Slats Honeymon Drilling Co. v. Union Oil Co. of California
Slats Honeymon Drilling Co. v. Union Oil Co. of California
Opinion of the Court
This is an action on an Acreage and Dry Hole Contribution Agreement entered into between the plaintiff and the defendant on December 22, 1960, and specifically involves the dry hole contribution provisions of said agreement.
In connection with this agreement the plaintiff drilled a well in Kingfisher County, Oklahoma, known as the Wrob-bel-Geis No. 1, having commenced the well on or about March 3, 1961, within the prescribed time as extended, and the drilling operation having been completed on or about May 9, 1961. By letter dated August 21, 1962, the plaintiff made demand of the defendant for dry hole money in the amount of $17,900.00 pursuant to the aforementioned agreement.
The provisions of the said agreement pertinent to this litigation provide:
“Further, Union agrees when, in Union’s opinion, this well has been completed in the manner and to the depth above specified, and when evidence has been obtained that the well has been plugged and abandoned as a dry hole, to pay to the Operator the sum of $2.00 per foot of all hole drilled, not to exceed a total of $17,900.00.”
******
“The assignment of acreage and the dry hole contribution pertaining to each of the three tests heretofore mentioned will be made separately within 30 days after the completion of each of these three tests and will not be dependent or be conditioned upon the drilling or completion of each other, except that each test must be commenced according to the time table established by the drilling and completion of the first test.”
******
“Time shall be of the essence of this agreement in all its parts.”
The evidence reveals that the Wrobbel-Geis No. 1, which was the first well covered by said agreement, was drilled as a wildcat to the Manning formation at about 8762-8792 feet and was drill-stem tested showing approximately 730,000 cubic feet of gas. The well was then drilled down to the Mississippi Lime at approximately 9,280 feet, at which time casing was set and the Mississippi Lime tested but found to be without a show. The operator then backed up to the Manning, perforated, sand-fractured and acidized the formation and had a showing of approximately 965,000 cubic feet of gas. For 16 days gas from this formation was vented and certain tests were made and the well cleaned out. Approximately 11,000,000 cubic feet of gas was so vented. Tests to improve production were authorized to October, 1961. It appeared that the well would make approximately 700,000 to 800,000 cubic feet of gas per day. At this time the nearest pipe line was six miles to the east and belonged to the Oklahoma Natural Gas
On June 8, 1961, efforts were undertaken by the plaintiff to obtain action on the part of Oklahoma Natural to extend its pipe line to this well. These efforts continued for several months with Oklahoma Natural showing interest but eventually the same proved fruitless when in July of 1962 this pipe line was extended but in a northerly direction and away from this well even though in the process the line came one mile closer to or approximately five miles from the well. Studies were also made by the plaintiff with reference to laying its own pipe line at its own expense to the nearest pipe line which was found to require an outlay in the neighborhood of $30,-000.00 for the line and approximately $6,000.00 for the necessary equipment to connect the well with the line and transport the gas from the well into the nearest pipe line. Sometime after the above well was drilled further exploration in the area was undertaken by others with a well started in the section immediately north of the subject well.
On July 3, 1961, the plaintiff wrote the defendant, bringing the defendant up to date with reference to the posture of the well, termed the well as non-commercial, requested advice with reference to the advisability of abandoning the well and also called for any suggestions the defendant may have with reference to any other action that should or might be taken with reference to the well. The defendant did not answer this communication.
While the Corporation Commission had not established spacing units for this area it was understood and agreed by all that a spacing order of 640 acres was proper and would be fixed. By the summer of 1962 the closest producing well was over five miles from the subject well. The well in the section to the north was completed on the 7th day of June, 1962, showed practically no porosity and only approximately two feet of the Manning formation. The same was plugged and abandoned as a dry hole.
After the north offset was plugged and abandoned as dry and the nearest pipe line was extended away from the well, by letter dated August 21, 1962, the plaintiff notified the defendant that it had decided to plug and abandon the subject well as a dry hole and made request for the payment of the stipulated dry hole money from the defendant. The well was plugged in October, 1962, and defendant furnished with the record of such action. The defendant refused to remit and this litigation ensued.
Briefly stated, it is the contention of the plaintiff herein that the subject well was a dry hole within the meaning of the pertinent provisions of said agreement even though the same was capable of producing some gas but which was not reasonably marketable. Further, that the plaintiff as the operator was entitled with due diligence to watch and await developments with reference to other drilling activities in the vicinity and pipe line extensions and was not restricted by the terms of the agreement or any usage of the oil industry to a particular period of time within which it had to plug and abandon the well, declare the same to be a dry hole and make demand for the dry hole money. Lastly, the plaintiff asserts that with reference to laying its own pipe line some five miles in distance and hooking up the well through this
The position of the defendant herein, briefly stated, is that the subject well was not a dry hole within the meaning of said agreement, inasmuch as the same was capable of producing some gas. Further, that time being of the essence of this contract, the above mentioned 30-day provision in the contract should be enforced against the plaintiff following the completion of drilling on May 9,1961, as the time within which plaintiff must plug and abandon, declare the well to be a dry hole and make demand of the defendant for dry hole money and, further, that according to its economics the plaintiff was not warranted in failing to expend the additional sum of $36,000.00 to build its own pipe line and connect the well to the nearest pipeline and thus provide the necessary transportation facilities to provide a market for the gas that could be produced from the well. Defendant also pleads that plaintiff was under a requirement to elect whether the well was dry or a producer and that plaintiff made such an election to the latter effect and is bound thereby, and further pleads that plaintiff is now es-topped to claim the well to be a dry hole.
The Court will now dispose of the plea of election for the reason that a requirement to elect is not found in said agreement and defendant has presented nothing to the Court by either evidence, law, or usage to support such as a defense under the facts of this case. Moreover, the Court specifically finds that the plaintiff by its conduct and statements with reference to the well cannot be said to have elected at any time to consider the well a producer under the said agreement of the parties and forego the dry hole money. The Court will also now dispose of the plea of estoppel for the reason that the evidence wholly fails to establish the essential elements necessary to support this plea. This is to say that the evidence fails to establish any false representations by plaintiff to defendant as well as any of the other essential elements of the defense of estoppel. See Continental Oil Co. v. Rapp, Okl., 301 P.2d 198.
Thus, we have three principal issues in this litigation, as follows:
1. Can a well be a dry hole under said agreement even though it is capable of producing some gas if there is no available pipe line and no reasonable ability to market the gas from the well and realize any income from the operation?
2. Under the terms of the agreement, was the operator entitled to watch developments and wait until August of 1962 to notify defendant of intent to plug and abandon the well, declare the same to be a dry hole and make demand for the dry hole money, or was it necessary for the operator to do so within some shorter prescribed or fixed period of time under the agreement or usage in the oil industry?
3. Was the plaintiff justified in not building its own pipe line to obtain a market for the gas or is defendant bound by the plaintiff’s decision not to build its own pipe line in the absence of bad faith, fraud or unconscionable conduct?
With reference to whether or not the well is to be considered a dry hole under said agreement, the Court is faced with a lack of pertinent authorities' in this precise area. The closest case appears to be Humphrey v. Placid Oil Co., D.C., 142 F.Supp. 246, affirmed 5 Cir., 244 F.2d 184, which, while not directly in point, would appear to recognize that a dry hole is one not capable of producing oil or gas in paying quantities. An analogy to the proposition here involved would be the matter of the extension of a lease past the primary term by a well which must be in production. The courts
In Hanks v. Magnolia Petroleum Company, Tex.Com.App., 24 S.W.2d 5, the Supreme Court of Texas considered what elements were to be included in the “operating costs” of the lessee in connection with whether or not the well was producing in paying quantities. In the- determination of that question the court held:
“Unlike oil, gas cannot be produced and stored. In order that it may have a value, there must exist pipe lines through which it may be marketed. If no such facilities exist in the vicinity in which a gas well is brought in, the question as to whether the gas produced.by such well is in paying quantities must necessarily depend upon the cost of construction of facilities for carrying such product to a prospective market and the price received therefor. The returns from the sale thereof must be such as would leave a profit in marketing the gas under such conditions.”
In Archer v. Skelly Oil Company, Tex. Civ.App., 314 S.W.2d 655, the court said:
“ ‘What might be determined to be gas in paying quantities in one well would not be so considered in another located in a different territory. A well producing much less gas than the one drilled by the plaintiff in error might be in paying quantities because of existing pipeline facilities furnishing a means of marketing the gas at a profit above the cost of operating the well. On the other hand, a well producing a large amount of gas drilled in a territory remote from any market and without pipeline facilities might not be in paying quantities, unless it was shown that the amount of gas produced was sufficient to justify the construction of transportation facilities and the marketing of such gas would yield a return over and above the expense of providing the same.’ ”
Thus, the Court finds that this well was a dry hole under said agreement notwithstanding its ability to produce some gas inasmuch as under the circumstances here present the gas was not reasonably marketable, could produce no income to the parties, in fact never produced any income to the parties, and such well must therefore be deemed to be one not capable of producing oil or gas in paying quantities and a dry hole.
With reference to the second proposition above set out, the Court is unable to obtain from the language of said agreement the result urged by the defendant. In the first place, the Court finds that the 30-day period mentioned in the agreement does not relate to any duty required of the plaintiff as operator but rather is confined to the period within which defendant must assign acreage and pay the dry hole money after being presented with evidence that the well has been abandoned and plugged as a dry hole. Also the Court is unable to attach to the “time shall be of th'e essence” sentence in the agreement, the import urged by the defendant. This agreement is full of many specific dates with reference to the commencement of the three wells and other details. The Court believes that this sentence relates only to those parts of the agreement which contain and prescribe some definite date or definite time period within which
The third proposition is connected with the first proposition. The plaintiff as operator evaluated the capabilities of the well when drilling was completed in May of 1961, attempted to cause existing pipe lines to be extended to the well, promptly investigated the matter of the cost of laying its own pipe line to the nearest existing pipe line. Then in the summer of 1962 when further data was obtained from the dry offset to the north and other operations in the vicinity and the nearest pipe line was extended away from the well, all of which information was also available to the defendant, the plaintiff re-evaluated the capabilities of the well, gave consideration to the necessary expense in laying its own pipe line and under the economies of the situation reached the conclusion that such action was not warranted, was not feasible and should not be accomplished in this case.
In this re-evaluation the plaintiff fairly concluded that the gas reserves of this well were only % to one billion cubic feet instead of between 2 to 2y% billion cubic feet; that the daily allowable for this well would permit only 270,000 cubic feet of gas per day to be produced; that it would not be economically feasible to expend the money to lay such a pipe line unless the well had gas reserves of 3 to 4 billion cubic feet. In the meantime, plaintiff sought the advice of the defendant in this area and none was forthcoming. The defendant at the trial now presents evidence regarding the economics of the situation which the defendant urges would show that had the plaintiff laid such a pipe line at its expense it would receive from such action ample income to pay for the same, pay for the operating expenses of the well and make a profit to the plaintiff. However, defendant’s expert witness Hamilton testified that he couldn’t say for sure that the pipe line would pay out. Both parties agreed during the trial that this well belonged to the plaintiff and that by reason thereof the plaintiff had exclusive authority with reference to such matters
It is, therefore, the finding, conclusion and decision of the Court that the well involved in this litigation is deemed to be a dry hole under the agreement of the parties entitling the plaintiff to the prescribed dry hole money; that the plaintiff conducted itself as a prudent and reasonable operator in connection with attempting to make the well capable of producing gas to the market and under the circumstances was not restricted in point of time in this connection and in demanding dry hole money except to be reasonable and prudent under the circumstances. The Court further finds that the plaintiff was supported by reliable data and advice and also acted in good faith, without fraud or bad motive in deciding not to lay approximately five miles of pipe line at its own expense but rather to plug and abandon the well as a dry hole.
Accordingly, plaintiff is entitled to judgment herein as prayed for. Interest would be recoverable from November 15, 1962, at the legal rate. 23 O.S.A. § 6; Ottinger v. United States for the Use of Brown, 230 F.2d 405 (10 Cir.Okla.).
Counsel for plaintiff will prepare an appropriate judgment in conformity with the foregoing and present the same to the Court for execution and filing herein.
Reference
- Full Case Name
- SLATS HONEYMON DRILLING COMPANY, a corporation v. UNION OIL COMPANY OF CALIFORNIA, a corporation
- Status
- Published