Albert Saggese, Inc. v. Town of Hempstead
Cases that cite this one
7 later published cases cite this decision.
- Metro Group Construction Corp. v. Town of Hempstead (Appellate Division of the Supreme Court of New York 2005)
- GVC II, Inc. v. Contract Dispute Resolution Board (Appellate Division of the Supreme Court of New York 2007)
- National States Electric Corp. v. City of New York (Appellate Division of the Supreme Court of New York 1996)
- Huff Enterprises, Inc. v. Triborough Bridge & Tunnel Authority (Appellate Division of the Supreme Court of New York 1993)
- A.I. Smith Electrical Contractors, Inc. v. Fire Department (Appellate Division of the Supreme Court of New York 1991)
- Melwood Construction Corp. v. State (Appellate Division of the Supreme Court of New York 1986)
- Buckley & Co. v. City of New York (Appellate Division of the Supreme Court of New York 1986)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion
OPINION OF THE COURT
Memorandum.
The order of the Appellate Division should be modified by providing that, on its second cause of action against the joint venture and its third counterclaim against the town, Royal shall *911 have judgment against the town in the amount of $54,060 and payment of that amount to Royal shall extinguish the town’s obligation on the award of judgment in that reduced amount to the joint venture and, as so modified, order affirmed, with costs to the town against the joint venture and Royal. The weight of the evidence comports with the conclusion that the items claimed as extras, other than the additional pile lengths, resulted from plaintiff’s failure adequately to gauge the cost of performance or from changes made as an accommodation to plaintiff and at its request rather than as a result of mutual mistake or of any fundamental change in the contract ordered by the town or its engineer. Modification is, however, required because the surety, as assignee of mechanic’s lienors paid by it on plaintiff’s behalf, rather than the plaintiff, is entitled to such moneys as may be due from the town.
Chief Judge Wachtler and Judges Jasen, Meyer, Simons, Kaye and Alexander concur.
Order modified in accordance with the memorandum herein and, as so modified, affirmed, with costs to the town against the joint venture and Royal.
Case-law data current through September 30, 2026. Source: CourtListener bulk data.