Goldsmith v. City of Cincinnati
Opinion of the Court
Tbe material facts in this case as we understand them, briefly stated, are these: Neidermeyer entered into a contract with the city of Cincinnati for the improvement and construction of a street of the city; and Spooner & Humpreys were his sureties on such contract. Neider-meyer commenced and prosecuted said work for some time, but was unable from financial embarrassment to complete it, and the city was about to take steps to cancel the contract and re-let it, and look to Neider-meyer and his sureties for any damage that would result from his failure to complete it. This the sureties were anxious to avoid, and negotiated with Evan Evans to have him take an assignment of the contract and complete it — he to pay to the sureties the contract price of the work already done by Neidermeyer. This was verbally agreed to by them, and it was further agreed by them verbally that the amount of the work which had been done by Neidermeyer was to be completed and ascertained by Mr. Caldwell, a civil engineer, whose estimate was to be accepted by the parties as correct. It was accordingly measured and calculated by Caldwell, who made a report to the parties, and on September 13,
A. W. Goldsmith, Trustee.”
On the same day, and to carry out this arrangement, with the knowledge of Evans, another written contract was entered into between the Equitable National Bank of the first part, and said Humprey, Spooner and others of the second part, which recited that whereas the said parties of the second part were sureties on notes given to the Equitable National Bank by Neidermeyer for $11,000, and that the bank was the holder by assignment from Neidermeyer of those contracts with the city, and whereas said contracts have been assigned by said Neidermeyer to Evans for the sum of $7,889.20, which it has been agreed shall be collected by Goldsmith, as trustee, and the proceeds to be applied to the payment of the debts of Neidermeyer, incurred in carrying out said contracts — u was then agreed that said debts should be paid in the following order. 1st. To the payment of debts for labor and materials furnished in carrying out said contracts, and the balance to be paid to the bank on said debt; and the bank thereupon released all liens or claims to any money and for any future work, and for all materials put in said work by said Evans. This,
It is admitted that Evans paid to Goldsmith, as trustee, a sufficient amount to pay all the liens on the work, except that due to the Equitable National Bank, and that this required all of said sum of $7,889.20, except about the sum of $2,500 with the interest thereon, and which he declines to pay, claiming that in his measurement and estimate of the amount of work done by Neidermeyer, Caldwell made a great mistake and gave him, Neidermeyer, credit for a much greater amount than had been done by him, and consequently that Evans is entitled to a credit on this balance, due from him to Goldsmith, in the amount of such mistake.
On the evidence submitted to us, we are of the opinion that there was a very material mistake made by Caldwell in his measurement of the work done on this contract by Neidermeyer, before it was assigned to Evans. His estimate of work so done in grad'ng and excavation was 32,088.67 cubic yards, while the estimate of the city, on the completion of the work by Evans, and after the latter had done a considerable amount of grading and excavation, was but 26,432 cubic yards — making a difference of 5,656.67 cubic yards. We are satisfied that this estimate of the city was correct; and that of Caldwell was erroneous, and therefore that it is satisfactorily shown that Caldwell gave Neidermeyer credit for at least 5,656.67 cubic yards of grading and excavation more than he was entitled to, and probably the error was greater than this in favor of Neidermeyer; but this is not shown with certainty. This over-estimate at 16 cents a cubic yard would amount to about $905.00.
This being so, if the controversy was solely between the parties to the first contract we have referred to, viz.: that between Spooner' & Humpreys of the first part and Evans of the second part, we should feel bound under the law as we understand it, to hold that it having been entered into between these parties in good faith, but acting under a mutual mistake as to a material part thereof, that it should be corrected in that particular.
But in our judgment it does not follow as a consequence, that this contract can be corrected or reformed as against the Equitable National Bank or against Mr. Goldsmith, who was by the parties appointed and constituted as a trustee to receive and distribute this $7,889.20, in a particular manner. Neither the bank or Goldsmith or the other persons who were entitled to liens, or actually held such liens on the fund coming from the city, were parties to the contract which was predicated on this mistake. Certainly both the bank and Goldsmith, and probably the lien-holders who have already been paid the full amount of their claims, knew of the contract and its terms. None of them knew of this mistake, and had no agency in bringing it about, and were in no sense responsible therefor. They simply knew that by the contract Evans, for a good and valuable consideration, had agreed to pay this amount to Goldsmith for them, on the condition that they would release to him their claims or liens on the amount that would be payable to them by the city when the contract >'bon]d be completed, and on the faith of the promise and undertaking of Evans to make such payment to Goldsmith for them, they release all their liens against the fund, and in the ease of the bank, it in effect assigns the contract which it held as collateral to its claims against
Case-law data current through December 31, 2025. Source: CourtListener bulk data.