Dyczkiewycz v. Tremont Ridge Phase 1 Ltd. Partnership

Ohio Court of Appeals
Dyczkiewycz v. Tremont Ridge Phase 1 Ltd. Partnership, 2012 Ohio 5173 (2012)
Jones

Dyczkiewycz v. Tremont Ridge Phase 1 Ltd. Partnership

Opinion

[Cite as Dyczkiewycz v. Tremont Ridge Phase 1 Ltd. Partnership,

2012-Ohio-5173

.]

Court of Appeals of Ohio EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

JOURNAL ENTRY AND OPINION No. 97909

PETER DYCZKIEWYCZ, ET AL. PLAINTIFFS-APPELLANTS

vs.

TREMONT RIDGE PHASE 1 LIMITED PARTNERSHIP DEFENDANT-APPELLEE

JUDGMENT: AFFIRMED IN PART; REVERSED IN PART AND REMANDED

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-652300

BEFORE: Jones, P.J., Keough, J., and E. Gallagher, J.

RELEASED AND JOURNALIZED: November 8, 2012 ATTORNEYS FOR APPELLANTS

Joseph B. Jerome Andrew T. Czarzasty 55 Public Square Suite 1950 Cleveland, Ohio 44113

ATTORNEYS FOR APPELLEE

Thomas G. Lobe Thomas G. Lobe Co., L.P.A. 614 West Superior Avenue Suite 1300 Cleveland, Ohio 44113

Brian C. Salvagni Joseph D. Carney & Associates, LLC 2001 Crocker Road Suite 530 Westlake, Ohio 44145 LARRY A. JONES, SR., P.J.:

{¶1} Plaintiffs-appellants, Peter and Jackie Dyczkiewycz, appeal the trial court’s

decision to terminate the receivership in Cuyahoga C.P. No. CV-652300 and order that the

Dyczkiewyczs pay the receiver’s fees. For the reasons that follow, we affirm in part, and

reverse in part.

{¶2} In 2000, the Dyczkiewyczs entered into a contract with Tremont Ridge Phase I

Limited Partnership (“Tremont Ridge”) to build their house in the Tremont neighborhood

of Cleveland. Shortly after moving into the house, the Dyczkiewyczs experienced

extensive water problems. In 2006, an arbitrator found that the brick veneer and exterior

insulation and finish system were improperly installed, which, in turn, affected the

sheathing, dimensional wood framing, drywall, insulation, glass block, windows, and

doors. The arbitrator further found that Tremont Ridge had breached the contract and

ordered the company to properly replace the above items at its own expense.

{¶3} Tremont Ridge did not abide by the arbitrator’s order, so the arbitrator ordered

Tremont Ridge to pay $400,000 to a third-party contractor to perform the work and also

ordered the company to pay the Dyczkiewyczs’ attorney fees. Tremont Ridge failed to

pay any of the ordered money, claiming insolvency. In 2008, the arbitrator awarded the

Dyczkiewyczs $400,000 in damages plus attorneys fees, for a total of $439,167.89.

{¶4} The Dyczkiewyczs subsequently filed the complaint in the instant case,

requesting a confirmation of the arbitration award. Tremont Ridge initially failed to make an appearance in the action and the Dyczkiewyczs filed a motion for default

judgment, which the court granted. The Dyczkiewyczs then perfected a judgment lien

against Tremont Ridge in Case No. JL-08-326553.

{¶5} The Dyczkiewyczs filed a motion for appointment of a receiver in this case,

but the trial court denied their motion. The Dyczkiewyczs appealed, and this court

reversed, finding that the trial court abused its discretion in denying their motion.

Dyczkiewycz v. Tremont Ridge Phase I, Ltd. Partnership, 8th Dist. No. 91773,

2009-Ohio-495

. This court found:

The instant case is an example of an extraordinary situation. There is evidence in the record that Tremont Ridge may have assets, despite its claim of insolvency. In addition, there is evidence in the record that Tremont Ridge and Sutton are owned by the same individual. Furthermore, Tremont Ridge breached a contract with plaintiffs; failed to specifically perform the contract, failed to pay a third party to perform the contract, failed to pay attorney’s fees, and failed to pay plaintiffs $400,000, after being ordered to do these things in arbitration; and is now claiming insolvency after the court issued a $439,167.89 judgment against it.

Id. at ¶ 16.

{¶6} On remand from this court, the trial court held a hearing and the parties agreed

upon a receiver.1

{¶7} In October 2010, the receiver filed his first report in which he stated that

although the Dyczkiewyczs had requested he initiate various lawsuits against Tremont

The Dyczkiewyczs also filed another lawsuit against Tremont Ridge and other defendants, 1

asserting claims of fraud and piercing of the corporate veil. Dyczkiewycz v. Tremont Ridge Phase I Ltd. Partnership, Cuyahoga C.P. No. CV-711831. In July 2012, the Dyczkiewyczs voluntarily dismissed the case without prejudice. Ridge and its related entities, he had found no evidence that additional litigation would

uncover any assets with which to pay the judgment. He reported that the Dyczkiewyczs

requested, in the alternative, that they be assigned the rights of Tremont Ridge to pursue

actions against related entities; the receiver stated he had no objection to such action if

they could “demonstrate there is no ethical conflict” in the assignation.

{¶8} In March 2011, the receiver filed a second report, indicating that he had

located two assets belonging to Tremont Ridge: (1) a narrow piece of undeveloped land

that apparently had no value and (2) a receivable due to Tremont Ridge from Sutton

Builders for $253,000. In his report, the receiver noted that Keith Sutton was both a

general partner of Tremont Ridge and majority owner of Sutton Builders. The receiver

stated that as of February 24, 2011, Tremont Ridge had a net value of $0, Sutton Builders,

Inc. had a net value of $567,000, and Sutton Builders, LLC, had a net value of -$339,000.

He concluded that none of the entities had assets with which to pay a judgment.

{¶9} The receiver submitted that:

the evidence adduced under oath by the Receiver at the [examination of the debtor, Keith Sutton,] demonstrated the complete financial inability of the entities to provide liquid assets to pay any portion of Plaintiffs’ claim. The evidence further failed to demonstrate even a remote possibility that any of the entities will ever, or at least into the foreseeable future, possess such liquid assets especially in light of the local construction industry situation. {¶10} As part of his report, the receiver included professional accountings of the

related companies and owners that demonstrated massive debts, including reports that

showed that Keith Sutton’s personal statement of financial condition found him at a

negative net worth with an aggregate debt exceeding $4.5 million. {¶11} The receiver further sought leave to resign and asked that the Dyczkiewyczs

be ordered to pay his fees and costs.

{¶12} The Dyczkiewyczs objected to the March 2011 report and requested the court

allow the receiver to transfer his authority to the Dyczkiewyczs. The Dyczkiewyczs also

objected to paying the full amount of the receiver’s fees.

{¶13} In May 2011, the trial court held a hearing at which the parties and the

receiver discussed the receiver’s reports and the various liabilities and alleged assets of

Tremont Ridge. The Dyczkiewyczs claimed they possessed evidence that Sutton

Builders owned 14 properties that should be considered assets of Tremont Ridge. But

both the receiver and Tremont Ridge countered that Sutton Builders was “upside down” on

the mortgages for those properties, i.e., Sutton Builders owed more on each property than

it was worth. The court also noted that Sutton Builders was not a party to the action.

Tremont Ridge further argued that the $253,000 receivable should not be considered an

asset because there was no evidence that Sutton Builders could ever pay.

{¶14} The receiver filed additional reports in June, July, and October 2011. In his

June 2011 report, the receiver stated that upon “further review and reflection,” he had in

his capacity as receiver commenced a legal action for Tremont Ridge against Sutton

Builders to recover the $253,000 receivable, titled Tremont Ridge Phase I Ltd. Partnership

v. Sutton Builders, LLC, Cuyahoga C.P. No. CV-11-756965. In the July 2011 report, the

receiver asked the court to: (1) allow him to assign and quitclaim “a parcel of real property”2 and the $253,000 receivable to plaintiffs for plaintiffs to hold in constructive

trust for all creditors; (2) require plaintiffs to pay receiver fees in the amount of

$27,794.41; and (3) be permitted to resign as receiver.

{¶15} In his October 2011 report, the receiver requested the court: (1) assign and

quitclaim to plaintiffs real property owned by Tremont Ridge, specifically Cuyahoga

County Permit Parcel Number 004-18-151; (2) assign to plaintiffs an “approximately

$260,000” receivable Sutton Builders owed to Tremont Ridge; (3) assign to plaintiffs Case

No. CV-756965 and have plaintiffs designated and substituted as the real parties in

interest; and (4) have plaintiffs hold any funds acquired in constructive trust.

{¶16} Tremont Ridge filed objections to the October 2011 report noting, among

other things, that parcel number 004-18-151 had been deeded from Tremont Ridge to

another entity in 2000.

{¶17} In November 2011, the trial court held a hearing on the receiver’s October

2011 report. In December 2011, the receiver filed a motion to dismiss Case No.

CV-756965 without prejudice and the court dismissed the case.

{¶18} In January 2012, the trial court issued an order (1) allowing the receiver to

resign; (2) denying the Dyczkiewyczs’s and receiver’s request to assign the receiver’s

rights and interests in Case No. CV-756965 to the Dyczkiewyczs, noting that the case had

been dismissed; (3) denying the Dyczkiewyczs’ and receiver’s request to assign Tremont

Ridge’s $253,000 receivable to the Dyczkiewyczs; (4) denying the Dyczkiewyczs’ and

The parcel was not identified in the report. 2 receiver’s request to quitclaim real property to the Dyczkiewyczs; (5) ordering the

Dyczkiewyczs to pay the receiver’s fees in the amount of $27,794.71; and (6) terminating

the receivership.

{¶19} It is from this order that the Dyczkiewyczs now appeal, raising six

assignments of error for our review, the full text of which are set forth in the appendix.

Appellate Rules

{¶20} In the second assignment of error, in which the Dyczkiewyczs claim that the

trial court erred in denying their request to assign to them the rights and interests of Case

No. CV-756965, the Dyczkiewyczs failed to cite to any authority to support their claim.

In the third and fourth assignments of error, the Dyczkiewyczs merely incorporate the

arguments of the other assignments of error.

{¶21} App.R. 16(A)(7) states that appellant shall include

[a]n argument containing the contentions of the appellant with respect to each assignment of error presented for review and the reasons in support of the contentions, with citations to the authorities, statutes, and parts of the record on which appellant relies. The argument may be preceded by a summary.

{¶22} App.R. 12(A)(2) provides that an appellate court “may disregard an

assignment of error presented for review if the party raising it fails to identify in the record

the error on which the assignment of error is based or fails to argue the assignment

separately in the brief, as required under App.R. 16(A).”

{¶23} Although the appellate rules were not complied with here, we recognize that

cases are best decided on their merits; therefore, we will briefly consider the assignments of error.

Receiver

{¶24} R.C. 2735.01 authorizes a court to appoint a receiver in the following

circumstances applicable to this case:

[i]n an action by a * * * creditor to subject property or a fund to his claim, * * * on the application of the plaintiff, or of a party whose right to or interest in the property or fund, or the proceeds thereof, is probable, and when it is shown that the property or fund is in danger of being lost, removed, or materially injured; “[a]fter judgment, to carry the judgment into effect”; and “[i]n all other cases in which receivers have been appointed by the usages of equity.”

{¶25} The appointment of the receiver in this case gave the receiver all rights, title,

and interests of the assets of Tremont Ridge so as to allow the receiver to objectively take

action as an independently operating business. Any assets the receiver located would

then be distributed by the receiver for the benefit of Tremont Ridge’s creditors.

{¶26} The decision to terminate a receivership is in the discretion of the trial court;

thus, such decision will not be reversed absent an abuse of discretion. See Milo v. Curtis,

100 Ohio App.3d 1, 6

,

651 N.E.2d 1340

(9th Dist. 1994), citing Cincinnati, Sandusky &

Cleveland RR. v. Sloan,

31 Ohio St. 1

(1876). This may be especially important in a

decision made by the trial court concerning a complicated matter with which it had

intimate working knowledge.

Milo at 4

.

Assignment of Rights and Interests

{¶27} In the first assignment of error, the Dyczkiewyczs argue that the trial court

erred in denying their motion to have the receiver assign his rights and interests to them. This is essentially the same argument made in the second, third, and fourth assignments of

error.

{¶28} Within these assignments of error, the Dyczkiewyczs claim that they are

entitled to the assignment of Tremont Ridge’s $253,000 receivable, transfer of a parcel of

real property owned by Tremont Ridge, and the right to pursue their claims against

Sutton LLC. To support their position that the receiver should be allowed to assign to

them Tremont Ridge’s assets, the Dyczkiewyczs cite Hoolahan v. Harajli, 6th Dist. No.

L-00-1181,

2001 Ohio App. LEXIS 756

(Mar. 2, 2001). In Hoolahan, a federal court

appointed the appellant as the receiver of a financially troubled Ohio corporation. The

receiver eventually petitioned the federal court to close the receivership. The federal

court granted the motion and authorized appellant to create a creditor’s trust with any

unpaid claims outstanding at the time of the receivership’s dissolution. The appellant then

transferred his interest in a pending lawsuit to the creditor’s trust. In that suit, the

appellant moved to amend the complaint to show the creditor’s trust, rather than the

receiver, as plaintiff. The trial court denied the motion and the appellant moved to

substitute the trust for the receiver.

{¶29} The defendants moved for summary judgment, arguing that when the federal

court dissolved the receivership, the receiver no longer had authority to prosecute the

claim or assign it to a trust. The trial court granted the defendants’ summary judgment,

finding that the receiver was no longer a real party in interest after the receivership was

dissolved. {¶30} The Sixth Appellate District disagreed, finding that the appellant, as receiver,

held residual authority under the receivership to either pursue the claims or assign them

and, as directed by the federal court, elected to assign the claim to the creditor’s trust,

which became a real party in interest. The appellate court noted that “[t]here is some

authority that a party who assigns a pending claim may either continue as a plaintiff or

substitute the assignee.” (Internal citations omitted.)

Hoolahan at * 4

. The court

concluded that the appellant should have been permitted to substitute the creditor’s trust as

plaintiff and the matter should have proceeded to disposition on the merits.

{¶31} The Dyczkiewyczs argue that the receiver in this case is essentially in the

same position as the receiver in Hoolahan because the receiver had unpaid claims against

Sutton Builders. Thus, the Dyczkiewyczs contend, the trial court should have ordered the

receiver to transfer the unpaid claims for the benefit of the creditors — the Dyczkiewyczs

— to avoid wasting those unpaid claims.

{¶32} Tremont Ridge argues that such an assignment “would create an intractable

and irresolvable conflict of interest” because the Dyczkiewyczs and their attorney would

be essentially acting as the receiver. To support its position, Tremont Ridge cites its

proposed expert’s opinion, the Ohio Rules of Professional Responsibility, and R.C.

2735.02, which provides in part that “no party, attorney, or person interested in an action

shall be appointed receiver therein except by consent of the parties.”

{¶33} We agree with Tremont Ridge. Although the Dyczkiewyczs adamantly

argue, and the receiver apparently agreed, that there was no ethical conflict because the receiver would be assigning assets, not his powers as a receiver, the de facto effect of such

action would be to give the Dyczkiewyczs the same powers as the receiver. If the

Dyczkiewyczs were assigned the receivable, they could elect to refile the case against

Sutton Builders (the debtor), and would stand-in as Tremont Ridge (the creditor). In

effect, the Dyczkiewyczs’s attorney would “stand in place” as the receiver in asserting the

claims of the partnership through the assigned rights and duties of the receiver, which

would be in contravention of R.C. 2735.02 and Rule 1.7 of the Ohio Rules of Professional

Conduct.3

{¶34} Further, the trial court did not err in failing to assign any rights and interests

in Case No. CV-756965 to the Dyczkiewyczs because the receiver dismissed the case in

December 2011. The trial court could not permit assignment of rights to a case that no

longer existed.

{¶35} As to the parcel of property the Dyczkiewyczs contend Tremont Ridge owns,

Tremont Ridge offered uncontroverted evidence that it no longer owned the property,

Ohio Rule of Professional Conduct 1.7 states, in part: 3

(a) A lawyer’s acceptance or continuation of representation of a client creates a conflict of interest if either of the following applies:

(1) the representation of that client will be directly adverse to another current client;

(2) there is a substantial risk that the lawyer’s ability to consider, recommend, or carry out an appropriate course of action for that client will be materially limited by the lawyer’s responsibilities to another client, a former client, or a third person or by the lawyer’s own personal interests. having deeded it to another entity in 2000. As to the Dyczkiewyczs’s claim that they

should be allowed to pursue their claims directly against Tremont Ridge and Sutton

Builders, the receiver found and the trial court agreed that Tremont Ridge had no assets

that were in danger of being lost, removed, or materially injured.

{¶36} Hoolahan is easily distinguishable. In Hoolahan, the receiver assigned the

lawsuit to a creditor’s trust. There was no evidence that the creditor’s trust was being

represented by one of the plaintiffs (or one of the plaintiffs’ attorneys). Here, the

Dyczkiewyczs, or their attorney, would essentially serve as administrator of the trust and,

although the Dyczkiewyczs argue that there was no evidence that any other creditors

existed, Tremont Ridge disputed that claim. If other creditors did come forward, the

plaintiffs, as administrators of the creditor’s trust, would develop impermissible conflicts.

Even if no other creditors existed, it would most likely be impermissible for the

Dyczkiewyczs’s attorney to represent both the Dyczkiewyczs and Tremont Ridge through

the assigned rights and responsibilities of the receiver.

{¶37} Based on these facts, the trial court did not err in denying the Dyczkiewyczs’

motion to have the receiver assign Tremont Ridge’s rights and interests to them.

{¶38} The first, second, third, and fourth assignments of error are overruled.

Receiver’s Fees

{¶39} In the fifth assignment of error, the Dyczkiewyczs challenge the trial court’s

order that they be held liable for the receiver’s fees.

The Ohio Supreme Court has held that [p]arties who invoke the jurisdiction and process of a court for the appointment of a receiver by sufficient allegations and showing of necessity therefor, resulting in such appointment, do not become personally liable for the compensation of the receiver and the expenses of administration of an insolvent concern, in the absence of special circumstances calling for the application of equitable principles creating such liability. Such debts and expenses are ordinarily payable out of the corpus of the property.

Richey v. Brett,

112 Ohio St. 582

,

148 N.E. 92

(1925), syllabus. Thus, parties who

invoke the appointment of a receiver may become personally liable for the compensation

of the receiver and the expenses of administration only when special circumstances are

present. See Sec. Dollar Bank v. Yamaha Corp. of Am., 11th Dist. No. 98-T-0059,

1999 Ohio App. LEXIS 2945

(June 25, 1999).

{¶40} “Special circumstances” can arise when

there has been an irregular or unauthorized appointment of a receiver, or where a party has received benefits from the receivership in excess of the amount required to be paid, or where an action has unjustly been maintained without right.

Richey at 587

.

{¶41} R.C. 2333.27 provides that a judge may allow “receivers * * * such

compensation as is allowed for like services in other cases, to be taxed as costs in the case,

and by order, shall enforce their collection from such parties as ought to pay them.”

(Emphasis added.) In this case, there were no assets recovered; therefore, the receiver’s

fees could not be paid out of the collection. In his final report, the receiver asked that the

plaintiffs be required to pay his fees, presumably because he had found no assets of the

defendant from which to recover the fees.

{¶42} But in its order, the trial court did not articulate or find that any “special circumstances” existed that would justify holding the Dyczkiewyczs solely responsible for

the receiver’s fees. Tremont Ridge claims that special circumstances exist because the

Dyczkiewyczs requested the receiver and the receiver fulfilled his duties. But neither the

fact that the receiver could not locate any readily ascertainable assets or the fact that the

Dyczkiewyczs were the party that requested the receiver amount to special circumstances

so as to render the Dyczkiewyczs solely liable for the receiver’s fees.

{¶43} Further, as previously noted by this court, this case presents itself as “an

example of an extraordinary situation,” that included Tremont Ridge breaching its contract

with the Dyczkiewyczs, and failing, after being ordered in arbitration, to (1) specifically

perform the contract, (2) pay a third-party to perform the contract, and (3) pay the

Dyczkiewyczs’ attorney fees. Dyczkiewycz v. Tremont Ridge Phase I, Ltd. Partnership,

2009-Ohio-495, ¶ 16

.

{¶44} Based on these facts, the trial court abused its discretion in ordering the

Dyczkiewyczs to pay the full amount of the receiver’s fees. Therefore, the case is

remanded for the trial court to order the receiver’s fees be split equally between the

parties.

{¶45} The fifth assignment of error is sustained.

Termination of Receivership

{¶46} In the sixth assignment of error, the Dyczkiewyczs argue that the trial court

erred in terminating the receivership because, as a consequence of the termination, they

have been denied all opportunities for relief. We disagree; the Dyczkiewyczs retain the judgment lien against Tremont Ridge in the amount of $439,167.89 plus interest.

{¶47} It was within the trial court’s discretion to consider Tremont Ridge’s legal

argument in relation to all the facts and circumstances of the case, and in doing so, the trial

court could find with a reasonable degree of probability that there were no recoverable

assets.

{¶48} The record reflects the substantial amount of time and effort the receiver

spent trying to locate any assets of Tremont Ridge, which resulted in the filing of five

different reports with the court. After carefully reviewing the record, we are not inclined

to second-guess the court’s decision to terminate the receivership, especially because it

was made in a complicated matter with which the trial court had an intimate working

knowledge for close to four years. Based on these facts, the trial court did not abuse its

discretion in terminating the receivership.

{¶49} The sixth assignment of error is overruled.

{¶50} Accordingly, judgment is affirmed in part and reversed in part. Case

remanded for proceedings consistent with this opinion.

It is ordered that appellants and appellee split the costs herein taxed.

The court finds there were reasonable grounds for this appeal.

It is ordered that a special mandate issue out of this court directing the Cuyahoga

County Court of Common Pleas to carry this judgment into execution.

A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the

Rules of Appellate Procedure. LARRY A. JONES, SR., PRESIDING JUDGE KATHLEEN ANN KEOUGH, J., and EILEEN A. GALLAGHER, J., CONCUR Appendix Assignments of Error

I. The trial court erred in its decision as a matter of law associated with denying plaintiffs’ motion for assignment of rights and interests of receiver to the extent that such ruling is a misapplication of the facts presented. The facts, coupled with and supported by the receiver’s amended final report, established that, contrary to the trial court’s ruling, there exists assets of the defendant that are in danger of being lost, removed or materially injured to the extent that, absent action by the court/receiver, appellee will continue to willfully refuse to exercise its rights to realize those assets, thereby ultimately allowing those assets to dissolve.

II. The trial court erred in its decision, as a matter of law, associated with denying plaintiffs and receiver’s request to assign all of the rights and interests with respect to case number CV-11-756965 and such ruling is inconsistent and amounts to a misapplication of the facts presented to the court.

III. The trial court erred in its decision, as a matter of law, associated with the denial of the request by appellants and the receiver to assign a certain “receivable” of appellee Tremont Ridge Phase I Limited Partnership, owned by Sutton Builders, Inc. as it was clearly established in the receiver’s report that a debt existed of an appellee-related entity owed to appellee Tremont Ridge constituting an asset of appellee. The receiver was charged with identifying the assets of appellee and distributing that asset and other assets for the benefit of all creditors, namely appellants. The judgment of the trial court through its entry is therefore in error in that such order prevents the receiver from performing such actions.

IV. The trial court erred in its decision, as a matter of law, associated with the denial of appellants’ and receiver’s request to assign and quitclaim real property owned by appellee to appellants. The real property in question is owned by appellee and is an asset with a present value and, therefore, as is the duty of the receiver, must be distributed for the benefit of all creditors.

V. The trial court erred in its decision, as a matter of law, associated with ordering the appellants to pay the receiver’s fees in the amount of $27,794.71. The facts presented to the court did not support any grounds for ordering the plaintiff to have to bear the cost of the receiver fees as there [was] no evidence that “unusual circumstances” existed as to the receivership such that appellants should bear the costs of the receivership.

VI. The trial court erred in its decision, as a matter of law, associated with terminating the receivership in its entirety in that the receiver had not performed. Such trial court decision was issued in error such that the receiver was prevented by the trial court from performing his duties (as previously addressed in the previous appeal before the appellate court) as a product of the termination of the receivership. The receiver had identified viable assets that appellee owned and was attempting to distribute them. However such distribution was halted and the assets are again in danger of being lost and/or materially damaged.

Reference

Cited By
3 cases
Status
Published