Golub Mechanical Contractors v. U. of Akron, Unpublished Decision (3-7-2001)
Golub Mechanical Contractors v. U. of Akron, Unpublished Decision (3-7-2001)
Opinion of the Court
After bidding closed, the University opened the submitted bids and selected its alternates. After calculating the respective contractors' bids, the University determined that S.A. Comunale Co., Inc. (Comunale) was the lowest responsive bidder and awarded it the HVAC contract. In the end, the five separate contracts, including the selected alternates, totaled $4,687,515.
On February 29, 2000, Appellant Golub Mechanical Contractors, Inc. (Golub), one of the companies that submitted bids on the HVAC contract, filed a complaint in the Summit County Common Pleas Court, seeking a temporary restraining order, injunctive relief and declaratory relief. Golub essentially sought (1) an order declaring that the University had violated Ohio's public bidding laws by entering contracts exceeding the base estimate by over 10%, and, (2) an order prohibiting the University and Comunale from entering a contract and proceeding with construction. After evidence was submitted, on March 20, 2000, a magistrate denied Golub's request for a temporary restraining order. Two days later, the trial court adopted the magistrate's findings and decision.
Thereafter, the University moved for summary judgment, claiming it had absolutely complied with Ohio's bidding laws. After briefing by the parties, the trial court granted the motion and entered summary judgment in favor of the University. Golub timely appealed, asserting three assignments of error. The first and second assignments of error have been consolidated for ease of discussion.
The trial court erred in granting summary judgment in favor of [the University and Comunale] as genuine issues of material fact exist and [they were] not entitled to summary judgment as a matter of law.
The trial court erred in improperly applying R.C.153.12 by not finding that the University violated R.C.153.12 and its own bid documents in accepting aggregate bids which total exceeds 10% of the published estimate.
In its first and second assignments of error, Golub has argued that the entire bidding process for the Polymer Engineering Annex Project was illegal and has requested that this Court hold each of the five contracts void. In its effort, Golub has invoked the Ten-Percent Rule, found in R.C.
The University has responded by arguing that Golub failed to include the estimates for the project's ultimate alternates, which were available for review upon request. It has argued, therefore, that the true "entire estimate" was $4,304,292. Based on this amount, the increase was a mere 8.9%, a difference insufficient to void the bidding process under the Ten-Percent Rule. Like Golub, the University has submitted evidence to support its factual allegations.
* * * No contract to which this section applies shall be entered into if the price of the contract, or, if the project involves multiple contracts where the total price of all contracts for the project, is in excess of ten per cent above the entire estimate thereof, * * *.
Golub would have this Court hold that the "entire estimate" means only the entire project's base estimate published in the notice to bidders, reading language into R.C.
This Court now turns to the undisputed, material facts in the case at bar. Comunale submitted the lowest bid on the base and particular alternates selected for the HVAC contract. The entire estimate for the Polymer Engineering Annex Project, available for review pursuant to R.C.
The Court finds that there were reasonable grounds for this appeal.
We order that a special mandate issue out of this Court, directing the County of Summit, Court of Common Pleas, to carry this judgment into execution. A certified copy of this journal entry shall constitute the mandate, pursuant to App.R. 27.
Immediately upon the filing hereof, this document shall constitute the journal entry of judgment, and it shall be file stamped by the Clerk of the Court of Appeals at which time the period for review shall begin to run. App.R. 22(E).
Costs taxed to Appellant.
Exceptions.
___________________________ BETH WHITMORE
BATCHELDER, P. J., BAIRD, J., CONCUR.
Copies of the plans, details, bills of material, estimates of cost, and specifications shall be open to public inspection at all business hours between the day of the first publication and the day for opening the bids, at the office of the department where the bids are received, and such other place as may be designated in such notice. (Emphasis added). Based on this language, estimates of cost are to be made available for public inspection during business hours until the bids are opened. Moreover, R.C.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.