City of Toledo v. Libbie
Opinion of the Court
As counsel are not present, I will content myself with a very brief statement of this case and of the conclusion arrived at.
Henry Libbie obtained a judgment in the common pleas, at the April term, for two thousand dollars, against the city, and it is now sought in this proceeding to reverse that judgment. There are a number of errors,-assigned. One is: That the court erred in admitting evidence offered by the defendant in error at the trial of said cause against the objection of the plaintiff in error.
That the court erred in rejecting certain requests for charges to the jury made by the plaintiff in error at said trial.
That the court erred in the charge given at the trial of said cause to the jury.
That the verdict rendered at said trial was contrary to the evidence produced thereat.
That said verdict was contrary to law.
That judgment was rendered by said court for tfae defendant in error when it should have been rendered for the plaintiff, in error.
That the court erred in overruling the motion of the plaintiff for a new trial in the court below.
This suit was brought by Mr. Libbie to recover for the failure
A demurrer was filed to this petition, but the overruling of the demurrer is not assigned as error in this petition in error.
The defendant, by his answer to this petition, first denies the propositions made and the acceptance of them and the notification oí such acceptance and the confirmation by the common council — that they did not make the contract. Of course, that was the conclusion of the pleader that they did not make the contract. The allegations of the petition, however, in that regard are not denied. The defendant, however, does deny that any motion or resolution was adopted by the common council prohibiting the defendant from completing his contract or that the street commissioner was prohibí ted, or that he was refusing to go on and construct his walk upon his contract, and also sets out that he made the contract, a copy of which is attached to the petition signed by him.
A reply is interposed which alleges that under the ordinances of the city and under the terms of the contract, before he could proceed in furtherance of what he had contracted to do, that it became the duty of the city civil engineer to fix the grade— the inclination — and to set stakes for him to work by, and that this was not done; that the city did not proceed to do anything under the ordinance and cmtract which they were bound to do before he could further proceed with his contract, and that it would have been unlawful and in violation of the ordinanes of the city for him to proceed without that having been done. Of course this is denied.
The plaintiff in error relies very much upon the verdict of the jury being against the evidence A bill of exceptions was taken, and upon examination of the bill of exceptions we find that what perhaps was very material in determining the issues made by the answer and reply, is not in the bill of exceptionsi
"We find also in this record, although it does not appear that it was formally offered, but was used in the trial of the case and to the jury, a certain paper which contained the lots upon which improvement was to be made, designated by red lines, and it answered the purpose of specifications to a building contract, and it undoubtedly was material in the determination of this case and it appeared to have been used as evidence in the case, and it is not attached to the bill of exceptions; so that there is another reason that it would not be proper for us to undertake to review this case upon the assignment of error that the verdict is against the weight of the evidence. In examination of the record, we find but one question raised, as to the admission of testimony, and that is this:
“Q. On this day, when you were in front of George Ketch-am’s property, state what, if any, direction or communication was made to you by anybody as to the continuance of the work, by any offioers of the city? (Objected to by defendant’s, counsel; objection overruled; defendant exceps.) A. Mr. Tyrel told me what had — what was done in the council room, about as far as the resolution was passed.”
Perhaps it would not have been proper for him to narrate what happened in the council room, but, so far as that answer goes, no one was prejudiced by it, and the further questions which drew out what that resolution was which was passed by the council are not objected to. This is all there is as to Jfchis matter relating to the admission of testimony.
It appeared in this case upon the trial of it, that the plaintiff below had proceeded to and had constructed sidewalks along certain lots and he had received a certificate of assessment for the amount that he had completed and there was no claim made for any amount that was due upon work that he had actually done — that was paid for. The defendant below asked these charges to be giren:
“9. If the plaintiff requested and accepted the assessment without complaining, he thereby waived all further right under the contract, if he had any, with the city.
“10. And having received an assessment in terms like that taken by che plaintiff, he is estopped from claiming anything further by way of damages, under the contract from the city.”
Of course, this challenges us to some extent to look at the issues which were made. There was nothing in the answer but denials. There was no pleading of settlement; none of accord and satisfaction, or of estoppel or payment; there was no issue made upon the pleadings in the case to which those propositions of law could apply. Evidence was properly admitted to show what had been done under the contract, and that the party was proceeding to fulfill his contract when the city caused him to desist from the prosecution of it, but it was not received upon any issue that had been tendered by the defendant below — that is: that he had accepted this in payment or satisfaction or by way of adjustment or any plea of estoppel that would require any such charge to be given, and we think the court very properly refused, under the state of the pleadings to give those propositions of law.
Exception was taken to the charge of the court on the measure of damages and, without taking time to read what the court did charge, it was in effect, that the plaintiff would be entitled to recover the difference between the contract prioe and what it would have actually cost to have constructed the sidewalks — in other words, the profit which he would have made, was the loss which resulted from the failure of the city to perform; and we think that is the proper rule of damages— that would be the loss. In the case of Doolittle v. McCullough, 12 O. S., 360, where a party had been prevented from performing his contract, having, performed a part of it, as in this case he had taken the contract at far less than it was really worth to do the labor, and he brought suit, and the court permitted him to offer evidence to prove what it was reasonably worth to do the work. The contract was abandoned. The supreme court said that was not the rule. It said that he lost nothing: that he had been paid for what he had done and he lost nothig, but if his contract price was in excess of what it would be worth to complete the remainder of the work, that would be the measure of damages. This was certainly the rule which the trial court followed in its charge.
So that disposes of all the questions raised in this record, unless it bo the assignment of error in the petition in error