Keeton v. Hinkle, Unpublished Decision (3-10-2000)
Keeton v. Hinkle, Unpublished Decision (3-10-2000)
Opinion of the Court
OPINION
Appellants Linda and Dennis Keeton appeal from the June 29, 1998, judgment entry of the Morrow County Court of Common Pleas.ASSIGNMENT OF ERROR I
THE COURT'S FAILURE TO FIND A VIOLATION OF THE CONSUMER SALES PRACTICE (SIC) ACT WAS AN ABUSE OF DISCRETION AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.
ASSIGNMENT OF ERROR II
THE COURT'S FAILURE TO AWARD DAMAGES FOR THE CONTRACTOR'S FAILURE TO SUBSTANTIALLY COMPLETE CONSTRUCTION WITHIN "90 WORKING DAYS" WAS AN ABUSE OF DISCRETION AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.
ASSIGNMENT OF ERROR III
THE COURT'S CALCULATION OF PLAINTIFF'S (SIC) DAMAGES FOR DEFENDANT'S BREACH OF ITS IMPLIED DUTY TO PERFORM WORK IN A WORKMANLIKE MANNER WAS AN ABUSE OF DISCRETION AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.
ASSIGNMENT OF ERROR IV
THE COURT'S FAILURE TO AWARD DAMAGES FOR THE UNDERPINNING OF THE FOOTER WAS AN ABUSE OF DISCRETION AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.
ASSIGNMENT OF ERROR V
THE COURT'S AWARD OF DAMAGES TO APPELLEE ON HIS COUNTERCLAIM FOR EXTRAS WAS AN ABUSE OF DISCRETION AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.
ASSIGNMENT OF ERROR VI
THE COURT'S DIRECTION TO PAY THE MECHANICS' LIEN TO BALDAUF WITHOUT GIVING THE OTHER PARTIES AN OPPORTUNITY TO BE HEARD AS TO THE PROPRIETY OF THE PAYMENT WAS CONTRARY TO THE PARTIES' STIPULATION BIFURCATING BALDAUF'S CLAIMS AND THEREFORE WAS AN ABUSE OF DISCRETION AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.
(2) That the subject of a consumer transaction is of a particular standard, quality, grade, style, prescription, or model, if it is not;
* * *
(5) That the subject of a consumer transaction has been supplied in accordance with a previous representation, if it has not, except that the act of a supplier in furnishing similar merchandise of equal or greater value as a good faith substitute does not violate this section;
* * *
(9) That the supplier has a sponsorship, approval, or affiliation that he does not have;
Under R.C.
Q. Did you believe, at that time, did you believe that you could get it done in 90 days?A. I thought it would be enough, he was told that when we — in fact Mike and I talked about April.
However, appellee also testified that he told Mike Myers that appellee "didn't think 90 days was doable." Id. Upon further questioning, appellee admitted that he did not tell the appellants that he did not think the ninety days was feasible. However, appellee also testified that he believed that "[i]f everything went right . . ." appellee could get appellants in the house by the middle of April, 1996. Id. at 256, 257. Prior to March 1996, it became clear to appellee that he could not make the mid-April deadline:
Q. When was the foundation ready for you to start work?
A. In March, the exact date, I don't know. And Mike and I discussed the day he come to inspect the foundation, that there was no way we could get the extension, just to do the best you can do, and that's what I did.Q. And you didn't communicate that with the Keetons at that time either?
A. No.
Q. Did you tell Mr. Myers to communicate that to the Keetons?
A. No, I did not, because the 90 working days, we hadn't began to use the 90 working days, when you take the bad weather out in January, December, February.
Id. at 266.
The Court, in its judgment entry, noted that "there is no contract definition as to what constitutes working day" and that the initial delay was chargeable to appellants "as they were owners of land with a title defect." While appellee's lack of candor may have been regrettable, we do not find that the trial court's refusal to find that appellee's actions constituted a violation of the Consumer Sales Practices Act was against the manifest weight of the evidence. Such decision was supported by competent, credible evidence. As appellants note, a violation of R.C.
In short, appellee lost approximately three months, August 21, 1995, to approximately November 22, 1995, of productive construction time due to the problems associated with the Ashland easement. When appellee was finally able to commence construction, winter weather conditions had set in, making it extremely difficult for him to lay the foundation. Furthermore, as the trial court pointed out in its judgment entry, the term "working days" was never defined in the parties' contract. Based on such factors, we find that the trial court's refusal to award appellants damages for delay was not against the manifest weight of the evidence. We find that there was competent, credible evidence supporting the trial court's decision. Appellants' Second Assignment of Error is overruled.
Appellants sought a total of $14,490 in damages for underpinning of the footer for the basement foundation walls. Don Davis, in his report, estimated the cost of underpinning at $14,490. Davis also stated that "[a]n engineering report will better identify the actual structural integrity of the ground (base), footings, foundation walls, floor . . ." The trial court denied appellants' request for $14,490 in damages. We do not find that the trial court erred in declining to award $14,490 in damages for underpinning since there was competent, credible evidence supporting the trial court's decision. Crane Engineering Consultants, in a report prepared for appellants, provides, in pertinent part, with respect to the foundation: If step and vertical cracking patterns persist after moisture has been eliminated, stabilization of the foundation footing is normally needed. This can be achieved by underpinning or rebuilding the footing. This can be an extensive and expensive repair. Many times, further investigation is needed (i.e. soil samples taken, and possible excavation along the building to examine the condition of the footing.)
At minimum, the foundation walls require point and tuck work, elimination of the moisture that may contribute to the situation, and monitoring the walls for any additional movement. In some cases, in lieu of monitoring the situation, further investigation may be undertaken at this time since many times the effects of foundation settlement can occur over several years and the remedies can be very expensive.
The clear implication from the language in the Crane Engineering report is that underpinning may be needed in the future depending on whether cracking persists after moisture is eliminated. Since, based on such report, there was competent, credible evidence from appellants' own expert supporting the trial court's decision that such damage was "speculative", we find the trial court's decision in refusing to award damages for the underpinning was not against the manifest weight of the evidence. Appellants Fourth Assignment of Error is overruled.
Appellants selected cabinets on appellee's credit costing $5,179.35, or $1,679.35 more than the $3,500.00 allotted in the contract. Appellee testified as follows when asked whether Appellant Linda Keeton knew the cost of the cabinets when she met with the Amish cabinet maker and appellee:
A. No, she knew there was a $3,500 allowance.
Q. She never knew what they cost?
A. She ordered them, I don't know.
Q. You never gave her an opportunity to —
A. No.
Q. — make changes?
A. Not —
Q. You took total responsibility for the cost of cabinets; do you remember that?
A. No, I don't.
Tr. at 312. Appellants agreed that the $1,679.35 excess for the cabinets was an "extra" that was not authorized in writing as required by the contract. However, the trial court, in holding that the $1,679.35 excess was not an "extra" and that appellee was entitled to a judgment against appellants in such amount, specifically stated in its judgment entry as follows: "Plaintiffs [appellants] made the selection and was [sic] aware of the contract allowance, and (in the court's view) had an obligation to inquire as to the price of items selected. They should not be rewarded by this failure to inquire to the extent of such excess selection of material." We find that the trial court erred in granting judgment to appellee in the amount of $1,679.35 on his claim for an extra in connection with the cabinets and vanities. The contract between the parties expressly provided that "[a]ny deviation from these specifications or plans involving an extra charge . . . must be agreed upon in writing." There is no evidence that there was such a writing between the parties. Appellee, therefore, is not entitled to recover for the "extras" that he provided in connection with the cabinets and vanities. See Sites v. Moore (1992),
Based on the foregoing opinion, appellants' First, Second, Third and Fourth Assignments of Error are overruled. Appellants' Fifth and Sixth Assignments of Error are sustained. This matter is remanded to the trial court for further proceedings consistent with this opinion.
HOFFMAN, J., CONCURS IN PART AND DISSENTS IN PART.
EDWARDS, J. DISSENTS.
Dissenting Opinion
I concur in the majority's analysis and disposition of appellants' second, third, fourth, fifth and sixth assignments of error. I disagree, in part, with the majority's analysis and disposition of appellants' first assignment of error. I find the submitting of false affidavits by appellee does violate R.C.
Dissenting Opinion
I agree with Judge Wise as to the analysis and disposition of the first assignment of error. I agree with Judges Wise and Hoffman as to the analysis and disposition of the second, fourth, fifth and sixth assignments of error. However, I respectfully dissent as to the analysis and disposition of the third assignment of error. Appellants, in their third assignment of error, challenge the trial court's calculation of compensatory damages. Appellants specifically argue that the trial court's calculation of appellants' damages for appellee's breach of its implied duty to perform work in a workmanlike manner was against the manifest weight of the evidence. I agree with appellants that the damage figure awarded by the trial court was not supported by the manifest weight of the evidence. The trial court in its April 13, 1998, Decision, awarded appellants a total of $11,465.00 in compensatory damages due to appellee's breach of contractual duties. The decision reads, in pertinent part, as follows:
"The specific dollar amounts for damages due to plaintiffs were based upon the testimony of Don Davis. It is found by the Court that the following damages have been proven by a preponderance of the evidence to have been proximately caused by defendant's breach of contract duties. The measure of damages is the reasonable cost of material and labor required to place the building in the conditions contemplated by the parties at the time they entered into the contract.
First National Bank of Akron v. Coan, (N.D.Ohio. 1980).
The Court does find the following damages to plaintiffs as a proximate result of defendant Hinkles breach of his contract obligations:
(a) Repair of foundation block wall, excavation around exterior of basement walls to the bottom of the footer, scraping and cleaning of basement walls, waterproofing and backfilling with stone. $3000
(b) Removing and replacing garage concrete apron on east side of house. $800
(c) Install siding at dog pen and install rubber lines for drain gutter. $190
(d) Remove and replace front porch slab. $1410
(e) Repairs of garage and basement floor slabs. $500
(f) Repairs of main support beam in basement with additional 2" x 12's added support column jacks and adequate support bearing plates, also repair of sump pump pipe connection. $1200
(g) Repair of interior dry wall as needed, painting interior walls and ceilings and adjustment of doors. $2700
(h) Removal of excavation debris, rough grade of yard, install shutters, restretch living room carpet, repair gutters and adjust garage doors. $900
(i) Repair/replace back steps to usable condition, including repair of basement stairs.
*It appears that the drawings do show a porch or steps, and the height above ground would imply need for steps. $200
(j) Reimbursement of plaintiffs for advances repairs, including correcting drains, driveway grading, trash removal and repair of air conditioner. $565
TOTAL $11,465
In his itemized report, appellants' expert, Don Davis, a real estate appraiser and consultant, had estimated the total cost to "return the home to a solid structure" at $31,676.07. (This figure includes $14,490.00 for the underpinning addressed in the fourth assignment of error.) The trial court, in its April 13, 1998, Decision, specifically awarded appellants a total of $3,000.00 for repairs to the foundation block, including excavation, scraping, waterproofing and backfilling with stone. However, Don Davis, appellants' expert, testified that the total cost for the same would be $3,829.48. See Transcript of Proceedings at 176-177. Moreover, Davis, in his report, broke down the costs as follows:
Excavate around the exterior of the basement walls to the bottom of the footer. 104 cubic yards at 6.00 per cubic yard $624.00
Install new perimeter drain tile 136' at $7.54 per foot $1,025.44
Scrape and clean exterior basement walls 16 hours at $18.86 per hour $301.76
Spray two coats of basement seal — approximately 1,248 square feet at $.48 per foot $599.04
Backfill with #8 washed stone within two feet of the top of the ground — 100 ton #8 limestone at $10.00 per ton $1,000.00 Labor w/loader to install stone 4 hours at $40.00 per hour $160.00
Backfill remaining two feet with soil to provide a positive grade away from the foundation walls. 22 cubic yards soil at $5.42 per yard $119.24
The above figures total $3,829.48, which is consistent with Davis' competent, credible testimony. Since such figure was unrefuted by appellee, the trial court erred in only awarding appellants $3,000.00 for repairs to the foundation block wall rather than $3,829.48. Such decision was against the manifest weight of the evidence. The trial court, in its April 13, 1998, Decision, also awarded appellants $500.00 for repairs to the garage and basement floor slabs. This court is unable to determine how the trial court arrived at such figure. Don Davis, in his report, listed repairs to the garage floor alone totaling $2,339.71. At the trial in this matter, Davis himself testified that it would cost $2,339.71 "to remove the concrete floor in the garage and replace it." Transcript of Proceedings at 180. Since such testimony was unrefuted by appellant, we find that the trial court's decision to award appellants only $500.00 for repairs to the garage and basement floors rather than $2,339.71 was against the manifest weight of the evidence. In short, we find that the trial court `s determination of damages was against the manifest weight of the evidence. The trial court substituted its own repair figures for the figures testified to by Don Davis despite the unrefuted competent, credible evidence presented by Don Davis, via his testimony and report. We find that Don Davis, via his unrefuted testimony and report, established damages totaling $15,737.07. Moreover, testimony was adduced at trial that engineering services in the amount of $2,000.00 to $3,000.00 would be needed to make the required repairs. Based on the foregoing, we find that the trial court, from the clear and unrefuted evidence, should have awarded appellants a total of $17,737.07 ($15,737.07 plus $2,000.00) in compensatory damages. The trial court's decision to award appellants only $11,465.00 in damages despite unrefuted competent, credible evidence establishing $17,737.07 in damages was against the manifest weight of the evidence. Such decision was unreasonable based upon the testimony and evidence adduced at trial. While I agree with my colleagues that the trial court did not have to accept the credibility of the expert's testimony in toto, the trial court cannot just arbitrarily select damage amounts. Therefore, I would sustain appellant's third assignment of error.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.