State v. Citizens Trust & Guaranty Co.
Opinion of the Court
The armory board of state of Ohio, under Sections 5257, et seq., contracted with J. H. L. Barr to build an armory at Batavia. Barr executed a bond in the sum of $9;000 conditioned for the faithful performance of the contract, the Citizens
It was insisted in argument by counsel for the bonding company that the state can not be sued, nor can any lien be acquired on the armory building, or on funds in hands of armory board.
It is so well settled by numerous decisions of the Supreme Court of the United States and of this state, that the state is sovereign and can not without its consent be sued, that it is unnecessary to cite cases on this point. Were this question in issue in this case, it would be disastrous to the bonding company and defeat not only all other creditors but the bonding company
“Mann entered into a contract with Hill to construct a dwelling; Regg, a sub-contractor, agreed to do the brick work; Mann was aware of this sub-contract. Hill, the principal, abandoned the job when the work was about half done; Regg, having nearly completed his sub-contract for brick work, was willing and prepared to go on and complete his sub-contract. There was due Regg, on his sub-contract, when Hill abandoned the job, $122. The owner, Mann, had paid Hill $1,375 on the contract, and had he completed the work there would have been due the additional sum of $1,233. Mann advertised for bids to complete the work, but he rejected all bids and personally completed the dwelling, and the whole cost, including amount paid principal contractor, was $109.84 less than original contract price. Regg, the sub-contractor, filed with the owner an itemized statement of his claim under mechanic’s lien law. The circuit court as conclusion of the law found, (1) the contract was entire and Hill, the principal contractor, forfeited all his rights when he abandoned the contract; (2) that this abandonment worked a forfeiture against the plaintiff as sub-contractor, and that the mechanic’s lien law could not afford plaintiff any remedy.”
It is urged that Sections 8324 and 8325, General Code, part of the mechanic’s lien law, are broad enough to include either the state or the armory board, and this is true if the words “or other public buildings provided for in a contract between the owner, or the board officer, or public authority” would include an armory, and the clause authorizing sub-contractors to file with the owner, board officer or public authority, an itemized statement, would give a sub-contractor a right to a lien on the fund. The mechanic’s lien sections of General Code, are general laws,
The question then remains: does the bond given by the bonding company, for the faithful performance of the contract of Barr, require the bonding company to complete the building at its own expense, and prevent it receiving any money out of the fund in hands of armory board, retained under the law, and the contract ?
It is claimed that the statute authorizing building of an armory, Section 5253, et seq., General Code, makes the bonding company liable to complete the building, and does not give the
“After the bid is accepted the board shall cause a contract and bond to be prepared between its members, as representatives of the state of Ohio, and the contractor. Such contract and bond shall be prepared by the Attorney-General, and provide for the completion of the armory and the protection of the state for the pay of material and employees. It may provide for payment from time to time, in the manner therein specified, but in no ease shall the advance payment exceed eighty per cent, of the bid. In ease of default upon the contract, the board may sue on the bond and advertise for other bids for the completion of the work.”
This being a bond ^prescribed by law and a contract made in pursuance to statute, the statute must read as a part of the contract (Secrest et al v. Harbee et al, 17 O. S., 430; Sorg v. Pike, 27 O. S., 506). The bond is for protection of the state, not for anyone else, and when the armory is completed, the eon-tract is carried out and no cause of action can aceure on the bond. The state has not bought or become liable for any ma-rial entering onto the building, nor has the state paid or become liable to ipay any employee on account of this building. When Barr died the work was nearly 80% completed. His administrator refused to complete the work, and had the bonding company declined, then the state, under law and by express provision of Article 5 of the contract, could provide labor and materials to finish the work and deduct the cost thereof from any money then due and thereafter to become due to Barr, or the state might have re-let the unfinished portion of the work, and if it had not sufficient funds remaining unpaid, it would have a right of action against the bonding company for any deficit. The bonding company, as to creditors of Barr, did not assume to pay his debts, and the fact that the debt was incurred for material that was used in the building did not, nor does it, make a bond simply that a contract shall be carried out liable for any debt of contractor. The state held a double security; it was required to retain at least 20% of the contract price un
Article 9 of the contract authorizes the state to retain out of any payment due or to become due to Barr, an amount sufficient to indemnify the state against any lien or claim. There was no lien or claim against the state at the time of Barr’s death; the administrator refusing to complete the contract, nothing further could be due or become due to Barr.. How then, could any debt, lien or claim for past labor or material for Barr be paid out of money not due at his death, and never earned or| due him or his estate? In the case of Village of Pt. Clinton v. Cleveland Stone Company, 10 C. C., 1, it is held:
“Where a contract for street improvement provided payments should be made the contractor as the work progresses, on estimates of city engineer, 85%, and 15%, to be paid on completion of the work, the contractor abandoned the contract and his sureties completed the contract in order to save themselves, the sureties are entitled to the 15% remaining unpaid as against the lienholders.”
The facts in the ease show that the principal contractor abandoned his work; that up to the time no estimates had been made him; that it afterwards was estimated that he had performed $2,414.48 worth of work; the sureties completed the work, the village paid the sureties the 15%, and it seems that no one questioned the duty or right of the village to pay the
The circuit court of this first circuit, in case of Peal & Bro. v. Board of Education, 12 C. C., 266, an attachment and garnishee case, held:
“That when the sureties complete a job, which had been abandoned by the principal, the sureties are entitled to the monies coming due thereafter on the work, and no liens can attach thereto for a debt due from the principal contractor.”
The authorities cited in brief of counsel for the bonding company are all to the effect that where a contractor abandons his work, the unearned portion of the fund applicable to the completed contract is to the extent that a surety has been compelled to expend money to complete the work, the money of the surety.
The bond in this ease does not bind the sureties to do any thing except to see that Barr completes the contract. At Barr’s death the contract was uncompleted and abandoned; nothing further could by any possible means become due to Barr. Had the state re-let the unfinished work, the 20%, and more if needed, would have been used, and the creditors could not have received any portion of it. It is difficult to see how the bonding company, as surety, by completing the work earned money for the creditors of Barr. Why as to this fund as- to other creditors, does the bonding company occupy any other position than any other person.
“Sureties are never visited with penalties and their liability is never extended beyond the strict letter of the obligation into which they have entered.” State of Ohio v. Cutting, 2 O. S., 1; Smith v. Huseman, 30 O. S., 662.
The answer and cross-petition of Keen & Bro., and Ferris, show that a small portion of the material set out in their respec
The fund will be distributed as follows:
The claim of the bonding company to be paid in full and out of the amount due it, the costs of this action are to be taken.
To Keen & Brother, and Ferris, the amount shown to be due them for material furnished and used after November 12th, the date of the death of Barr; the balance of the fund is to be distributed pro rata among all claimants.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.