Palladino v. Mayor of New York
Palladino v. Mayor of New York
Opinion of the Court
The action was brought to recover the amount claimed to be unpaid for regulating and grading Fort George avenue from Tenth to Eleventh avenues, and setting curbstones and flagging sidewalks therein. The work was let by a contract, executed by the commissioner of public works and James H. Sullivan, on or about the 17th of August, 1886. And after it had been in part performed, the contract was assigned to the plaintiff, who completed
It was claimed on behalf of the defendant that it was entitled still to retain the balance remaining unpaid upon the contract price of the work, because of proceedings taken to establish a lien against the contract or by other persons. But the evidence tended so directly to prove that this lien had been satisfied as to leave no substantial reason for doubting the right of the plaintiff to recover the amount of this balance. And accordingly the verdict of the jury in his favor for that sum, together with the interest upon it, should not be unnecessarily disturbed.
But the claim made by the plaintiff for filling furnished by him to raise the street to the grade prescribed, stands upon different grounds. For by the terms of the proposals for the contract, no material of this description was included or required to be furnished. But the entire work, as proposals were invited for it, consisted of earth and rock to be excavated, curbstones to be furnished and set, and flagging stones to be furnished and laid. The amount of this work and materials were included in the published proposals. But no material for filling was mentioned, nor required to be estimated, which should be obtained, or supplied by the person whose proposals should be accepted for the performance of the work.
The work was ordered by a resolution adopted by the aldermen on the 11th, and approved by the mayor on the 18th of May, 1885. And this work was directed to be done under the action of the commissioner of public works. And sealed estimates for this work were invited by a notice published, as the charter required that to be done, in the early part of July, 1886. When the resolution was approved by the mayor, the earth included within the line of the
It was further insisted on behalf of the plaintiff that he was entitled under the contract to recover the value of the earth obtained and used by himself from other localities in filling the avenue up to its requisite grade. This claim proceeded upon the ground that it was mentioned in the specifications, which were inserted in the contract, that the “ street which is above the grade line is to be excavated, and such and so much of the material excavated as may be fit for the purpose, and as may be necessary, shall be filled in those parts of the street which are below the grade lines in the manner hereinafter provided; the material excavated not so used for filling shall be removed from the street; if the amount of material excavated that is fit for filling shall not be sufficient to regulate the street, the contractor shall furnish and supply material of proper kind and quality sufficient for the purpose, but only the difference between the total quantity of filling to finish grade and line, as shown in cross section, and the total quantity of excavation to the
And the contract itself declared that: “ For any work the price of which is not specified in this contract, the provisions herein contained in relation to work not provided for in this contract shall apply.” But no other provision appears to have been inserted in the contract relating to this subject, beyond that which was made a part of the specification. And while the difference in the quantity of filling exceeding that supplied by the earth taken from the avenue itself is stated to be considered as filling to be furnished, and as such to be paid for, there is yet no provision in the contract binding the defendant to make such payment. But, on the contrary, it was agreed by the contractor that he would receive in full for his compensation for furnishing all the materials and labor for, and the faithful performance of the whole of the work mentioned in the agreement, the following prices :
For excavating earth, per cubic yard, the sum of twenty- ■ seven (27) cents.
For excavating rock, per cubic yard, the sum of ninety-five (95) cents.
For furnishing and setting new curbstone, per linear foot, the sum of sixty-seven (67) cents.
For furnishing and laying new flagging, per square foot, the sum of thirty-one (31) cents.
And by a preceding part of the agreement it was also agreed by the contractor that he would, “ at his or their own cost and expense, furnish and provide all the materials and labor for the purpose of regulating and grading Fort George avenue from Tenth to Eleventh avenue, and set curbstones and flag sidewalks therein.” And that he would “complete the entire work to the satisfaction of the commisioner of public works and in substantial accordance with said specifications and the plan therein mentioned, and that he
It was further declared that “ this contract is made with reference to the proposals for estimates for the above described work hereto annexed, which are to be taken as part and parcel of these presents.” And in and by the proposals it was stated that “no extra compensation beyond the amount payable for the several classes of work before enumerated, which shall be actually performed, at the prices therefor to be specified by the lowest bidder, shall be due or payable for the entire work.”
And also that “ work or materials not specified, and for which a price is not fixed in the contract, will not be allowed for.”
The contract is not entirely harmonious and consistent in its stipulations and statements, but the intention to bind the contractor to furnish the materials and perform the labor for the prices contained in the contract, appears to be predominant. For he was obliged to agree, as a part of the terms upon which he received the contract, that he would not ask for, demand, sue for, or recover for the entire work, any extra compensation beyond the amount payable for the several classes of work in the contract enumerated ; and that no extra compensation beyond the amount payable for the classes of work enumerated should be due or payable for the entire work. And that all the materials and labor required for the work should be supplied and performed by the contractor. These stipulations and provisions are clearly and definitely expressed ; and so are those adjusting and prescribing the prices to be received in fall compensation for all the materials and labor, and the faithful performance of the whole work mentioned in the contract; and filling the avenue up to its prescribed grade was a neces
But if the contract from this general language employed in the specifications, and relating to any work the price of which was not specified in the contract, should be held to-be controlling as to the intention of the agreement, the effect would still remain the same. For by the law, as it was in force at the time when the agreement was made, and as it still remains, the Commissioner of Public Works was required to advertise for proposals for the work, and to let the contract to the lowest bidder. This imperative regula^ tion was prescribed by § 91 of article 16, chapter 335 of the Laws of 1873. And it was afterwards, by § 64, made apart of chapter 410 of the Laws of 1882. By this enactment it was provided that, “ Whenever any work is necessary to be done to complete or perfect a particular job, or any supply is needful for any particular purpose, which work and job is to be undertaken or supply furnished for the corporation, and the several parts of the said work or supply shall together involve the expenditure of more than SI,000, the same shall be by contract under such regulations concerning it as shall be established by ordinance of the- common council, excepting such works now in progress as are authorized by law or ordinance to be done otherwise than by contract, and unless otherwise ordered by a vote of three-fourths of the members elected to the common council. And all contracts shall be entered into by the appropriate heads of departments, and shall, except as herein otherwise provided, be founded on sealed bids or proposals made in.
It was proved upon the trial that by the revised ordinances of 1880, adopted after the enactment of the law of 1873, the proposals for estimates should contain among others a statement of “ The quantity and quality of supplies, or the nature and extent as near as possible of the work required.” But the proposals which were published in no manner in-, eluded material to be supplied by the contractor for the filling of the avenue beyond that which might be excavated in the performance of the work. And no estimate was made
And that it was not expected that the contractor furnishing estimates, and afterwards receiving a contract under the advertised proposals, would be compensated for such filling, was entirely evident from the proposals themselves as they were published. And that such additional filling might become necessary must have been obvious to the contractor before he submitted his estimates, for the proof established the fact that the land included in the avenue exhibited the previous removal of the earth, amounting in quantity, according to the statements of the plaintiff, to about 5,300 cubic yards. And it was with this knowledge which had been, or readily could have been, acquired by the contractor, that the estimates were made and the contract was taken. And it would be a violation of the mandatory provisions of the statute to permit a recovery by the plaintiff for the value of this filling under the facts and circumstances in this way presented. If that could be done, then any other part of the work or material included in the improvement could likewise have been omitted and the defendant rendered liable to pay for the labor and materials used in performing it. And thereby the restraints and directions of the statute would be as thoroughly disregarded as though it were in the plainest language repealed. If the courts may disregard it in one particular they may in another, and as consistently defeat it altogether by sanctioning a recovery for work done and material supplied in total violation of its provisions. And that the court has no authority to do." But its duty is to enforce and maintain the law without regard to the consequences which may be encountered by the contractor,
The judgment and order should be reversed and a new trial directed, with costs to the defendant to abide the event unless within twenty days after notice of this decision the
Van Brunt, P. J., and Brady, J., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.