Ohio Supreme Court, 2015

In re Ohio Power Co.

In re Ohio Power Co.
Ohio Supreme Court · Decided February 2, 2015
141 Ohio St. 3d 1460; 24 N.E.3d 1179

In re Ohio Power Co.

Opinion of the Court

Public Utilities Commission, Nos. 11-4920-EL-RDR and 11-4921-EL-RDR. This cause is pending before the court as an appeal from the Public Utilities Commission of Ohio, and is scheduled for oral argument on Tuesday, February 3, 2015.

It is ordered by the court, sua sponte, that oral argument in this case shall proceed as follows: Ohio Power Company shall argue first and is permitted ten minutes of oral-argument time. Industrial Energy Users-Ohio shall argue second and is permitted ten minutes of oral-argument time. Public Utilities Commission of Ohio shall argue third and is permitted ten minutes of oral-argument time.

Ohio Power Company and Industrial Energy Users-Ohio may reserve any portion of their allotted time for rebuttal, and rebuttal shall proceed in the same order as specified above.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.