Carter-Holmes v. Sousa
Carter-Holmes v. Sousa
Opinion of the Court
Plaintiffs in a legal malpractice action appeal from a directed verdict for defendant. The trial court concluded that plaintiffs’ proof of damage from defendant’s alleged negligence was insufficient as a matter of law. We reverse and remand.
In 1988, plaintiffs asked an insurance agency to help them obtain insurance coverage for a four-plex apartment building they owned in Northeast Portland. They told the agency’s representative that they required insurance for the cost of replacing the building, rather than for its actual cash value. The agency secured coverage with North Pacific Insurance Company. Although the policy’s limits were consistent with cost of replacement coverage, unbeknownst to plaintiffs the policy covered the building only to the extent of its actual cash value.
In 1989, the building was severely damaged by fire. When plaintiffs contacted North Pacific about filing a claim, they were told that their fire insurance policy did not provide for cost of replacement coverage. Plaintiffs believed that they were entitled to such coverage, and hired defendant attorney to pursue their purported entitlement to cost of replacement benefits.
Defendant submitted a proof of loss form to North Pacific, claiming $285,000 — the estimated cost of repairing the building — as the loss. North Pacific rejected that claim of loss, and sent plaintiffs a check for $82,890.60, which represented the appraised actual cash value of the building, $70,000, plus the cost of debris removal, $12,890.60. Plaintiffs refused to accept that amount.
Under the terms of plaintiffs’ policy, as well as under ORS 742.240,
Plaintiffs brought a legal malpractice action against defendant based on his failure to file a timely action against North Pacific. They alleged that if defendant had pursued their claim for replacement cost benefits promptly, North Pacific would have become legally obligated to pay such benefits for their fire loss. Plaintiffs sought damages of $176,947.08 which, they alleged, represented the difference between the estimated cost of repairing their building and the building’s actual cash value.
At trial, plaintiffs presented, as evidence of damages, estimates that two construction contractors prepared for North Pacific shortly after the fire. Those estimates set the cost of repairing the building at, respectively, $246,947.08 and $250,311.49. At the close of plaintiffs’ case, defendant moved for a directed verdict, arguing that plaintiffs’ proof of damages was legally insufficient because they had failed to offer evidence that the cash value of the building, if reconstructed, would have been any greater than the amount North Pacific had tendered and acknowledged was due. The trial court agreed, and entered judgment for defendant.
On appeal, plaintiffs readily acknowledge that they did not proffer proof of the “rebuilt cash value” of the four-plex. They contend, however, that that is not the proper measure of damages and that the court erred in testing their proof against that standard. In particular, plaintiffs assert: (1) The proper measure of damages is the cost of putting
Defendant raises two related arguments in response. First, defendant contends, plaintiffs’ claim must fail because the type of damage they pleaded and attempted to prove — i. e., the cost of replacing their four-plex — is not legally cognizable. Moreover, defendant argues that, even if cost of replacement might otherwise be an appropriate measure of damage, plaintiffs failed to satisfy the conditions for recovering such damages. In particular, defendant reasons as follows: (1) Even if defendant had timely filed an action to reform plaintiffs’ insurance policy, and plaintiffs had prevailed in that action, they would not have received a lump sum payment for the total projected cost of rebuilding the four-plex. (2) Instead, they would have obtained a judgment reforming the contract to include an obligation to reimburse expenses actually incurred in repairing the building. (3) Because plaintiffs never rebuilt the building and it is now incapable of being rebuilt, they cannot actually incur replacement expenses and, thus, are not entitled to recover damages approximating reimbursement for such expenses.
The parties agree that the measure of damages in a malpractice action arising from the loss of a viable claim is generally the value of the putative “lost judgment.” See Meiselman, Attorney Malpractice: Law and Procedure § 4.2 (1980); 7 Am Jur 2d, “Attorneys at Law,” § 226; Cf. Ridenour v. Lewis, 121 Or App 416, 419, 854 P2d 1005, rev den 317 Or
Defendant argues:
‘ ‘The value of a reformation decree to plaintiffs is the value of a rebuilt fourplex, not the cost of rebuilding it. Indeed, had defendant negligently burned down the fourplex, plaintiffs still would have been allowed to recover from him only the building’s fair market value, not the cost of repairing it.”
That argument, which is derived from cases involving tor-tious property damage,
The value of the coverage allegedly lost as a result of defendant’s negligence is the measure of the value of the lost judgment and, hence, of plaintiffs’ damages. The value of that coverage is, in turn, the difference between cash value coverage and cost of replacement coverage. Thus, the measure of plaintiffs’ malpractice damages is the value of plaintiffs’ reasonably projected replacement costs minus the amount of the cash value coverage.
Defendant’s position further fails for a second, common sense reason. If defendant were correct, parties in the position of the present plaintiffs would have no recourse against attorneys who negligently failed to pursue claims to reform “cash value” coverage as “replacement cost” coverage. Because such plaintiffs could recover nothing more than cash value, attorneys who negligently failed to pursue such reformation actions would be effectively immunized from liability.
Plaintiffs do not dispute the principle expressed in Higgins. They argue, however, that: (1) But for defendant’s negligence, frustrating successful prosecution of their reformation claim, the four-plex would not have been demolished. (2) If the four-plex had not been demolished, they could have, and would have, repaired the building. And (3) defendant should not be permitted to invoke plaintiffs’ inability to repair the building, which resulted from his own negligence, as a basis for reducing plaintiffs’ damages from the loss of replacement cost coverage.
We agree with plaintiffs that a reasonable jury could conclude from the evidence that, but for defendant’s malpractice, the four-plex would not have been demolished and, particularly, that plaintiffs would have incurred substantial replacement expenses. We also agree that, in these circumstances, defendant cannot invoke the consequences of his malpractice, which prevented plaintiffs from repairing their building, as a basis for reducing his own liability. Accord Anderson v. Allison, 256 Or 116, 121, 471 P2d 772 (1970) (“[W]here the conduct of the defendant has prevented the performance of a contract provision by the plaintiff, [defendant] cannot avail himself of any such failure to perform.”); Gilbert v. California Oregon Power Co., 223 Or 1, 15-16, 353 P2d 870 (1960) (same). Thus, Higgins’s “actual repair” principle does not preclude plaintiffs from recovering damages representing the value of replacement cost coverage.
We conclude that plaintiffs’ proof of cost of replacement damages was sufficient to be submitted to the jury. A reasonable person, viewing plaintiffs’ testimony and the repair estimates prepared for North Pacific in the light most favorable to plaintiffs, could conclude that they suffered damages to the extent of those estimates minus the building’s cash value. The trial court erred in granting defendant’s motion for a directed verdict.
Reversed and remanded.
As amplified below, under “cost of replacement” insurance, the insurer is obligated to reimburse the insured for any amount actually expended for repair or replacement of the insured property.
At the time of the events described, ORS 742.240 imposed a one-year limitation period for fire insurance policy claims. It has since been amended to provide a two-year limitation period. Or Laws 1991, ch 437, § 1.
Plaintiffs later settled with the agency.
Plaintiffs’ calculation of damages is based on the difference between the lower of two repair estimates prepared at North Pacific’s instance ($246,974.08) and North Pacific’s estimate of the building’s actual cash value ($70,000). Plaintiffs’ original $285,000 claim of loss reflects that estimate, plus the cost of reconstructing a damaged skylight that had been omitted from the estimate.
See, e.g., Millers Mut. Fire Co. v. Wildish Const. Co., 306 Or 102, 124, 758 P2d 836 (1988) (proper measure of damage when property is damaged by tort is the diminution in market value caused by the tort).
In defendant’s view, the nature of plaintiffs’ lost coverage is immaterial. It would make no difference whether plaintiffs’ insurance agent had failed to obtain cost of replacement coverage or had failed to obtain cash value coverage. In either case, the measure of damages is the same: cash value.
Defendant contends that if plaintiffs’ insurance policy had been reformed to provide replacement cost coverage, that coverage would inevitably have included that standard limitation. The record supports that contention.
Reference
- Full Case Name
- Josephine CARTER-HOLMES, Lenton Holmes and Allen D. Wilson v. Dennis J. SOUSA
- Cited By
- 1 case
- Status
- Published