Ashtabula Gas Co. v. Public Utilities Commission
070rehearing
DECISION ON REHEARING.
(No. 15673
On rehearing: The court adheres to the views stated in the opinion filed herein after the former hearing of the case, but inasmuch as the commission now asserts that the language of its former order inadvertently provided for a charge to be paid to the company in addition to the just and reasonable rate which the commission fixed for the service, and that the language of the order of the commission conveys a meaning not intended by the commission, it is ordered and adjudged that the order heretofore made by this court herein be set aside and that this cause be remanded to the public
Order modified.
Opinion of the Court
The record contains considerable testimony which was offered touching the contentions of the different parties. The results of extensive exáminations by experts, officers of the Gas Company and other witnesses were produced. We have also had the benefit of the written opinion of the Commission, from which it appears that that body in the consideration of the case proceeded in compliance with the requirements of the statute which defines its duties. In the effort to arrive at a just and reasonable rate as required by the statute, it ascertained values, costs, expenses, depreciation and the other elements which are essential to approximating a correct result.
Before this court will interfere with an order of the Public Utilities Commission it must appear from a consideration of the record that its action
The city contends that the inclusion of the charge referred to is unreasonable and unlawful. It must be conceded that there has been considerable confusion and inaptness in the use of the terms, “minimum charge” and “readiness to serve,” in connection with public utilities rate-fixing. The terminology involved in the entire subject is as yet too indefinite and extensive. But there is not much dispute concerning the meaning of the term “minimum charge,” as applied to that service. In substance it means the minimum monthly bill which will be rendered regardless of whether or not the consumer has used sufficient of the commodity to make up that sum at the agreed rate. If the consumer uses as much of the gas as will make up this minimum charge, or more, the minimum charge is absorbed in that sum. It means simply that the consumer binds himself to
Now, as stated, the order of the Commission in this case, after fixing the rate of 36 cents per thousand, is that there shall be “in addition thereto a readiness to serve charge to the distributing com
Section 9329, General Code, contains the provision that no gas company shall charge rent for meters.
Section 3982, General Code, provides that the council may regulate and fix the price which such companies shall charge for the rent of their meters, and such ordinance may provide that such price shall include the use of meters to be furnished by the companies, and in such case meters shall be furnished and kept in repair by the company and no separate charge shall be made either directly or indirectly for the use or repair of them.
In the ordinance -appealed from there was a provision that the company might collect as a “readiness to serve charge” for each meter, each month, such sum as added to the net gas bill for such month will make a total of twenty-five cents, but if the net gas bill registered by the meter for any one month amounts to twenty-five cents or more no readiness to serve charge shall be charged during said month.
It will be observed that this is simply and only a minimum charge; that is, that each customer agrees to pay at least twenty-five cents a month. If he uses that or more there is no ready to serve charge, but it is absorbed in the bill. But in the
By the provisions of Section 614-44, General Code, the city of Ashtabula was empowered to fix the rate and do the things provided for in Sections 3982 and 3983, General Code. These sections provide that the council may from time to time regulate the price of gas, etc., and also contain the provision as to regulating the charge for meters which is above referred to. . The ordinance did not regulate or fix the price which the company could charge for the rent of meters. In legal effect it simply provided for a rate to be charged for gas, and required the use of at least so much at that rate. That ordinance was the thing appealed from.
Section 614-46 provides that if the commission shall be of the opinion that the rate, etc., so fixed by ordinance, is or will be unjust or unreasonable or insufficient to yield reasonable compensation, it shall under the conditions set forth in detail in the section proceed to fix and determine the just and reasonable rate, etc., to be charged during the time fixed by the ordinance. In this case the order of the commission not only found that the rate fixed by the ordinance was unjust and unreasonable and fixed a rate which it found to be just and reasonable, but made the additional charge described.
The section provides that such arrangement, etc., shall be first filed with the commission and approved by it before it is effective. It will be observed that by this section there is an express provision allowing a minimum charge, unless it is made or prohibited by the ordinance under which the utility is operated. There is no mention of a provision for a “readiness to serve charge,” and the presumption is that none was intended to be included or implied, unless the language “providing any other financial device” permits a readiness to serve charge. This language, “any other financial device that may be practicable or advantageous to the parties interested,” is extremely vague and in
Moreover, as pointed out, Section 614-17, General Code, above referred to, contains an express provision allowing a minimum charge “unless made or prohibited by the ordinance.” This ordinance contains what is in effect a minimum charge, though it is denominated a readiness to serve charge in the ordinance. It is “made by the ordinance” and cannot be made by the company in its own schedule. This conclusion follows from the plain implication of the statute.
The Commission found that the rates fixed by the ordinance were unjust and unreasonable. As pointed out, it ordered that the rate should be fixed at not exceeding 36 cents per thousand feet, and in addition thereto a readiness to serve charge of 20 cents per meter per month. The effect of this was to set aside the minimum charge fixed by the ordinance and to insert in its place the readiness to serve charge referred to.
We think it clear that the, portion of the Commission’s order touching the readiness to serve charge and setting aside the minimum charge was
The order of the Commission will be modified by striking out the portion thereof which refers to the readiness to serve charge and inserting therein that portion of the ordinance in question which follows the clause fixing the rate, and as thus modified the order of the Commission will be affirmed.
Order modified and affirmed as modified.