’s finances as related to this project through a dedicated bank account, Gorshkov necessarily knew that IVM had no legitimate lien claim against Big Poll at the time the Lien was filed. Accordingly, this court finds that IVM wrongfully, unlawfully and knowingly filed the mechanic’s lien against the property based upon a fictitious claim.
In its summary judgment decision in the IVM action in 2010, this court noted that there were a number of issues of fact that prevented the court from summarily dismissing FVM’s complaint at that time, including the date of the Final Release signed by Big Poll, the date Big Poll was removed from the project, and whether Big Poll was owed funds from Neptune when the Lien was filed (IVM, 29 Misc 3d 1238[A], 2010 NY Slip Op 52188[U]). At trial, it was established that Lutso signed the Final Release on April 23, 2009 (exhibit 12) and that Big Poll was no longer on the site at least as of April 21, 2009. Further, IVM failed to establish that Big Poll was owed any funds from Neptune at the time the Lien was filed. In its summary judgment decision, this court specifically relied upon an affidavit submitted by IVM from Lutso, dated May 4, 2010, in which Lutso stated that Big Poll was not paid in full and was told that if it “did not sign the [Final Waiver], the project could not continue.” However, at trial, neither IVM nor Big Poll introduced any credible evidence
The court notes that IVM did not include Future City as a defendant or even reference the Future City contract in the IVM action complaint despite referencing Future City in both the January Lien and the Lien.
In support of its argument to dismiss Neptune’s causes of action, IVM contends that “two courts have sustained the validity
Neptune argues that it incurred three separate elements of damage as a result of the injury to its property. Neptune argues that during the work stoppage from January to June of 2010, that resulted from Brooklyn Federal Savings Bank ceasing distribution of funds until the Lien was secured, Neptune paid for six months of flood insurance and six months of interest on its mortgage. Neptune calculates that the flood insurance totaled $3,635.40 (exhibits 47, 48) and the mortgage interest totaled $199,633.39 (exhibit 49). Neptune also alleges that to secure the Lien, it took a loan from Benny Barmapov (Barmapov) who is the brother-in-law of Leon Szusterman (Szusterman), a part owner of Neptune. Neptune claims, and Barmapov and Szusterman testified, that Barmapov loaned Neptune the money at an interest rate of 10% per annum, payable in cash on a monthly basis. Neptune and Barmapov did not record the terms of the loan in writing signed by Neptune, the party to be charged, nor did Barmapov issue receipts for the purported cash payments. Other than oral testimony, Neptune offered little proof as to its purported interest payments. IVM argues that plaintiff cannot recover damages for the interest on the loan taken to secure the Lien as there was no promissory note and no receipts from the purported lender for the cash interest payments.
Neptune contends that it is entitled to the $3,635.40 it paid for flood insurance between January 14, 2010 and June 11, 2010 (exhibits 47, 48).
Neptune further argues that it is entitled to $199,633.39 in mortgage interest payments between January 5, 2010 and June 7, 2010 (exhibit 49) .
Neptune also asserts that it is entitled to a judgment for the interest it claims to have owed Barmapov to the date the Lien was vacated, calculated as $125,010 as of December 7, 2012. Although plaintiff would be entitled to interest paid upon a loan taken in order to secure the Lien so as to continue work on the project, plaintiff has failed to adduce sufficient evidence of payments made. The checks issued by Irma Taxi Corp. demonstrate that Szusterman’s brother-in-law, Barmapov, made a $500,000 payment from his business to secure the Lien (exhibit 41). However, it is undisputed that no note or other writing signed by plaintiff, memorializing the terms of the loan, was created. Although Barmapov prepared a self-serving letter indicating a 10% interest rate on the purported loan, beginning in June of 2010, it is dated February 8, 2011, eight months after the Lien was secured and is not signed by plaintiff (exhibit 42). Even were this self-serving memorandum sufficient to establish that a 10% interest rate had been agreed upon, Barmapov did not issue receipts for the many purported cash interest payments made by plaintiff, nor is there a tax record of such payments or the receipt of such income by the recipient. The only evidence that plaintiff submitted as proof of its interest payments, other than oral testimony, is a handwritten “ledger” created by Szusterman showing three interest payments beginning in December of 2010 totaling $12,501 (exhibit 44), Neptune’s bank statements showing six cash withdrawals of between $4,166 and $6,917
The documents admitted into evidence are insufficient to establish that Barmapov was the recipient of cash payments as a
Plaintiff is awarded judgment against IVM for $150,036.41 for the cost of flood insurance and mortgage interest incurred during the period defendants’ fraudulent lien delayed construction, with interest from May 1, 2010.
Plaintiff is also entitled to recover against Gorshkov in his individual capacity under the seventh cause of action for a wrongfully filed mechanic’s lien. Plaintiff argues that Gorshkov is individually liable to Neptune as he was an officer of IVM and participated in the tortious act of wrongfully filing the lien on behalf of IVM. “A corporate officer may be liable for torts committed by or for the benefit of the corporation if the officer participated in their commission” (PDK Labs, Inc. v G.M.G. Trans W. Corp., 101 AD3d 970, 973 [2d Dept 2012], citing Hamlet at Willow Cr. Dev. Co., LLC v Northeast Land Dev. Corp., 64
Conclusion
Defendant Big Poll & Son Construction, LLC’s first and third counterclaims are dismissed.
Plaintiff is granted judgment on the sixth and seventh causes of action, jointly and severally, against IVM General Construction, Inc. and Vadim Gorshkov, in the amount of $150,036.41 with interest from May 1, 2010.
. The project at issue was the construction of a seven-story residential condominium building which was expected to include 21 units.
. In the decision, this court denied Neptune’s summary judgment motion to dismiss the complaint, discharge IVM’s mechanic’s lien and cancel the notice of pendency. The court denied the motion as there were issues of fact as to whether Neptune owed funds to Big Poll when the lien was filed and whether IVM’s lien had been timely filed against Big Poll within the statutory eight months following Big Poll’s departure as general contractor.
. Neptune speculates that the subcontractor agreements between IVM and Big Poll dated “February 2009” (exhibit 58) only “came into existence between January 28 and February 22 [2010], when IVM served its Lien Law 38 Statement. . . .”
. This lien is the subject of the present action and the IVM action.
. In this court’s decision denying the summary judgment motion, the Lien filing date was deemed to be that of the January Lien (see IVM Gen. Constr. v Neptune Estates, LLC, 29 Misc 3d 1238[A], 2010 NY Slip Op 52188[U], *4 n 6 [2010]).
. It appears that FVM’s reply letter confuses the parties and which causes of action it is opposing. From the context of the reply letter, IVM opposes Neptune’s sixth and seventh causes of action and takes no position on Big Poll’s counterclaims.
. Payment application number five, was signed on July 3, 2009 by Dmitry Kadishev, principal of Future City, as it became the general contractor on the project after Big Poll was removed (exhibit 9).
. Although the Brooklyn Federal Savings Bank statement does not identify the recipient of the wire transfer, it is uncontested that Big Poll was the recipient.
. Exhibit 4, a summary of payments from Neptune to Big Poll and corresponding checks, demonstrates that Neptune paid Big Poll $1,475,480 for its work. However, there was testimony at trial suggesting that this number was higher. In the posttrial brief, plaintiff contends that Big Poll was paid $1,500,480. Big Poll did not submit any explanation of its calculations as to how much Big Poll was paid despite direction from the court to do so.
. In its answer, Big Poll sought damages “estimated to be not less than $679,570.”
. At trial, it was established that Future City worked on the project prior to Big Poll becoming the general contractor in August 2008. At the insistence of Neptune’s lender, Brooklyn Federal Savings Bank, Big Poll was brought in to replace Future City as the general contractor at that time.
. General Construction Law § 25-b, the identical definition of “injury to property” as contained in section 3343 (10) of the Code of Civil Procedure, was added to the General Construction Law in 1920 (L 1920, ch 917, § 1) which was first enacted in 1909 (L 1909, ch 27). The statutory language dates back to at least the 1848 Code of Procedure (see Lippes v Atlantic Bank of N.Y., 69 AD2d 127, 139 [1st Dept 1979]).
. IVM brought a claim for $536,671.94, the value of the Lien, against Big Poll in the IVM action and raised it in its pretrial memorandum. At the conclusion of the trial, after voiding the Lien, the court dismissed the IVM action without further addressing IVM’s claim against Big Poll. IVM did not move for judgment on its breach of contract cause of action against Big Poll and did not cross-claim against Big Poll in the surviving action. As IVM has not made any application to this court since the conclusion of trial to pursue relief against Big Poll, it is presumed that IVM has either abandoned its claim against Big Poll or the parties have resolved the issue through a settlement between themselves. The evidence at trial was that Big Poll and IVM were joined in interest and that IVM acted as Big Poll’s agent in performing the contract, even to the extent of signing Big Poll’s requisitions for payment and checks in payment to itself and other subcontractors.
. Similarly, this was not a cause of action for injurious falsehood. It is noted that although the courts have grappled with distinguishing causes of action for “slander of title” and “injurious falsehood,” it appears to he settled that the elements of these causes of action are “essentially identical” (see Casa de Meadows Inc. [Cayman Is.] v Zaman, 76 AD3d 917, 922 [1st Dept 2010], citing Rosenbaum v City of New York, 5 AD3d 154, 155 [1st Dept 2004]; Tolisano v Texon, 144 AD2d 267, 272 [1st Dept 1988, Smith, J., dissenting], revd on dissenting mem 75 NY2d 732 [1989]; Masaryk, 2005 NY Slip Op 30425[U]; compare Hirschhorn v Town of Harrison, 210 AD2d 587, 588 [1994]).
. Arguably, the statutory cause of action for wilful exaggeration under Lien Law § 39-a might appear to have been intended to supercede the common-law tort of injury to property, at least with respect to the filing of a false lien. However, to recover for wilful exaggeration under the Lien Law, a party must fully litigate the merits of the lien to a conclusion in a foreclosure action, and the lien must survive as valid in sill other respects, before recovery can be had for damages sustained. Thus, the statute does not provide a vehicle for relief to a wronged property owner, against whom the lien has been improperly filed, unless the lienor chooses to foreclose. While recovery in the nature of a penalty may be appropriately thus limited (see Joe Smith, Inc. v Otis-Charles Corp., 279 App Div 1, 4-5 [4th Dept 1951]), it could not have been the legislative intent to preempt all relief otherwise available to the damaged owner.
. In this court’s summary judgment decision in the IVM action, it was noted that the inclusion of Future City did not invalidate the Lien; however, any foreclosure upon unpaid amounts pursuant to contracts with Future City would require separate liens (see IVM, 29 Misc 3d 1238[A], 2010 NY Slip Op 52188[U]).
. Exhibit 24 is the December 14, 2009 email from Future City to IVM in which Future City removed IVM from the project as of December 15, 2009.
. Neptune raised the issue of listing both Big Poll and Future City in the January Lien in an affirmation, dated February 8, 2010, in what appears to be Neptune’s first attempt to invalidate the January Lien in Matter of Neptune Estates, LLC v IVM Gen. Constr., Inc. (Sup Ct, Kings County, Bunyan, J, index No. 3575/10).
. IVM does not contest the plaintiffs calculations other than to state that “[t]he [plaintiffs] suggestion that its financial problems were the result of the [defendant’s] lien is totally contradicted by the record” referencing, dehors the record, a lien filed by Future City against the property and the purported commencement of a mortgage foreclosure action. Plaintiff has responded in its reply to IVM’s posttrial reply letter, which included claims of
. Exhibits 47 and 48 include five checks issued by Neptune to Brooklyn Federal Escrow in the amount of $727.08 each for a total of $3,635.40.
. Exhibit 49 includes a mortgage interest ledger showing monthly mortgage interest payments in 2010 and Neptune’s form 1098 for tax year 2010 which indicates total mortgage interest payments for 2010 as $399,266.78.
. There was testimony at trial indicating that the cash withdrawals varied as some of the funds were purportedly used for separate loan interest payments to Barmapov with respect to the securing of a lien filed by former defendant Stillwell or for other personal uses. However, plaintiff claimed that either $4,166 or $4,167 of each withdrawal was payment to Barmapov for the interest on the purported $500,000 loan used to secure the Lien.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.