City of Elmira v. Larry Walter, Inc.
Cases that cite this one
17 later published cases cite this decision.
- United States Fidelity And Guaranty Company v. Braspetro Oil Services Company (2d Cir. 2004)
- United States Fidelity & Guaranty Co. v. Braspetro Oil Services Co. (2d Cir. 2004)
- Congel v. Malfitano (N.Y. 2018)
- Cuesport Properties, LLC v. Critical Developments, LLC (Md. Ct. Spec. App. 2013)
- International Fidelity Insurance v. County of Rockland (District Court, S.D. New York 2000)
- Construction Contracting & Management, Inc. v. McConnell (N.M. 1991)
- Episcopal Church Home & Affiliates Life Care Community, Inc. v. Gates Circle Holdings, LLC (Appellate Division of the Supreme Court of New York 2022)
- Paguirigan v. Prompt Nursing Employment Agency, LLC (2d Cir. 2020)
- Congel v. Malfitano (Appellate Division of the Supreme Court of New York 2016)
- Spectrum Painting Contractors, Inc. v. Kreisler Borg Florman General Construction Co. (Appellate Division of the Supreme Court of New York 2009)
- Becker Parkin Dental Supply Co. v. 450 Westside Partners (Appellate Division of the Supreme Court of New York 2004)
- Village of New Paltz v. Merlex Contracting, Inc. (Appellate Division of the Supreme Court of New York 2004)
- Savoy Little Neck Associates v. Halpern Construction, Inc. (Appellate Division of the Supreme Court of New York 2003)
- BGW Development Corp. v. Mount Kisco Lodge (Appellate Division of the Supreme Court of New York 1999)
- Hill v. Arnold (Appellate Division of the Supreme Court of New York 1996)
- J & J Structures, Inc. v. Callanan Industries, Inc. (Appellate Division of the Supreme Court of New York 1995)
- Aero Garage Corp. v. Hirschfeld (Appellate Division of the Supreme Court of New York 1992)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
OPINION OF THE COURT
Memorandum.
The order of the Appellate Division should be affirmed, with costs.
This breach of contract action has its origins in an agreement for the construction of a municipal parking garage. While the construction project was underway, disputes arose concerning a number of issues, including defendant contractor’s entitlement to progress payments. As a consequence of these disputes, defendant discontinued further work on the project some five months before the contractually designated completion date. Plaintiff was forced to retain another contractor to finish the project and, as a result, the municipal parking garage was not ready to open at the anticipated time. Following the final disposition of an arbitration proceeding, plaintiff commenced the present action against defendant contractor for breach of contract damages.
After protracted litigation, defendant was found to have breached its contractual obligations, and plaintiff was awarded actual damages, as well as liquidated damages. The latter award was based on a liquidated damage clause in the parties’ agreement that provided: "As actual damages for any delay in completing the work * * * are impossible to determine, the Contractors and their Sureties shall be liable for * * * the sum of One Thousand Dollars * * * as fixed, agreed and liquidated damages for each calendar day of delay from the above stipulated completion * * * until such work is satisfactorily completed and accepted.” On cross appeals, the Appellate Division modified the judgment by, inter alia, subtracting the portion of the award that represented liquidated damages under this clause. The propriety of the Appellate Division’s decision on the liquidated damages question is the only issue before us on this appeal.
The liquidated damage clause on which plaintiff relies, by its terms, represents an attempt by the parties to anticipate and provide for the specific possibility that defendant’s satisfactory completion of the project might be delayed beyond the
Plaintiff’s contention that such an interpretation of its agreement would encourage contractors to abandon projects as a means of avoiding contractually agreed-upon liquidated delay damages is unavailing. Even assuming that such a concern has some practical foundation, owners who wish to protect themselves against it may negotiate for the inclusion of express contractual provisions for liquidated damages for delay even in the event of an abandonment. Accordingly, since these parties’ contract contained no such express provision, plaintiff was not entitled to an award for liquidated damages.
Chief Judge Wachtler and Judges Simons, Kaye, Alexander, Titone, Hancock, Jr., and Bellacosa concur.
Order affirmed, with costs, in a memorandum.