Ostendorf v. Bd., Cty. Commrs., Montgomery, Unpublished Decision (8-27-2004)
Ostendorf v. Bd., Cty. Commrs., Montgomery, Unpublished Decision (8-27-2004)
Opinion of the Court
{¶ 2} The events giving rise to the estates' claims are undisputed. In the early morning hours of December 27, 1998, Daniel Ostendorf was a passenger in a car driven by Kevin Lapp when the car was involved in a one-car accident. Both men had been drinking prior to the accident, and their blood alcohol levels were well above the legal limits. At about 2:15 a.m., the car left the roadway on westbound West Alexander-Bellbrook Road as it approached county bridge #0197, which crosses Holes Creek at the border of Washington and Miami Townships in Montgomery County. The road curves slightly as it approaches the bridge, and Lapp failed to negotiate the curve. After hitting a road sign and a mailbox, the front driver's side of the car struck the outer wing-wall on the northeast corner of the bridge, causing the car to flip and to land upside down in the dry creek bed below. The car then burst into flames, and both men were killed.
{¶ 3} The estate of Ostendorf filed a complaint against Lapp's estate, several insurance companies, and the Board. Only the claim against the Board is at issue in this appeal. Lapp's estate also filed a crossclaim against the Board. The estates asserted that the Board had acted negligently and had breached a statutory duty in failing to erect a guardrail that would have prevented the car from falling into the creek.
{¶ 4} The Board filed a counterclaim for declaratory judgment, contending that it had fulfilled its obligations pursuant to R.C.
{¶ 5} 1. "The trial court erred to the prejudice of the appellants when it refused to consider the expert deposition testimony and affidavits of appellants['] expert witnesses peter parsonson and frederick lickert in support of appellants['] motion for summary judgment and in opposition to appellee montgomery county's motion for summary judgment."
{¶ 6} 2. "The trial court erred to the prejudice of appellant by granting appellee montgomery county's motion for summary judgement and denying appellants['] motion for summary judgment."
{¶ 7} Civ.R. 56(C) provides that summary judgment may be granted when the moving party demonstrates that (1) there is no genuine issue of material fact; (2) the moving party is entitled to judgment as a matter of law, and (3) viewing the evidence most strongly in favor of the nonmoving party, reasonable minds can come to but one conclusion and that conclusion is adverse to the party against whom the motion for summary judgment is made.State ex rel. Grady v. State Emp. Relations Bd.,
{¶ 8} As a preliminary matter, we note that the estates' experts, in depositions and affidavits, offered opinions about whether the Board had complied with the requirements of the Revised Code with respect to the guardrails around the bridge. The appropriateness of these opinions is disputed by the parties. The estates attempt to distinguish between "`engineering' decisions and issues" and "`legal' decisions and issues," characterizing the expert opinions as engineering opinions. Without delving into the distinction between "engineering" and "legal" opinions, we simply note that the trial court was the arbiter of all issues regarding what the law required, and it was not required to consider expert opinion on that issue.
{¶ 9} Construing the evidence in the light most favorable to the estate, the trial court concluded that there was no genuine issue of material fact as to whether the guardrails had complied with R.C.
{¶ 10} "The board of county commissioners shall erect and maintain, where not already done, one or more guardrails on each end of a county bridge, viaduct, or culvert more than five feet high and on each side of every approach to a county bridge, viaduct, or culvert, if the approach or embankment is more than six feet high. The board shall also protect, by suitable guardrails, all perpendicular wash banks more than eight feet in height, where such banks have an immediate connection with a public highway other than state highways, or are adjacent thereto in an unprotected condition."
{¶ 11} R.C.
{¶ 12} One of the estates' experts, Peter Parsonson, testified that the Board had not complied with R.C.
{¶ 13} The trial court addressed each of the three circumstances set forth in R.C.
{¶ 14} One of the estates' experts admitted that the guardrail on the bridge extended past the end of the bridge, i.e., the concrete wing-wall, to a point where the bridge was less than five feet high. The photographs also demonstrate this fact. Moreover, the trial court found that there was no distinction between a bridge rail, as discussed by the estates' experts, and a guardrail, because the experts admitted that there was no meaningful distinction. Thus, the trial court properly concluded that there was no genuine issue of material fact as to whether the guardrail on the end of the bridge complied with R.C.
{¶ 15} The estates' experts asserted that the approach to the bridge warranted a guardrail because the height of the approach was greater than six feet as measured by the difference in height between the approach to the bridge and the "bottom of the water" that the bridge spanned. The court concluded that this manner of calculating the height of an embankment was not supported by Ohio law, and that an embankment refers to the area along the side
of the approach to the bridge. See Board of Commrs. v. Darst
(1917),
{¶ 16} Finally, the court turned to the issue of perpendicular wash banks. One of the estates' experts, Parsonson, contended in an affidavit that Holes Creek had perpendicular wash banks in excess of eight feet, which required the county to install guardrails pursuant to R.C.
{¶ 17} The estates correctly point out that the trial court erred in relying on Rogan. The holding in that case was reversed in Bowen v. Kil-Kare, Inc. (1992),
{¶ 18} "Perpendicular wash bank" is not defined in the Revised Code. However, the name suggests, and the estates' expert agreed, that the term refers to a riverbank that is "essentially vertical." In this context, the term "perpendicular" has also been defined as "extremely steep." Jenkins v. Harrison Twp.Trustees (Oct. 4, 1982), Scioto App. No. 1385. However, the supreme court has approved a holding that the term "perpendicular" should not be interpreted literally with respect to wash banks, meaning only a ninety-degree wash bank, because to do so would render R.C.
{¶ 19} The Jenkins court held that a wash bank which fell eighteen feet at an angle of sixty-five to seventy degrees was perpendicular within the meaning of the statute. Likewise, the appellate court in Franks found that "perpendicular" can include a slope of seventy degrees. Franks,
{¶ 20} In this case, Parsonson stated, in a conclusory fashion, that the perpendicular wash banks were "more than eight feet in height where such banks have an immediate connection with the highway or are adjacent thereto in an unprotected condition." Another expert, Ruth Campbell, made a similar statement. These statements mirror the statute. Pursuant to Bowen,
{¶ 21} Parsonson did not provide any specific information regarding the steepness of the bank or its height except for his opinion that the approach to the bridge, as measured from the creek bed to the road, was more than six feet high. Neither Parsonson's nor Campbell's affidavit included any basis for the conclusion that there was a perpendicular wash bank at this location, and neither discussed the slope of the wash bank. From the numerous pictures offered into evidence, it does not appear that the slope approached sixty-five or seventy degrees. In fact, the survey incorporated into the affidavit of Ruth Campbell on behalf of the estates establishes that the wash bank's angle was approximately forty-five degrees, because it illustrates a drop of approximately ten feet over a span of approximately ten feet. As discussed supra, a forty-five degree angle is far less than the angle required to satisfy the definition of a perpendicular wash bank. See Franks,
{¶ 22} Moreover, the trial court observed that the car had left the roadway 194 feet before it reached the wing-wall of the bridge and the bank of the creek. It was undisputed that, at the point where the car left the roadway, the ground was almost level to the roadway and no guardrail was required. It was also undisputed that the car never returned to the road and that it continued along the grassy right-of-way until it struck the outer wing-wall. Even construing all of the evidence in the estates' favor, we are constrained to conclude that there was no genuine issue of material fact as to the existence of a perpendicular wash bank. The civil engineer's evidence offered by the estates' expert suggests an angle of only forty-five degrees for the slope of the wash bank. As a matter of law, we conclude that a forty-five degree angle is not "perpendicular" within the meaning of R.C.
{¶ 23} Finally, the trial court noted that the estates' experts made much of the fact that the corners or wing-walls of the bridge were unprotected. This assertion is debatable, but the trial court disposed of the issue by pointing out that the statute does not require the protection of the bridge's corners. We agree with the trial court that, as a matter of law, R.C. 5911.36 did not impose such a duty.
{¶ 24} In sum, the trial court properly concluded that the estates had failed to create a genuine issue of material fact that the guardrails at the ends of the bridge or along the approach to the bridge had failed to comply with R.C.
{¶ 25} The first and second assignments of error are overruled.
{¶ 26} In its reply brief, the estate of Ostendorf raises a third assignment of error, styled as the "first additional assignment of error."
{¶ 27} "The trial court erred to the prejudice of the plaintiff-appellants when it denied plaintiff-appellant[']s motion to strike defendant-appellee's affirmative defenses as they relate to Ohio Revised Code §
{¶ 28} The Ostendorf estate claims that the trial court erred in failing to strike the Board's affirmative defenses because R.C.
{¶ 29} Pursuant to App.R. 16(C), reply briefs are to be used only to rebut arguments raised in the appellee's brief. An appellant may not use a reply brief to raise new issues or assignments of error. Durham v. Pike Cty. Joint VocationalSchool,
{¶ 30} The Ostendorf estate's "first additional assignment of error" is overruled.
{¶ 31} The judgment of the trial court will be affirmed.
Judgment affirmed.
Fain, P.J., and Grady, J., concur.
Reference
- Full Case Name
- Bernard Ostendorf, Administrator of the Estate of Daniel Ostendorf v. Board of County Commissioners of Montgomery County, Ohio, Bernard Ostendorf, Administrator of the Estate of Daniel Ostendorf v. Brian Lapp, Administrator of the Estate of Kevin Lapp
- Cited By
- 8 cases
- Status
- Unpublished