Doolittle & Chamberlain v. McCullough
Doolittle & Chamberlain v. McCullough
Opinion of the Court
The evidence is voluminous, and it might be difficult for us to determine, from the record, whether or not it warranted the conclusion to which the jury must have arrived, not only that the conduct of Bates, toward the workmen of the plaintiff, was improper, and induced them to leave the work, but also, that the defendants were accountable for
We have no difficulty, however, in coming to a conclusion, in relation to the first assignment of error.
The defendants below requested the court to instruct the jury, that if they found the work to have been done under the written contract, previous to the abandonment of the contract by the parties in November, 1850, that the plaintiff could only recover for the actual amount of the work then done, at the contract price. The court refused to so instruct the jury, but instructed them that, if they believed the contract was terminated by the defendants, against the consent of the plaintiff, he would not be confined to the contract price, but might, in the action, recover what the work done was actually worth.
We regard the exception to the charge of the court, as having respect particularly to this part of the charge; and to this point our attention has been more particularly given.
What, then, is the rule of damages, in an action brought upon a cause of action arising under a contract terminated by the other party against the will of the party bringing the action ? And is it true, that the price of services rendered, or goods delivered under a contract fixing, by its terms, such price, is to be in nowise thereby affected, after the contract has been terminated by the other party, against the will of the party performing ?
This precise question, I believe, has not been heretofore decided by this court. In the case of Taft v. Wildman, 15 Ohio Rep. 123, tried in this court at the December term, 1846, the court say: “ In contracts where the precise sum is fixed and agreed upon by the parties, as in many actions of assumpsit and covenant, the jury are confined to that sum.”
In the case of Alder and another, assignees of Berkill, a bankrupt v. Keighley (H. T., 1846), 15 Meeson & Welsby, 117, Bullock, C. B., says : “ But there are certain established rules according to which they (the jury) ought to find; and here, then, is a clear rule — that the amount which would have been received if the contract had been kept, is the measure of dam
In this view of the case, whether the contract has been fully performed by the plaintiff, or only partly performed, and prevented by the defendant; to obtain remuneration for the services so rendered, the plaintiff might, under our former practice, either commence an action of general assumpsit to-recover the amount such services were actually worth, or an action of special assumpsit, and recover for a breach of the express contract, under which the services had been performed. The only difference would be, that if the action were commenced upon the expressed contract, the plaintiff might have to prove the terms of the contract, and the rendering of the services according to its terms; whereas, if the action were in general assumpsit the plaintiff would only be required to prove the fact of having rendered the services at the instance of the defendant, and the value of the services; and it would then be incumbent upon the defendants to prove the special contract, to take the case out of the implied -contract. But when the special contract is proved, whether by
And if-the action upon the contract so made by the parties, and terminated by the defendants against the will of the plaintiff, be brought to recover damages generally, the same rule would apply, as to the services actually rendered. The party having rendered the services would be entitled to recover at the rate agreed upon and stipulated in the contract between the parties, although of much less value than the price expressed in the contract; and, in like manner, the plaintiff would be restricted to the amount' stipulated in the contract as the agreed price, although actually of much greater value.
The action of assumpsit is termed an equitable action. When brought to recover damages for breach of contract, whether express or implied, it is always for the recovery of money which the plaintiff, by reason of such delinquency of’ duty, on the part of the defendant, is, in equity and good conscience, entitled to demand and receive of him. This is-the argument: it is the duty of parties to perform their contracts ; and where one party has been delinquent, in the performance of his contract, and damage has in consequence resulted to the other party, the party sustaining the damage' has his right of action to recover the damage from the delinquent party. The actual damages resulting to the plaintiff from the breach of the contract by the defendant is the amount §f damage, which the defendant is liable to pay, and which
It is true, that the early English writers, and among which authorities, perhaps, may be mentioned Bacon’s Abridgment and Chitty on Contracts, seem to express the opinion that the contract itself, hardly furnishes any measure of damages; and that the amount of damages is to be left for the .most part in actions on contract, in such cases, in the same manner as in actions of tort, to the discretion of the jury. But the modern authorities are not so,subject to tha*.
Thus, in the case of Farrand v. Bouchell, Harper’s Rep. 83,. the court say, “ in no ease where the action (assumpsit) is for money had and received, goods sold and delivered, or for' work and labor performed, which from the nature of the contract itself furnishes the standard of assessment, are the jury allowed to give more than the amount received with interest, or the value of the articles delivered, or the services rendered.”
The counsel for the defendant in error refer to the case of Clark et al. v. The Mayor of New York, 4 Comst. Rep. 338, as an authority to sustain their claim to recover the full amount of the costs of doing the work which had been done before the contract was terminated. Pratt, J., in delivering the opinion in that case, says : “ It is clear, that under the common counts the plaintiffs can not recover the same amount of damages which they might be entitled to recover in an action for a •breach of the special contract. They must be confined in this-action, either to the price of the work stipulated in the contract, or the actual worth of the work done. When parties-deviate from the t.erms of a special contract, -the contract ‘ price will, so far as applicable, generally be the rule of damages. But when the contract is terminated by one party against the consent of the other, the latter will not be confined to the contract price, but may bring his action for the breach of the contract, and recover all that he may lose bj way of profits in not being allowed to fulfill the contract; oi he may waive the contract, and bring his action on the com mon counts for work and labor, generally, and recover what the work dope is actually worth.” No authorities are referred
This case in Denio, then, is no authority; nor are we aware of any authority for the opinion so expressed by the judge in the case of Clark v. The Mayor, that “when the •contract is terminated by one party against the consent of the other, the latter will not be confined to the contract price; ” •and that, if he bring his action on the common counts for work and labor, he may “ recover what the work done is actually worth ; ” and that “ the actual value of the work and materials must be the rule of damages.”
Indeed, there is no intimation by the court in this case of Clark v. The Mayor, of an intention to depart from the former holdings of the court in that state. In the case of Koon v. Greenman, 7 Wend. 121, the question was directly presented to the court. Greenman had agreed to build two
It is true, in the case of Merrill v. The Ithaca and Owego Railroad Co., 16 Wend. 586, the court hold that when delay is caused by the willful acts or omissions of the party for whom the work is done, originating in a premeditated design to embarrass and throw obstacles in the way of performance by the other party, who, notwithstanding, proceeds, and bestows his time and labor in attempting the completion of the job, until, in despair, he finally abandons the work, the rule that the special contract must control, as to the rate of compensation, no longer prevails, and the party is entitled to recover under a quantum meruit. But the court say, in that case, “ If one-
While it must be admitted that there are cases, and dicta of judges, frequently to be found in the books which seem to sustain the rule given in charge to the jury by the district court, I think the weight of authority, as well as the reason upon which the true rule of damage must necessarily rest, will be found very decidedly opposed to the instruction so given to the jury.
In the case of Haywood v. Leonard, 7 Pick. 181, where the plaintiff was allowed to recover for work done under a special contract, on a quantum meruit, for building the house, not built according to the contract, the jury had been told at the trial to consider what the house was worth to the defendant, and to give that sum in damages; but the court held such instruction wrong, and that the jury should have been instructed to deduct so much from the contract price, as the house was worth less, on account of the departure from the stipulations of the contract. And the same doctrine is held in New York and other states, as applicable in like cases. Indeed, in the case of Clark and others v. The Mayor of N. Y., it was held that where parties deviate from the terms of a special contract to perform work and labor, in an action for work done, the contract price will, so far as applicable, generally be the rule of damages.
But a better illustration of the correctness of the rule ol damage can hardly be found, than is by this case presented
How, then, stood the case between the plaintiff and defendants -under that contract, as shown by the proof upon the trial; and what damage was McCullough thereby shown to-have sustained from the delinquency or wrongdoing of Doolittle & Chamberlain, in regard to the contract between the parties ?
The written contract required McCullough to do all the excavation at eleven cents per cubic yard. The proof shows-that- he proceeded to do the least expensive part of the work, the surface excavation, which, say the witnesses, might be done at from fifty to thirty-three per cent, of the cost per yard, required to do the remaining part of the work embraced in the contract.- The proof also showed that the plaintiff had been fully paid the eleven cents per cubic yard for all the excavation and work by him done under and according to the terms of the written contract. But the plaintiff, it is true, proves that the excavation which he did under the contract, actually cost or was worth from eighteen to twenty cents per cubic yard; and that Doolittle & Chamberlain had terminated the contract without his consent. In this state of facts the law gives McCullough this equitable action of assumpsit to recover from Doolittle & Chamberlain, the damage which their wrongful termination or disregard of the contract has caused to him, McCullough. But McCullough can only recover the amount which he shows he has lost by such delinquency of
The instruction given by the court below to the jury, that the plaintiff was entitled to recover the actual cost of the services rendered, regardless of the price fixed by the express ■contract, would allow the plaintiff to recover a large sum of money from the defendants without consideration and without cause. Indeed, it would allow the plaintiff not only to recover, without any cause of action being shown, but, in. fact, his proof showed that the termination of the contract complained of, had, in fact, occasioned him no loss, but had actually saved
The judgment of the district court must therefore be reversed.
Reference
- Full Case Name
- Doolittle and Chamberlain v. Edward McCullough
- Status
- Published