Cleveland v. Connelly
Opinion of the Court
The facts in this ease are that on August 6, 1900, the Cleveland Steam Boiler Works, by D. Connelly, proprietor, entered into a contract with the city of Cleveland to furnish seven steam fire engines, five being of the second size and two of the third size, for the use in the fire department of the city. The contract was made pursuant to competitive bidding, the advertisement being authorized by resolution of the council passed in June, 1900. The advertisement required bids to be tendered not later than 12 o’clock M., July 12, 1900, and contained a stipulation that each bid should be accompanied by a certified check on a solvent bank in the -sum of $2,000 as a guarantee, if the bid were accepted, that a contract would be entered into, that the performance of the contract would, be secured to the satisfaction of the city, and that, in addition to such guarantee, said check should be forfeited to the city as liquidated damages for any failure to comply with the terms of the proposal. By resolution of the council, of July, 1900,
The bidding pursuant to the advertisement, was required to be upon blanks furnished by the board of control and Connelly’s bid, partly printed and partly written, stipulated that the bidder proposed to furnish one or more second and third size -steam fire engines, in accordance with specifications and guarantee accompanying the proposal, at fire station No. 1, within 210 days after the execution of the contract for the same; that for each day that the contractor shall fail to deliver said engine or engines, within the time specified, it is agreed that the contractor shall pay to the order of the director of fire service of the city, $25 per day as liquidated damages for such failure; and, in the itemized specifications as to price for the several sizes of engines, that deliveries are proposed to be made, two engines in 120 days, two engines in 160 days, two engines in 200 days and one engine in 210 days.
The contract was made on August 6, 1900, and the engines were not delivered until May 21, 1901, fifty-one days over and ' above the 210 days within which the 'proposal accepted by the council agreed that they should be furnished. The city of Cleveland thereupon paid the agreed price for the engines, less the sum of $1,275 which it retained as liquidated damages for the delay. Subsequently, the council of the city o.f Cleveland passed a resolution directing the payment of this $1,275. It was not paid and suit was brought.
It is evident that if any one of these questions is decided! adversely to the city, such decision disposes of the whole case. The court below held that the proposition made by D. Connelly and physically attached to the contract, was in law no part of the contract. Passing, however, to the question whether the provision for $25 per day as liquidated damages is to be construed as a provision for stipulated damages, or as in the nature of a mere penalty, as upon a bond given for faithful performance of the contract, the tests applied in such cases are usually these: 1. Is .the subject-matter of the contract of such a nature that the actual damages in case of breach will be entirely uncertain and indeterminate? 2. Were damages evidently the subject of calculation and adjustment between the parties at the time the contract was made? 3. Is the stipulation reasonable? 4. What was the intent of the parties? 5. What was the language employed?
Without attempting formally to discuss or apply these tests in their order, we may note some significant facts shown in the record. The circumstance that the formal contract, as distinguished from the proposition attached thereto, contains no reference to this subject nor any express reference to the paper which does mention it, is itself an indication that the parties did not have the subject of damages so prominently before their minds when they made their agreement as to make it a matter of deliberate calculation and adjustment. Moreover, if the attached paper is properly a part of the contract, the reference therein to the subject of damages is contained in the original form or blank furnished to bidders and not in the portion thereof afterwards filled in. It is a formal provision which does not apply with precision to the plan of installment
It is claimed by the city, however, that there was error in the rejection of certain evidence, which it tendered to show •.that Connelly, by exacting from his subcontractor a contract ¡similar in this respect to the one in question here, and by claiming thereunder the same rights that the city claims here, has evinced his construction of the contract here to be what the city claims. It is not contended that this evidence of res inter alios actae was admissible in order to prevent an unjust result here, but as tending to show how the parties themselves interpreted this contract. We think the evidence was properly excluded. This court has recently held that the procurement" of indemnity against loss from the threatened enforcement of a claim, cannot, of itself, be considered an admission, or in the nature of an admission of liability on such claim.' The cases
Case-law data current through December 31, 2025. Source: CourtListener bulk data.