Short v. Greenfield Meadows Assoc., 07ca14 (6-24-2008)
Short v. Greenfield Meadows Assoc., 07ca14 (6-24-2008)
Opinion of the Court
{¶ 2} The trial court declined to award Greenfield damages on its counterclaim alleging that Short breached the construction contract. On appeal, Greenfield contends that the trial court erred by determining that the proper measure of damages is the diminution in value, instead of the cost to repair. Because unreasonable economic waste would occur if the trial court awarded Greenfield the cost to repair, we disagree. Greenfield further contends that the trial court's judgment to not award it damages is against the manifest weight of the evidence. Because competent, credible evidence supports the trial court's finding, we disagree. *Page 2
{¶ 3} Short contends in his separate appeal that the trial court improperly interpreted the contract specifications regarding his duty to plant grass. Because the trial court correctly interpreted the plain, unambiguous language of the contract provisions requiring that Short use dirt in which grass would grow, we disagree. Accordingly, we affirm the judgment of the trial court.
{¶ 5} Short filed a mechanic's lien against Greenfield's property for $6,300. Subsequently, he filed a complaint to foreclose upon its mechanic's lien. Greenfield filed a counterclaim alleging that Short failed to perform in a workmanlike manner and that he negligently performed the work. Greenfield alleged that the concrete began deteriorating the winter after Short completed the work. Greenfield sought damages for the cost to replace the concrete, which was over $40,000.
{¶ 6} At the bench trial, the parties presented conflicting evidence as to the cause of the concrete's deterioration. Short presented evidence that a severe winter, salt, and Greenfield's failure to seal the concrete caused the damage to the concrete. Greenfield presented evidence that Short failed to properly finish *Page 3 or cure the concrete. One of Greenfield's experts testified that the proper remedy was to remove the concrete and replace it at a cost of $40,997.
{¶ 7} At the end of the trial, the court determined that Short did not perform the grass contract specification in a workmanlike manner in that he did not use proper dirt. The court noted that Short requested $6,300, and Greenfield owed Short $6,000 to properly repair the grass. Therefore, it concluded that Greenfield owes Short $300. The court also found that Short failed to install the concrete in a workmanlike manner. The court stated that, for some reason, the original curing of the concrete was not adequate. However, the court determined that the damage was only cosmetic. As a result, the court found that the proper measure of damages is the current value of the premises as opposed to the property's value had the job been satisfactory. However, because Greenfield failed to present any evidence of the diminution in value, the court declined to award Greenfield damages.
{¶ 8} Greenfield and Short appeal. Greenfield asserts the following assignment of error. "The trial court erred in failing to award Defendant damages based upon the evidence of damages provided by Defendant." Short raises the following assignment of error: "The trial court erred to the prejudice of cross-appellant/appellee by improperly interpreting the contract and its specifications in a manner detrimental to cross-appellant, notwithstanding the plain terms thereof."
"[W]hen separate facts are not requested by counsel and/or supplied by the court the challenger is not entitled to be elevated to a position superior to that he would have enjoyed had he made his request. Thus, if from an examination of the record as a whole in the trial court there is some evidence from which the court could have reached the ultimate conclusions of fact which are consistent with [its] judgment the appellate court is bound to affirm on the weight and sufficiency of the evidence.
The message is clear: If a party wishes to challenge the* * * judgment as being against the manifest weight of the evidence he had best secure separate findings of fact and conclusions of law. Otherwise his already `uphill' burden of demonstrating error becomes an almost insurmountable `mountain.'"
See, also, Bugg; International Converter, Inc. v. Ohio ValleyConverting, Ltd. (May 26, 1995), Washington App. No. 93CA34. *Page 5
{¶ 11} Here, the trial court entered a general judgment and Greenfield did not file a Civ.R. 52 request for findings of fact and conclusions of law. The trial court did orally recite its findings at the conclusion of the bench trial. However, because a court speaks only through its journal, we ordinarily will not consider matters that are not carried over into the court's judgment entry. See State v. King (1994),
{¶ 12} Here, even though Greenfield did not request findings of fact and conclusions of law, we will look to the trial court's oral decision to determine the basis for its judgment.
{¶ 15} "However, if repair would lead to unreasonable economic waste, damages are measured by the difference in market value between the structure as contracted for and the structure as received." Angles v.West, Pickaway App. No. 02CA16, 2003-Ohio-464, ¶ 9, citing Ohio ValleyBank. Economic waste exists when the cost to remedy the defect is grossly disproportionate to the good to be attained. See Capstone Homes,Inc. v. Ruffin (Apr. 13, 2001), Greene App. No. 2000-CA-101; Toth v.Spitzer (Dec. 18, 1998), Montgomery App. No. 17178.
{¶ 16} For example, in Toth, the court determined that repair would cause unreasonable economic waste. In that case, the evidence showed that the building did not have any structural problems and that it was functional, even *Page 8 though it did not meet the precise contract specifications. As a result, the court concluded that because the cost to tear up and replace the structure was grossly disproportionate to the good to be attained, the difference in value was the proper measure of damages.
{¶ 17} The court likewise determined in Tru-Built Garage and LumberCo., Inc. v. Mays, (Jan. 27, 1993), Montgomery App. No. 13432, that unreasonable economic waste would occur to award the costs of repair or replacement. The court noted that the contractor substantially complied with the contract by building a garage usable for the purpose intended and that to award the cost to tear out the roof and rafters and rebuild would result in a windfall to the property owner.
{¶ 18} In Dooley v. Purdum, (Feb. 14, 1997), Champaign App. No. 96CA07, the court determined that economic waste would not occur and, thus, affirmed the trial court's decision to award the cost to repair a driveway, even though the damage award exceeded the original contract price. In that case, the driveway that the contractor installed caused water to run into the garage. The property owner's expert testified that the contractor should have tested the area before installing the driveway to ensure that no water would run into the structure. The trial court found that to correct the water problem, the driveway had to be removed, graded and redone. The trial court determined that the contractor did not perform the work in a workmanlike manner and that he did not substantially comply with the contract. The appellate court thus concluded that because the driveway failed to function properly due to water constantly running into the *Page 9 garage, the cost to repair was not grossly disproportionate to the good to be attained.
{¶ 19} In Capstone Homes, the court also determined that unreasonable economic waste would not occur to award the cost to repair masonry work. The evidence showed not only that the brick and mortar color problems presented cosmetic issues with the home, but that bricks were missing and that the mortar was so weak in some areas that it would eventually deteriorate and cause structural problems.
{¶ 20} Here, the trial court determined that there was "something * * * wrong" with the concrete and that "for some reason the original curing was not adequate." In assessing damages, the court noted that the driveway is functional and that the flaking problem is "cosmetic." The court then determined that the proper measure of damages was not the cost of replacing it with a new driveway, but "the value of the premises as they are now as opposed to what they would have been had the job worked out perfect." However, because the parties did not present any evidence regarding the diminution in value, the court did not award Greenfield any damages on its counterclaim.
{¶ 21} Some evidence exists in the record to support the trial court's decision. Unreasonable economic waste would occur if the court awarded Greenfield the damages it seeks to rectify a purely cosmetic defect. Unlike the situations in Capstone Homes and Dooley, no evidence exists that the concrete driveway lacked functionality or structural integrity. Consequently, the trial court's failure to award Greenfield damages for the cost of replacing the driveway is not against *Page 10
the manifest weight of the evidence. Additionally, because Greenfield failed to present any evidence regarding the diminution in value, the trial court's failure to award this measure of damages is not against the manifest weight of the evidence. See South Shore Cable Const., Inc.v. Grafton Cable Communications, Inc., Lorain App. No. 03CA8359,
{¶ 22} Accordingly, we overrule Greenfield's sole assignment of error.
{¶ 24} Our role in interpreting a contract is to give effect to the contracting parties' intent. See, e.g., Westfield Ins. Co. v.Galatis,
{¶ 25} Conversely, when a contract is ambiguous, a court may consider extrinsic evidence to ascertain the parties' intent. Galatis at ¶ 12, citing Shifrin v. Forest City Enterprises, Inc. (1992),
{¶ 26} Generally, the fact finder must resolve ambiguity in a written contract. Id.; see, also, Crane Hollow, Inc. v. Marathon AshlandPipeline, LLC (2000),
{¶ 27} Here, the disputed contract provision specified that Short was to "[p]roperly grade all disturbed areas, seed and straw." Another provision stated: *Page 12 "At Grassy areas: Backfill with #57 gravel under, dirt along sides and to top of culvert, compact to 100 psi." The court seems to have relied upon the plain and ordinary meaning of these terms. The court looked to the dictionary definition of dirt and concluded that "dirt" meant "something in which vegetation would grow." The court observed that the photographic evidence demonstrated that grass did not grow in the disturbed areas and concluded that Short did not use "dirt," but instead used fill. We do not believe that the trial court erred in interpreting the contract. The contract specified that Short was to use "dirt." As the court noted, the common meaning of "dirt" is not the same as "fill," which the court determined Short used.
{¶ 28} Accordingly, we also overrule Short's sole assignment of error and affirm the judgment of the trial court.
*Page 13JUDGMENT AFFIRMED.
The Court finds there were reasonable grounds for this appeal.
It is ordered that a special mandate issue out of this Court directing the Highland County Court of Common Pleas to carry this judgment into execution.
A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the Rules of Appellate Procedure. Exceptions.
Abele, P.J. and McFarland, J.: Concur in Judgment and Opinion.
*Page 1
Reference
- Full Case Name
- Thomas Kendall Short, plaintiff-appellee/appellant v. Greenfield Meadows Associates, defendant-appellant/appellee.
- Cited By
- 4 cases
- Status
- Unpublished