Berry v. Polish White Eagle Bldg. Co.
Berry v. Polish White Eagle Bldg. Co.
Opinion of the Court
The action in the court below was brought by the Polish White Eagle Bldg. Co. against J. A. Berry for breach of contract for construction of a theater for $17,400.00, which amount was paid in full to Berry. The building company claims that the contractor did
A judgment was rendered for plaintiff for $1000.i0'0 for delay, $250.00 for defects in the second floor construction and $3156.00 for construction of the heating system. On motion for new trial, the judgment was modified and the $1000.00 allowed for delay was eliminated. The defendant prosecuted error and two questions raised:
1. Damages for defective flooring.
2. Defendant’s liability for the cost of the heating system required by the building inspector.
The specifications which were a part of the building contract provided that the laws of the state and the city of Dayton concerning theaters were to be considered a part of the contract and a violation of them were at the contractor’s risk. The Court of appeals held:
1. The question as to damages for defective flooring is one of fact for the jury, and the judgment was not contrary to the manifest weight of the evidence.
2. The question of the contractor’s liability for cost of heating system is one of law, based on the construction of the building contract, and by reason of the contract, the burden was upon the contractor to install the heating apparatus in accordance with the building code.