Opinion of the Court
Petitioners seek review of LUBA’s dismissal of their appeal from the City of Hillsboro’s adoption of an ordinance pertaining to property located in the area of an extension segment of the Westside Light Rail project. We affirm.
The ordinance amends the city’s zoning ordinance, and was adopted pursuant to ORS 197.610 to ORS 197.625 in April 1994. Petitioners filed their notice of intent to appeal to LUBA in January 1995. LUBA granted the city’s motion to dismiss the appeal as untimely. ORS 197.830(8), which governs the time for appeals to LUBA, provides, as material:
“A notice of intent to appeal a land use decision or limited land use decision shall be filed not later than 21 days after the date the decision sought to be reviewed becomes final. A notice of intent to appeal plan and land use regulation amendments processed pursuant to ORS 197.610 to 197.625 shall be filed not later than 21 days after the decision sought to be reviewed is mailed to parties entitled to notice under ORS 197.615.”
Petitioners do not appear to contend that any of them was entitled to notice under ORS 197.615, which sets forth the requirements for local government notices regarding amendments to acknowledged land use regulations. They also do not argue that they were entitled to notice under any other state statute. They argue, however, that petitioner Hedricks was entitled to a prehearing notice under provisions of the city’s zoning ordinance. Therefore, they maintain, the time for him to appeal under ORS 197.830(8) was tolled by ORS 197.830(3). The latter provides, in relevant part:
“If a local government makes a land use decision without providing a hearing * * *, a person adversely affected by the decision may appeal the decision to the board under this section:
“(a) Within 21 days of actual notice where notice is required; or
“(b) Within 21 days of the date a per son knew or should have known of the decision where no notice is required.”
ORS 197.830(8) defines two distinct 21-day appeal periods: the first, for land use or limited land use decisions, runs from the time of their finality; the second, for amendments to land use regulations under the post-acknowledgment statutes, ORS 197.610 to ORS 197.625, runs from the time that the notice specified in those statutes is given to persons entitled to notice under them. The city argues that neither period can be extended under ORS 197.830(3) by virtue of a failure to give notice pursuant to a local provision.
LUBA reasoned in Leonard that, if a local government fails to give a person a prehearing notice required by state or local law, the local government has effectively failed to provide a hearing as to that person, and his or her time for appealing is therefore tolled until the applicable post-decision notice or constructive notice described in ORS 197.830(3) occurs. The city contends that Leonard was wrongly decided in its entirety, and especially insofar as it permits local provisions to affect the state law question of LUBA’s jurisdiction. Because we conclude specifically that the time that ORS 197.830(8) prescribes for appealing a post-acknowledgment amendment to a land use regulation cannot be extended in this manner, we need not address the broader ramifications of the city’s argument relating to Leonard and to LUBA’s jurisdiction.
Under petitioners’ reading, ORS 197.830(3) makes it possible for a local notice provision, which has no analog in state statutes, either to alter the time at which an unappealed amendment is deemed acknowledged under those statutes or to extend the period for appealing such an amendment beyond the time that it has been deemed acknowledged under the statutes. Either of those effects would distort the roles that the post-acknowledgment statutes assign to the appeal process and to the finality of acknowledgments. In the light of their text and context, it is not plausible to interpret ORS 197.830(3) and (8) — as petitioners do — as allowing the fundamental operation of the statutory post-acknowledgment process to be a variable of, or a hostage to, locally adopted procedures.
We conclude that the appeal period was not tolled. The appeal was untimely under ORS 197.830(8), and LUBA was correct in dismissing it.
Affirmed.
The basis for LUBA’s decision made it unnecessary for it to make a factual determination concerning Hedricks’ assertion that he did not and should not have known the relevant fact until nine months after it occurred.