Custom Design Technologies v. Galt Alloys, Unpublished Decision (1-7-2002)
Custom Design Technologies v. Galt Alloys, Unpublished Decision (1-7-2002)
Opinion of the Court
Appellant CDT is engaged in the business of metal product fabrication. In 1998, Galt, a metal alloys producer, began seeking an entity to build a heavy steel platform. On June 10, 1998, CDT submitted a bid to Galt for producing the item as follows, in pertinent part:
"Platform assembly per prints ... labor and material .............. $329,768.00."1 However, Galt did not accept this initial bid.
Upon finding out its bid had not been accepted, CDT set up and held a meeting with Galt to further discuss the platform project. On July 2, 1998, CDT issued a second bid to Galt, indicating in pertinent part:
"Platform assembly per prints ... labor ............. $238,315.00 * * * CDT to locate material; Galt to purchase material." Upon Galt's rejection of the aforesaid second bid, CDT submitted a third bid four days later, reading as follows:
(1) PLATFORM ASSEMBLY PER PRINTS ....... $238,315.00 C.D.T. TO PROVIDE LABOR; NO SANDBLAST — BUFF ONLY; COMMERCIAL PRIMER/PAINT: NO WELD TOP SIDE OF PLATES — STITCH ON BOTTOM C.D.T. TO LOCATE MATERIAL; GALT TO PURCHASE MATERIAL
DELIVERY: WILL BEGIN AUGUST 10, 1998 F.O.B.: C.D.T. FACILITY CANTON, OHIO TERMS: PAYMENT (30) DAYS NET UPON INVOICING QUOTE: VALID FOR (30) DAYS
This July 6, 1998 bid was accepted by Galt with a purchase order dated July 10, 1998. Galt thereafter made two payments on the contract for $73,877.76 and $73,077.02, respectively, for a total of $146.954.78. Galt took the position that the balance of the contract figure of $238,315.00, which amounted to $91,360.22, would not be paid because Galt was owed a credit of the latter sum for materials it had purchased for the platform fabrication.
Nearly a year later, CDT, led by a new company president, reviewed the matter and set up negotiations between the two parties. After these negotiations broke down, CDT filed an action against Galt on November 3, 2000. A bench trial was held on March 23, 2001. On April 16, 2001, the trial court issued its judgment entry, finding the contract terms ambiguous, and concluding that the contract price was meant to include both labor and material. The court therefore held that Galt had paid in full after accounting for materials it had supplied, and thus owed nothing further to CDT.
CDT timely appealed and herein raises the following five Assignments of Error:
I. THE TRIAL COURT COMMITTED PLAIN ERROR WHEN IT FOUND THE CONTRACT OF THE PARTIES TO BE AMBIGUOUS.
II. THE TRIAL COURT COMMITTED PLAIN ERROR WHEN IT FOUND FULL PAYMENT HAD BEEN MADE BY GALT ALLOYS[,] INC.
III. THE AFFIRMATIVE DEFENSE OF ACCORD AND SATISFACTION SET FORTH IN THE ANSWER WAS NOT PURSUED BY DEFENDANT, GALT ALLOYS[,] INC., ON TRIAL OF THIS ACTION AND THUS THE TRIAL COURT FINDING OF FULL PAYMENT IS AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.
IV. THE TRIAL COURT COMMITTED PLAIN ERROR WHEN IT REFORMED THE CONTRACT OF THE PARTIES TO REQUIRE CUSTOM-DESIGNED TECHNOLOGIES TO PROVIDE LABOR FOR CONSTRUCTION OF THE PLATFORM AND TO PERMIT DEFENDANT TO SET-OFF COST OF MATERIALS AGAINST THE LABOR ONLY CONTRACT.
V. THE TRIAL COURT COMMITTED PLAIN ERROR WHEN IT FAILED TO GIVE THE CONTRACT WORDS USED BY THE PARTIES THEIR NATURAL AND COMMONLY ACCEPTED MEANING.
The question of whether a contract is ambiguous is a question of law to which this court applies a de novo standard of review. Ohio HistoricalSociety v. General Maintenance Engineering Co.(1989),
In the case sub judice, the trial court found that "[t]he contract is simply a quote with a few sketchy terms outlined within it. It contains many gaps, and can be read to provide for different meanings." Judgment Entry at 3. A contract is ambiguous if it is susceptible to more than one reasonable interpretation. Hillsboro v. Fraternal Order of Police, OhioLabor Council, Inc. (1990),
CDT's First and Fifth Assignments of Error are overruled.
"The party who asserts payment as a defense bears the burden of proving payment by a preponderance of the evidence." Blackwell v. Internatl.Union, U.A.W. (1984),
We find the trial court did not err in finding Galt made full payment on the contract. CDT's Second Assignment of Error is overruled.
In Witham v. South Side Building Loan Assn. (1938),
CDT's arguments in this regard are without merit, as the aforesaid defenses had no legal bearing on the outcome of the case sub judice. The dispute at issue arose from only one contract, which the trial court interpreted based on the evidence presented, including previous bids between these parties as well as others in this type of industry. Based on the evidence, the trial court simply concluded that Galt's checks for $146.954.78 constituted payment in full after accounting for the costs of materials.
CDT's Third and Fourth Assignments of Error are overruled.
For the reasons stated in the foregoing opinion, the decision of the Court of Common Pleas, Stark County, is hereby affirmed.
Costs are assessed to appellant.
Hon. W. Scott Gwin, P. J. Hon. William B. Hoffman, J. Hon. John W. Wise, J. concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.