Opinion of the Court
Among the errors assigned by the city, the only one relied upon in argument is the alleged error of
The question therefore arises whether the defendants in error, as owners of abutting property, and entitled to compensation for the injury caused by the change of the established grade of the street, are also entitled, as a matter of right, to interest on the amount of compensation found due from the date of the injury, and during the time the compensation was withheld.
This is not an action ex delicto, in which damages are claimed for trespass or injury to real property, and is not to. be governed, therefore, by the decisions in actions of tort, cited in argument, and which hold that unless the jury in their discretion give interest under the name of damages, it is not in accordance with legal principles to allow it on unliquidated claims, sounding in damages. Those decisions, it is said in 2 Sedgwick on Damages, 383, note e, are few in number, and cannot be considered of more than local authority, and are at variance with the general rule which now prevails. In Parrot v. The Knickerbocker Ice Co., 46 N. Y. 361, which was an action brought to recover damages caused by a collision between a sailing vessel and a steamer, the court said that in cases of trover, replevin and trespass, in
In making the public improvement of Eighth street, the municipality was in the exercise of a legitimate corporate power. The council had the care, supervision and control of all public highways and streets within the city limits, with the duty imposed of keeping the same .open and in repair, and with authority to ■ grade, change established grades, reconstruct streets, and make pavements and other improvements to facilitate travel and transportation. But, while the city had the right to improve the street by changing the established grade, there was a co-existing right of the owners of abutting property, who had made improvements on their lots in reference to such established grades. It is well settled by the decisions in -Ohio, that if the grade of a street has been established by the corporation, and the owner of a lot in good faith erects buildings thereon, with a view to the established grade, and the corporation after-wards, for the convenience of the public, alters the grade in such a manner as to substantially and materially injure the buildings, and cause the avenue to the place of business of the lot owner, and his use of the street as an incident to his permanent structures, to be blocked up and taken from him, it is as positive and substantial aii injury to private property, and as direct an invasion of private right incident to a lot, as if the erections upon the lot were taken for public use, and it comes manifestly within the spirit of the constitution, which requires compensation for property taken for public use. The easement in the street appendant to the lot is held to be as much property as the lot itself. And
The city, by the improvement of the street and the alteration of the established grade, virtually appropriated property rights of the defendants in error, the benefit and enjoyment of which as they then existed, depended upon the continuance of the grade as then established. “Where compensation is to be made for property, and delay has occurred in obtaining payment, interest is a recognized ele•ment in assessing the value.” White, J., in Gest v. Cincinnati, 26 Ohio St. 280. For damage to the abutting property, ■by reason of the street improvement, the property owners were entitled to full compensation, which should have been promptly made; and if there was not a prompt reparation, it was proper, as an additional means of making the owners whole, to instruct the jury to award interest on the eompensation while withheld- The injury for which full compensation was due, is referable to the time of the change of the grade in 1872 and 1873; and the interest in controversy represents what the property owners might have received, for the use of the compensation allowed, had the same been paid without delay.
In Sutherland on Damages, it is said: “ It being an accepted principle that land taken for public use should be valued, and damages ascertained, as of the date of the taking, payment is then legally due, unless a statute designate some other time; and on general principles, interest should be given from the time when the principal should be paid; or, in other words, from the time the land owner was éntitled to compensation.” The principle, that compensation for property taken by the public, shall either be paid at the time it is taken, or paid with interest, or with a fair allowance for the use of the property during the time it is withheld, was
The Delaware, Lackawanna & Western Railroad Co. v. Burson, 61 Pa. St. 369, was a case in which proceedings were commenced in the court of common pleas, for the assessment of damages for injury done by the railroad company, in locating and constructing a railroad through the land of Deborah Burson. Thompson, C. J., in delivering the opinion of the court said: “ Nor was there error in charging the jury to allow interest. If the plaintiff was entitled to compensation by reason of her property being taken at a particular time, she was certainly entitled to interest as a compensation for its wrongful detention. The company as well as the plaintiff could have had the damages assessed as soon as they pleased after locating the road, and it was no reason for withholding compensation that its amount was unknown or unascertained. As the company was the party to pay, it ought to have had the amount ascertained, and paid it; failing to do so, it has no right to complain at having to meet an incident of the delay in the shape of interest.”
In Parks v. Boston, 15 Pick. 198, the jury, in a highway case, were instructed by the judge, that the complainant was entitled to recover the value of the land at the time when it was taken, with interest from that time, subject to a reasonable deduction if he were consequentially benefited by the widening of the street, or with additional damages if he were consequential^ damnified by the taking of a part of his land and thereby injuring the residue. “It is not,” declared Chief Justice Shaw, “strictly speaking an action for damages ; but rather a valuation or appraisement of an incumbrance created on the plaintiff’s estate, for the use of the public. It is the purchase of a public easement, the consideration for which is settled by such appraisement only because the parties are unable to agree upon it. The true rule would be, as in the case of other purchases, that the price is
In making street improvements, the statute contemplates that there shall be no unnecessary delay in compensating owners for damages to abutting property. By section 2304, of the Revised Statutes, when it is deemed necessary by a city to make a public improvement, twenty days’ written notice of the resolution to make the improvement must be served upon the owners of the abutting property; and by section 2315, any such owner claiming that he will sustain damages by reason of the improvement, must within two weeks after service of such notice, file a claim in writing, setting forth the amount of damages claimed. By section 2316, it is provided that, at the expiration of the time limited for filing claims for damages, the council shall determine whether it will proceed with the proposed improvement or not, and whether the claims for damages shall be. judicially inquired into before commencing, or after the completion of the proposed improvement. Proceedings for the assessment of damages before commencing the improvement are prescribed by the statute. And by section 2321, in all cases where the council determines to assess the damages after the completion of any improvement, it is required that within ten days after the completion of such improvement written application shall be made to the court of common pleas, or probate court of the county, to assess the amount of damages in each particular case.
The defendants in error, and other property owners, within the time required by law, filed their claims for damages. On August 29, 1873, the city passed an ordinance to assess a special tax on real estate bounding on Eighth street, to pay the cost and expense of the improvement, but, the record
To prevent their buildings from being crushed and destroyed by the fill of earth made in the street, in front of the'premises, to a height of eight feet above the former curb of the street, the defendants in error found it necessary to construct a retaining wall. It was proper, we think, to instruct the jury to allow interest on the reasonable cost of such wall, from the time of its completion.
Judgment affirmed.