Gte Telephone Oper. v. Jh Reinforcing, Unpublished Decision (5-20-2002)
Gte Telephone Oper. v. Jh Reinforcing, Unpublished Decision (5-20-2002)
Opinion of the Court
FIRST ASSIGNMENT OF ERROR:
"THE TRIAL COURT ERRED WHEN IT FAILED TO FIND DEFENDANT/APPELLEE NEGLIGENT, AND, THEREFORE, LIABLE FOR DAMAGES, FOR FAILING TO NOTIFY THE OHIO UTILITIES PROTECTION SERVICE, AS REQUIRED BY O.R.C. SECTION
3781.28 -3781.30 ."
SECOND ASSIGNMENT OF ERROR:
"THE TRIAL COURT'S DECISION, AS A MATTER OF LAW, IS IN ERROR."
A brief summary of facts pertinent to this appeal is as follows. The Ohio Department of Transportation (ODOT) retained appellee to work on a bridge reconstruction project in Sciotoville. As part of that project, appellee was to remove a sidewalk. Appellee's employees began to cut a concrete sidewalk with a saw when they sliced into a conduit that contained appellant's phone cables.
Appellant commenced the action below on April 12, 2000, and alleged that appellee was liable for damage to its cables. Appellant asked for $31,392.47 in compensation. Appellee denied liability. The matter came on for a bench trial on August 29, 2001.
No question exists whether appellee cut into the conduit and damaged the phone cables. The central issue at trial was whether appellee and its employees behaved prudently in the process. To that end, considerable evidence was adduced to show that a "preconstruction meeting" occurred between appellee and various utility representatives. Eric McLaughlin, an ODOT engineer and appellee's employer on the project, testified that the purpose of the preconstruction meeting was to locate utility lines before work began. McLaughlin further related that they were informed that the phone lines ran beneath, not "in," the sidewalk. Because the construction plans only called for the removal of the sidewalk, without any excavation of the ground underneath, appellee's employees were not concerned about the possibility of phone line damage. Don Hadsell, appellee's owner, and project supervisor Jeff Clevenger, corroborated this story. Both witnesses testified that a Randy Chamberlin from the "phone company" had told them, before work began, that the cables were positioned underneath the sidewalk. In particular, Hadsell, related that Chamberlin told him that he could remove the sidewalk and that he would have no problems with the cables as long as he did not dig underneath the sidewalk.
As it turned out, the phone cables were buried or embedded inside the four inch (4") concrete sidewalk. McLaughlin testified that he had never seen cables embedded in a sidewalk. Indeed, Chamberlin, who previously worked for appellant, testified that the company typically buried cables thirty inches (30") under ground and did not embed cables in sidewalks.1 As for the preconstruction meeting, Chamberlin testified that he could not recall telling appellee that he could remove the sidewalk. By the same token, however, he also could not definitively say that he did not approve the sidewalk's removal.
At the conclusion of trial the court found in appellee's favor. The Court explained that appellee acted both "diligently" and "reasonably" in removing the sidewalk. Further, the Court found it credible that phone company representatives told appellee that it could remove the sidewalk as long as it did not dig underneath the sidewalk. The trial court filed its judgment on August 31, 2001. This appeal followed.
We jointly consider appellant's two assignments of error because they raise similar arguments. Our analysis begins from the premise that "[t]here is a positive nondelegable duty imposed on one excavating below ground to inform himself as to whether telephone cables are there so he can avoid damaging them." GTE North, Inc. v. Carr (1993),
Trial court judgments are generally affirmed if they are supported by some competent and credible evidence. See Shemo v. Mayfield Hts.,
After our review of the record in the case sub judice, we conclude that ample evidence supports the trial court's judgment for appellee. Considerable evidence was adduced at the trial below to show that appellee had a "preconstruction meeting" with utility companies in order to pinpoint the underground line location. Moreover, several witnesses, including a representative from ODOT, testified that they were told that appellant's phone lines were buried beneath the sidewalk. Hadsell testified that Chamberlin, a phone company representative, told him that he would be in "good shape" to remove the sidewalk as long as they did not dig underneath the sidewalk. The trial court expressly found this evidence to be credible and held that it was sufficient to show that appellee did not breach its duty to locate the underground cables and that appellee was not liable for damages. We find no error.
Appellant counter argues to the effect that, although appellee may have satisfied its common law duty to inform itself of the location of the phone cables, appellee nevertheless breached a statutory duty and is therefore liable. Specifically, appellant cites to R.C.
"Except as otherwise provided in divisions (C), (D), (E), and (F) of this section, at least forty-eight hours but not more than ten days before commencing excavation, the excavator shall notify the protectionservice of the location of the excavation site and the date on whichexcavation is planned to commence." (Emphasis added.)
The evidence was uncontroverted that appellee did not notify the Ohio Utility Protection Service (OUPS) as required by R.C.
In sum, we agree with the trial court that appellee met its duty to ascertain the location of the utility cables. The fault, if any, for this mishap lies either with the phone company or the party/parties who originally installed the phone cables inside the cement sidewalk.
For these reasons, the assignments of error are found to be without merit and are hereby overruled. We affirm the trial court's judgment.
JUDGMENT AFFIRMED.
The Court finds there were reasonable grounds for this appeal.
It is ordered that a special mandate issue out of this Court directing the Scioto County Common Pleas Court to carry this judgment into execution.
A certified copy of this entry shall constitute that mandate pursuant to Rule 27 of the Rules of Appellate Procedure. Exceptions.
Kline, J. Evans, J.: Concur in Judgment Opinion.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.