Ohio Supreme Court, 2014

In re Comm. Rev. of Capacity Charges of Ohio Power Co.

In re Comm. Rev. of Capacity Charges of Ohio Power Co.
Ohio Supreme Court · Decided July 11, 2014
139 Ohio St. 3d 1476; 11 N.E.3d 1197

In re Comm. Rev. of Capacity Charges of Ohio Power Co.

Opinion of the Court

Public Utilities Commission, No. 10-2929-EL-UNC. This cause is pending before the court as an appeal from the Public Utilities Commission of Ohio.

Upon consideration of the application of appellant/cross-appellee, FirstEnergy Solutions Corp., for *1477dismissal of its cross-appeal, it is ordered by the court that the application for dismissal is granted. The cross-appeal of FirstEnergy Solutions Corp. is dismissed, and the case remains pending on all other appeals.