Stearns Lehman, Inc. v. Davis Excavating, Unpublished Decision (10-29-1999)
Stearns Lehman, Inc. v. Davis Excavating, Unpublished Decision (10-29-1999)
Opinion of the Court
OPINION
Defendant Davis Excavating appeals a judgment of the Court of Common Pleas Richland County, Ohio, entered on a jury verdict in favor of plaintiff Stearns and Lehman, Inc. on its complaint for breach of contract between the parties. Appellant assigns three errors to the trial court:ASSIGNMENTS OF ERROR
ASSIGNMENT OF ERROR NUMBER 1
THE TRIAL COURT COMMITTED PREJUDICIAL ERROR IN NOT REMOVING AND TAKING THIS CASE FROM THE JURY AT THE CONCLUSION OF PLAINTIFF'S CASE.
ASSIGNMENT ERROR NUMBER 2
THE TRIAL COURT COMMITTED PREJUDICIAL ERROR IN NOT TAKING THE CASE FROM THE JURY AT THE CONCLUSION OF THE ENTIRE CASE.
ASSIGNMENT OF ERROR NUMBER 3
THE VERDICT AND JUDGMENT IS CONTRARY TO LAW.
The record indicates appellee Stearns and Lehman, Inc., hired appellant Davis to perform excavation work at a new facility to be built in the Mansfield, Richland County area. Appellant Davis began work to prepare the building site, but for reasons unrelated to appellant's performance, appellee Stearns Lehman, Inc., decided to put the entire project on hold because of cost overruns. Eventually, appellee constructed a building on the same location as the original site, smaller but still within the area appellant had excavated. Appellee had re-designed the project and employed other contractors to build this smaller building. At the time Stearns and Lehman put the project on hold, appellant Davis had completed a rough grade of the building site, although the project required further excavating work. Appellee Stearns and Lehman paid appellant $36,000.00. Approximately one year later, when appellee Stearns Lehman re-opened the building site, it planned for the front of the building to still be in the same spot as planned when appellant had done his site preparation work, and the general contractor began to dig footers for the building's foundation. At some point, the contractor found appellant Davis had not stripped the topsoil, grass, or other organic material but had simply covered the topsoil with compatible subsoil. The area had not been compacted properly, and the general contractor felt the building site preparation work appellant had done would not support the foundation of the building. Stearns Lehman asked appellant to repair the problems, but appellant would not do so without further payment. Eventually, Stearns Lehman paid another contractor $55,400.00 over and above the planned contract work to repair and redo the work done by appellant.
For the foregoing reasons, the judgment of the Court of Common Pleas of Richland County, Ohio, is affirmed.
By Gwin, J., Wise, P.J., and Farmer, J., concur
Case-law data current through December 31, 2025. Source: CourtListener bulk data.