Ohio Court of Appeals, 1999

G.R. Osterland Co. v. T. a Bridge Cons., Unpublished Decision (6-25-1999)

G.R. Osterland Co. v. T. a Bridge Cons., Unpublished Decision (6-25-1999)
Ohio Court of Appeals · Decided June 25, 1999

G.R. Osterland Co. v. T. a Bridge Cons., Unpublished Decision (6-25-1999)

Opinion of the Court

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] Judgment affirmed.

Nader, J., concurs in judgment only with Concurring Opinion. See Opinions and Judgment Entry. [FORD] (NADER) (O'NEILL)

STATUTES/CONSTITUTION:

R.C. 5525.16(C) requires a party suing a surety to recover money owed by the insured to furnish the surety with a "statement of the amount due" under the strict time limits articulated in the statute. The failure to furnish the statement within the time limits terminates the plaintiff's cause of action.