Greer v. Public Utilities Commission
Greer v. Public Utilities Commission
Opinion of the Court
The commission’s order of September 30, 1959, in its case No. 27800 was a final order from which no appeal was perfected and no application for rehearing was filed within 30 days as required by Section 4903.10, Revised Code. The commission, therefore, has no power to entertain an application for rehearing filed after the expiration of such 30-day period.
The hearing before the commission in its case No. 29141, from the order in which this appeal is taken and in which no evidence was offered but which consisted of arguments on the facts presented in the former proceeding before the commis
The order of the commission is affirmed.
Order affirmed.