State ex rel. Firestone Tire & Rubber Co v. Industrial Commission
Cases that cite this one
6 later published cases cite this decision.
- State Ex Rel. Fedex Ground Package System, Inc. v. Industrial Commission (Ohio Ct. App. 2009)
- Fedex Ground v. Indus. Com. (Ohio Ct. App. 2008)
- State Ex Rel. Pactive Corp./t. v. Harvey, Unpublished Decision (9-28-2004) (Ohio Ct. App. 2004)
- State ex rel. Roadway Express, Inc. v. Industrial Commission (Ohio 1992)
- State ex rel. Youghiogheny & Ohio Coal Co. v. Industrial Commission (Ohio 1992)
- State Ex Rel. Collins v. Indus. Comm., Unpublished Decision (12-30-2004) (Ohio Ct. App. 2004)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
A claimant who is capable of sustained remunerative employment is not permanently and totally disabled. State, ex rel. Jennings, v. Indus. Comm. (1983), 1 Ohio St. 3d 101, 1 OBR 135, 438 N.E. 2d 420. Firestone’s argument is contingent upon that finding: If claimant did not engage in sustained remunerative employment, then no viable basis for opposing continued permanent total disability compensation exists.
Firestone asserts that evidentiary review and identification are unnecessary since the parties “agree” that “some evidence” of sustained remunerative employment exists. This latter claim is based on claimant’s failure to appeal the commission’s order, which Firestone maintains is tantamount to an admission that “some evidence” is present. We are unpersuaded.
The alleged agreement between the parties does not bar us from performing our review. Merely because the parties agree that “some evidence” exists does not make it so. In State, ex rel. O.M. Scott & Sons Co., v. Indus. Comm. (1986), 28 Ohio St. 3d 341, 28 OBR 406, 503 N.E. 2d 1032, the parties’ “agreement” that mandamus was the proper vehicle for relief did not preclude us from holding otherwise.
In the present case we cannot reach the merits of Firestone’s abuse-of-discretion allegation without first finding “some evidence” of sustained remunerative employment. Being unable to do so, we remand this cause to the commission in accord with the appellate court’s decision, including compliance with Mitchell, supra.
Accordingly, the judgment of the court of appeals is affirmed.
Judgment affirmed.