Cleveland Fire. Const. Co. v. Cleveland
Cleveland Fire. Const. Co. v. Cleveland
Opinion of the Court
On February 6, 1919, the Cleveland Fireproof Construction Co. entered into a contract wherein, for a certain consideration, it agreed to complete concrete walls and fire proofing for the Public Hall Building, Cleveland, within one hundred calendar days, the contract stating, “That time was of the essence of the contract.”
It was provided that this work was to proceed in conjunction with the erection of the structural steel frame work of the building. The Construction Co-, was to be given j'ossession of the site by February 6, 1919, but possession was not so given. The city failed to proceed and complete the structural work according to the time schedule specified in the contract, thereby rendering the company unable to perform its work under the contract.
In July, 1919, parties to the suit and all contractors, pursuant to an action for an injunction brought by an adjoining property owner, were restrained by an order of the Cuyahoga Common Pleas from performing any further work on the West side of said building because the building was being erected on a street which had not been duly vacated and acquired for this purpose. This order remained in force until December 4, 1919. Thereafter a new city architect ordered all construction work to stop until further notice, which further delayed the company’s performance six weeks. On July 16, 1920, the company finished its work and on July 10, 1920 gave written notice of its claim for damages arising from aforestated delays.
The- trial court arrested the case from the jury and, upoi^ motion, the city instructed the jury to return a verdict for it on" the ground that written notice of a claim for damages was not given within 72 hours after such damage occurred as provided by the contract.
It is contended that the court erred in directing a verdict on the following grounds:
_ 1. The Company did give written notice of its claim for damages for delays within the time provided by the contract.
2. Whether written notice of its claim for damages for delays was given within 72 hours was a question of fact for the jury.
3. That the stipulation as to the time within which a written notice for damages for delays was to be given did not apply to delays caused by the city.
4. The 72 hour period stipulated in the contract for filing a claim for damages for delays was unreasonable and should have been so declared or left for the jury to determine its reasonableness and application.
Reference
- Full Case Name
- CLEVELAND FIRE. CONST. CO. v. CLEVELAND (City)
- Status
- Published