Union Gas & Electric Co. v. City of Cincinnati
Opinion of the Court
By consent of counsel this matter was submitted to the court without the intervention of a jury.
The cause of action set forth in the petition is one to recover the sum of $790.64 on an account for gas furnished to the village of Hartwell for street illuminating purposes and the re-location of one of the iamps in said village.
The only evidence offered in support of this claim is the record of the annexation proceedings whereby the village of Hartwell
Therefore, from all the evidence before the court, it is clear that the recovery sought for can not be had for the reason that a municipal corporation is not liable on a quantum, meruit for services rendered, and that in order that a recovery may be had for such services it must be shown that they were rendered under and by virtue of a contract, agreement, obligation or appropriation made and entered into according to statute. City of Wellston v. Morgan, 65 Ohio St., 219; McCormick v. City of Niles, 81 Ohio St., 246; Village of Pleasant Ridge v. Dayton Limestone Company, 17 C.C. (N.S.), 498.
Judgment will be entered for the defendant.