Respondent’s mechanic’s lien for making1 ‘ drawings of preliminary plans ” and allied architectural services which never became embodied in an erected structure, should not summarily be dismissed on motion under subdivision (6) of section 19 of the Lien Law, upon the ground that they are not final plans. Mechanic’s liens may be filed for materials furnished or labor performed “ for the improvement of real property ” (Lien Law, § 3). Subdivision 4 of section 2, as amended by chapter 608 of the Laws of 1934, defines “ improvement ” as including “ the drawing by any architect or engineer or surveyor, of any plans or specifications or survey, which are prepared for or used in connection with such improvement ”. Nothing contained in this language disallows architects’ plans which are preliminary in nature, provided that they have progressed to a point where they can be characterized as “ plans ” within the meaning of that term as it is used in the building trades.
The order appealed from should be affirmed, with costs.
Lewis, Ch. J., Conway, Desmond, Dye, Ftjld, Fboessel and Van Voobhis, JJ., concur.
Order affirmed.
Reference
- Full Case Name
- In the Matter of Bralus Corporation, against Irvin Berger
- Cited By
- 3 cases
- Status
- Published