Credit Rep. Serv. v. Joseph Sylvester Co., Unpublished Decision (8-24-1999)
Credit Rep. Serv. v. Joseph Sylvester Co., Unpublished Decision (8-24-1999)
Opinion of the Court
In April 1991, the parties entered into a written agreement under which Contractor would construct a commercial office building in Boardman, Ohio for CRS. In June 1991, CRS took possession of the building. Thereafter, Contractor remodeled the basement of the building to contain a lounge and a conference room. CRS later had a second stairway installed by an entity unidentified in the record. At the request of the county building inspector, Contractor closed this illegal stairway and installed a fire-rated stairwell with doors.
On July 12, 1994, the county building inspector sent a notice of violations to CRS which specified the following deviations from the Ohio Basic Building Code:
"1. Interior completions and alterations were performed under your direction contrary to the approved plans, specifically:
a. An interior stair was constructed. The stair as constructed does not conform to O.B.B.C. The risers exceed the 7" maximum height. The handrails do not have extensions. The work was performed without a building permit or submission of plans.
b. A conference room was constructed in the basement. The work was performed without a permit or submission of plans.
2. The building was occupied under your direction before issuance of a certificate of use and occupancy."
A notice of violations was also sent to Contractor which stated:
"1. Interior completions and alterations were performed under your direction contrary to the approved plans, specifically:
a. A one-hour fire-rated floor/ceiling assembly was not installed at the basement ceiling.
b. An interior stair was eliminated at the front (north) of the building. Although a one-exit space is allowable under O.B.B.C., plans must be submitted showing proposed change.
c. The basement storage area did not receive a limited area sprinkler system.
d. A conference room was constructed in the basement. The work was performed without a permit or submission of plans.
2. Restroom exhaust does not discharge to the exterior of the building." (Citations to code sections omitted)
The notices informed the recipients that they had thirty days to file an appeal and request a hearing before the Board of Building Appeals pursuant to Ohio Adm. Code
On April 9, 1996, CRS filed a civil suit against Contractor seeking to be reimbursed for the aforementioned sums of money expended on bringing the building up to code and obtaining an occupancy permit. After the case was assigned to a magistrate, CRS moved for summary judgment arguing that because Contractor failed to appeal its notice of violations, it is barred by the doctrine of res judicata from disputing liability. CRS also stated that the amount of damages was undisputed. Contractor filed a memorandum in opposition and filed its own motion for summary judgment stating that there existed genuine issues of material fact with regards to who performed the work that was code violative. On June 19, 1997, the magistrate granted summary judgment for CRS. Contractor filed timely objections to the magistrate's order. The trial court adopted the magistrate's decision on January 28, 1998. The within timely appeal resulted.
Contractor sets forth two assignments of error, the first of which contends:
Res judicata consists of two concepts: claim preclusion and issue preclusion. Grava v. Parkman Twp. (1995),
In the case at bar, CRS contends that Contractor is barred from defensively litigating the issue of whose work resulted in the code violations because the notice of violations, which became final when no appeal was filed, already determined this issue. Thus, it is the doctrine of collateral estoppel that CRS utilizes to defend the trial court's grant of summary judgment. More specifically, CRS is attempting to use the doctrine of offensive collateral estoppel. Offensive collateral estoppel is a term used to describe the scenario where a plaintiff prevents a defendant from relitigating issues that have previously been decided against the defendant in a suit by a different plaintiff. Black's Law Dictionary (6 Ed. 1991) 179. However, the use of offensive collateral estoppel is not permitted in Ohio courts. Goodson v.McDonough Power Equip., Inc. (1983),
In accordance, collateral estoppel will not operate in the case at bar to preclude Contractor from defending the breach of contract action brought against it by CRS. Initially, we point out that a notice of violations is not judicial in nature. The first sentence of the notice states that it is being issued without prior hearing. One could attempt to argue, although CRS does not, that even though the notice of violations is not judicial in nature, Contractor had ample opportunity to litigate the issues in the notice by appealing to the Board of Building Appeals.1 However, collateral estoppel requires the precluded issue to have been actually litigated at a prior time. Fort FryeTeachers Assn., OEA/NEA v. State Emr. Relations Bd. (1998),
Moreover, the required identity or mutuality of parties is lacking. A long-standing requirement of collateral estoppel is that the parties in both actions must be identical, or the parties in the subsequent action must be in privity with parties in the prior action. Whitehead, supra at 113. A notice of violations, also called an adjudication order, was sent to Contractor by the Mahoning County Building Inspection Department. A notice of violations must be issued before the state or a political subdivision seeks a civil or criminal remedy against one who violates applicable building codes. See Ohio Adm. Code
Moreover, there is no evidence that CRS was in privity with the building inspector. The building inspector was not acting on behalf of CRS. In fact, the building inspector sent CRS its own separate notice of violations. Because mutuality of parties between Contractor's notice of violations and the current civil suit is lacking, issue preclusion is inapplicable and Contractor is not barred by the doctrine of res judicata from defending itself against the claims of CRS. As such, the magistrate and the trial court incorrectly granted summary judgment on the basis of the res judicata doctrine.
The magistrate's decision stated that even if res judicata was inapplicable, Contractor could not defeat CRS's summary judgment motion with an affidavit that incorporated by reference the allegations in its memorandum in opposition to summary judgment. The affidavit submitted by Contractor was that of its president Joseph Sylvester. This affidavit stated that it was not Contractor's work on the building that resulted in code violations but was the work of CRS. This statement seems to be more than an incorporation by reference of the contents of the memorandum.
Regardless, we hold that CRS did not meet its initial burden of proving that there is no genuine issue of fact for trial. SeeDresher v. Burt (1996),
Moreover, CRS asked the magistrate for summary judgment on the issue of liability solely upon the grounds of res judicata. Instead of addressing why there was no genuine issue of fact with regards to who performed the code violative work, CRS merely stated that Contractor's argument was irrelevant since it was barred by res judicata. As previously analyzed, res judicata is inapplicable. CRS did not advance any other argument with regards to Contractor's liability. Thus, CRS failed to meet its initial burden. The decisions below focused on Contractor's failure to meet its burden; however, the nonmovant's burden does not become activated until the movant meets its burden. Accordingly, this assignment of error is sustained.
Contractor's second assignment of error provides:
For the foregoing reasons, the trial court's order which granted summary judgment is reversed and this cause is remanded for further proceedings according to law and consistent with this court's opinion.
Cox, P.J., concurs.
Donofrio, J., concurs.
APPROVED:
__________________________ JOSEPH J. VUKOVICH, JUDGE
Case-law data current through December 31, 2025. Source: CourtListener bulk data.