Sst Bearing. v. Geheb Elec., Unpublished Decision (12-23-2005)
Sst Bearing. v. Geheb Elec., Unpublished Decision (12-23-2005)
Opinion of the Court
OPINION
{¶ 1} Plaintiff-appellant SST Bearing Corporation ("SST") sued defendant-appellee Geheb Electric Industrial Supply Company ("Geheb") for breach of contract, promissory estoppel, and breach of the implied covenant of good faith and fair dealing. Following a bench trial, the trial court ruled in favor of Geheb on all counts. Because the trial court failed to determine whether the statute of frauds applied in this case under R.C.{¶ 2} SST regularly supplied ball bearings to Geheb for Geheb's customer Postal Tech. SST contended that it ordered these goods from an overseas supplier only after it received a purchase order from Geheb. At trial, it was undisputed that, in March 2000, Geheb ordered ball bearings from SST in a purchase order ("PO") numbered 99270. It was also undisputed that, in March 2000, SST placed an order for a little more than 125,000 ball bearings from its overseas supplier. Geheb accepted and paid for approximately 55,000 of these ball bearings, but refused delivery on further shipments made under this purchase order. SST argued below that Geheb had ordered 125,000 ball bearings in PO 99270 and that — even after SST had mitigated its damages by selling approximately 24,000 of the ball bearings to other companies — Geheb owed SST over $50,000 for the balance of this order.1 Geheb claimed that it had ordered only 60,000 ball bearings and that, after accounting for the ball bearings that SST had sold to others, it owed SST nothing.
{¶ 3} SST did not have a copy of PO 99270. And it is unclear from the record whether SST ever received a written order from Geheb. J.D. Varvell of SST testified that Geheb always phoned in its orders for ball bearings and that it never placed written orders. Geheb's witness, Richard Herron, testified that he placed PO 99270 with SST over the phone and also faxed a copy of Geheb's order. Herron stated that, at one point, he had a written copy of PO 99270, but that it had been removed from Geheb's files in the ordinary course of business. Because neither party had a copy of the purchase order in question, SST attempted to establish the terms of PO 99270 through other evidence. Specifically, SST produced a copy of a sales order dated March 2000 from SST to its overseas supplier. The sales order was for a little more than 125,000 ball bearings. C. Winifred Scott, the president of SST, testified that he placed this order based on Geheb's PO 99270, though he admitted that he never saw a copy of the purchase order. SST also produced a copy of a release schedule for 125,000 ball bearings allegedly associated with PO 99270 and claimed that Geheb did not initially object to these release dates. SST also argued that an e-mail from Herron to its customer Postal Tech constituted an admission that Geheb had ordered 125,000 ball bearings.
{¶ 4} According to Herron, Geheb ordered only 60,000 ball bearings in PO 99270. Herron testified that he supplied SST with release dates for 125,000 ball bearings only after denying that Geheb had ordered that many. Herron explained that he gave SST release dates because he was told that SST had to have dates to put "in its system" so that it could "move" the ball bearings in the future. As far as the e-mail, Herron presented an explanation to the court consistent with Geheb's position that the e-mail did not constitute an admission.
{¶ 5} Following a trial and post-trial briefing by both parties, the trial court found in favor of Geheb on all claims. In its sole assignment of error, SST now asserts that the trial court erred by entering judgment in favor of Geheb. Although SST urges this court to apply a de novo standard of review, we are persuaded that SST is raising a manifest-weight claim. The standard of review for a manifest-weight claim is highly deferential. We will not reverse a judgment on the manifest weight of the evidence provided that there is some competent, credible evidence going to all the essential elements of the case. C.E. Morris Co. v. Foley Constr. Co. (1978),
{¶ 7} The parties to this case contend, and we agree, that Ohio's version of the Uniform Commercial Code controls SST's breach-of-contract claim. In pertinent part, R.C.
{¶ 8} Therefore, due to the trial court's failure to make a necessary finding, we must reverse its judgment in part and remand SST's breach-of-contract claim. Should SST elect to retry this claim, the trial court must first determine whether the ball bearings at issue were "specially manufactured." If they were, then the exception to R.C.
{¶ 10} The trial court provided no analysis for its decision finding in favor of Geheb on this claim. Upon a review of the record, however, we hold that the trial court's decision was not against the manifest weight of the evidence, as Geheb presented competent, credible evidence that it never promised to purchase 125,000 ball bearings from SST. C.E. Morris Co., supra. Consequently, we affirm the judgment of the trial court as to this claim.
{¶ 12} Therefore, the trial court's judgment is affirmed in part and reversed in part, and this cause is remanded for a new trial on SST's breach-of-contract claim, or for further proceedings consistent with this decision.
Judgment accordingly.
Hildebrandt, P.J., and Hendon, J., concur.
Reference
- Full Case Name
- Sst Bearing Corporation v. Geheb Electric Industrial Supply Company
- Cited By
- 1 case
- Status
- Unpublished