National Electrical Contractors Ass'n v. City of Painesville
National Electrical Contractors Ass'n v. City of Painesville
Opinion of the Court
At the time bids were submitted for the Painesville water treatment project, the appellants made no protest or complaint about the bidding procedures. They did nothing until after a contract had been awarded,
Appeal dismissed.
It is conceded that the contract for the construction of the water treatment plant has been awarded to a general contractor and that the work is going forward.